Full Question Bank

All 121 420B Practice Questions & Answers

Every question with the correct answer, a full explanation and a key concept — free to read, no account needed.

About this page

This is the complete written list of our free 420B Ironworker (Generalist) practice questions — all 121 of them, with the correct answer marked, an explanation of why it is correct, and a one-line key concept for revision.

Questions are grouped by the occupational standard topic areas used on the exam: Structural Steel Erection, Rigging & Hoisting, Welding & Cutting, Blueprint Reading & Layout, Reinforcing Steel, Safety & Fall Protection, Tools & Equipment.

Reading is useful, but recall is what the exam tests — work through the timed 420B quiz as well, which shuffles the questions and saves the ones you get wrong.

Topics are collapsed so you can find your way around 121 questions. Tap a topic to open it, or search below.

Want these 121 questions offline?
The 420B Complete Question Bank is the same 121 questions with full explanations in one printable PDF — study without a signal.
Get the 420B Question Bank — CA$19 →
Structural Steel Erection 24 questions
Q1easy
What is the purpose of a base plate in a steel column installation?
  • A) To prevent corrosion of the column base
  • B) To allow lateral adjustment after erection
  • C) To hold the anchor bolts
  • D) To spread the column load over the foundation
Correct answer: D
A base plate distributes the concentrated column load over a larger bearing area on the concrete foundation, reducing bearing stress to within allowable limits.
Key concept: Base plate: distributes column point load over bearing area. Size determined by concrete bearing capacity.
Q2easy
A column is being lowered onto its anchor rods. What is the correct practice for the connectors receiving it?
  • A) Steady the base plate by hand so the holes drop over the rods
  • B) Guide it with taglines, hands and feet clear of the base plate
  • C) Slack the load line so the column settles onto the rods freely
  • D) Foot the base plate from the footing to stop it from swinging
Correct answer: B
IHSA's Construction Health and Safety Manual chapter on structural steel erection (Ironwork, M036, 2023 edition) gives two controls for column standing: keep the load line vertical and taut while the column is being stood, and keep hands and feet clear of the base plate while the column is being lowered onto the anchor rods. The base plate is the pinch point. A column landing on four rods can shift sideways in an instant, and a hand steadying the plate or a boot bracing it against the footing is between a plate of several hundred kilograms and hard concrete. Control the piece from a distance with taglines instead. Slackening the load line before the column is stable is the other error in this list: the same chapter directs that the column be stable before the rigging is disconnected, and a slack line lets the piece take charge of itself while the crew is still reaching into the connection.
Key concept: Column standing: keep the load line vertical and taut, control the piece with taglines, and keep hands and feet clear of the base plate as it comes down on the rods. The column must be stable before the rigging comes off. (IHSA M036, Structural Steel Erection: Ironwork.)
Q3medium
When installing high-strength bolts using the turn-of-nut method, what is the first step?
  • A) Install all bolts finger-tight only
  • B) Apply lubricant to all bolt threads
  • C) Bring all bolts to snug-tight first
  • D) Apply full final torque immediately
Correct answer: C
Turn-of-nut requires all bolts in the connection to be brought to the snug-tight condition first (full effort of an ironworker with a spud wrench), then a specified rotation is applied to achieve the minimum pretension.
Key concept: Turn-of-nut sequence: ALL bolts snug-tight first → then apply specified rotation (typically 1/3 to 2/3 turn depending on bolt length).
Q4easy
What does "plumbing up" a steel structure mean?
  • A) Installing the water supply lines before steel is covered
  • B) Applying anti-corrosion primer to exposed steel
  • C) Adjusting columns and beams to vertical and level
  • D) Installing floor deck drainage systems
Correct answer: C
Plumbing up involves checking and adjusting the structure so columns are perfectly plumb (vertical) and beams are level before making final bolted or welded connections.
Key concept: Plumbing up: establishing plumb columns and level beams before final connections — done with theodolite/transit and turnbuckle bracing.
Q5medium
Direct Tension Indicators (DTIs) are small washers with raised bumps. A connection is properly pretensioned when:
  • A) The bumps compress to a specified feeler-gauge gap
  • B) All bumps on the DTI are still fully raised
  • C) The bolt head has been rotated exactly 1/2 turn from snug-tight
  • D) The DTI is cracked and the bumps disappear
Correct answer: A
DTIs work by compressing their raised protrusions as bolt pretension increases. When sufficient tension is reached, the gaps between the protrusions and the contact surface fall below the specified maximum refusal value, verified with a feeler gauge.
Key concept: DTI: bumps compress as bolt is tensioned. Feeler gauge checks that refuse (gap) is below specified value — indicates minimum pretension achieved.
Q6hard
Two structural steel beams are to be connected to a common column. Under Ontario's Construction Projects regulation, how may that connection be made?
  • A) With the first beam's bolts pulled to let the second one in
  • B) As a clipped double connection, or the first beam seated
  • C) With the second beam tack welded until the bolting crew comes
  • D) With both beams sharing one set of bolts through the column
Correct answer: B
Ontario Regulation 213/91, s. 31 (2) allows two arrangements and no others: if two structural steel columns or structural steel beams are connected to a common column or common beam, the connection shall be made using a clipped double connection, or the first column or beam shall be secured in a seated connection. Both arrangements do the same job - the first member keeps support of its own, so hanging the second member does not depend on disturbing what is holding the first. That is what makes the other answers the wrong instinct. Pulling the first beam's bolts to make room takes the support out from under a member that a connector may be standing on. A tack weld is a fit-up aid rather than the connection the drawings call for, and it is not one of the two arrangements the section permits. Running both beams on one common set of bolts leaves the two members depending on the same fasteners, which is the arrangement the section is written to prevent.
Key concept: Double connection, O. Reg. 213/91 s. 31 (2): where two beams or columns are connected to a common member, the connection is made as a clipped double connection, or the first member is secured in a seated connection. Neither arrangement lets the second member be fitted by disturbing what supports the first.
Q7medium
Temporary bracing during steel erection serves which primary purpose?
  • A) To support the weight of the ironworkers on the steel
  • B) To permanently resist wind loads in the finished structure
  • C) To mark the locations where permanent connections will be made
  • D) To stabilize the partial structure against erection loads
Correct answer: D
During erection, the structure is not yet a complete load-resisting system. Temporary bracing stabilizes the partially erected structure against gravity, wind, and erection equipment loads before permanent connections are complete.
Key concept: Temporary bracing: stabilizes structure before permanent connections are complete — the erector is responsible until structure is self-supporting.
Q8easy
A column has just been stood on its anchor rods. What must be in place before horizontal members are hung from it?
  • A) The grout under the base plate poured and cured to full strength
  • B) Nuts and washers on the anchor rods, giving lateral support
  • C) The column's bolt-up and torquing completed at both splices
  • D) A survey confirming the column is plumb within the stated limit
Correct answer: B
IHSA's structural steel chapter is direct about the sequence: columns must have sufficient lateral support, with nuts and washers in place on the anchor bolts, before horizontal members such as grid beams and infill are installed. The nuts and washers, together with any temporary bracing called for in the site-specific steel erection work plan, are what stop the column from being pulled over by the first beam that lands on it. The other three are all real operations, but they come later. Grouting follows plumbing up, not the other way round, because grout is placed once the base plate is at its final elevation. Full bolt-up and torquing follow the erection crew rather than lead it. And plumbing up is done to the frame after a bay of steel is standing, then confirmed against the tolerance in the specification once beams tie the columns together.
Key concept: Sequence: stand the column, get nuts and washers on the anchor rods and any bracing the erection plan calls for, then hang horizontal members. Grouting, plumbing up and final torquing all come afterward. (IHSA M036, Structural Steel Erection: Ironwork.)
Q9medium
Steel floor decking should be laid in what sequence?
  • A) Starting from the centre of the bay and working to the edges
  • B) Starting at the column and working toward the beam midspan
  • C) In whatever order suits the crew that shift
  • D) Outward from the crane or access side
Correct answer: D
Deck is laid working away from the crane or access side, so the crew always advances over deck that is already landed, supported and fastened instead of stepping onto loose sheets or out along bare beams. Beginning in the middle of a bay fails for the same reason - somebody has to cross open steel to get there - and letting the order suit the crew leaves loose sheets lying where people walk. Ontario's O. Reg. 213/91, s. 32 (1) sets the principle the sequence serves: during the construction of a building, temporary or permanent flooring shall be installed progressively as the building is erected. The fastening and loading requirements in s. 32 (2) are written for temporary flooring and are quoted only as such. The IHSA ironworkers' chapter adds the handling that goes with the sequence: bundles are landed on framing members so they are supported well enough to be un-banded without being dislodged, decking is secured so that wind cannot blow it off, and access to the floor where deck is being placed and to the area below it is limited to the workers doing that job.
Key concept: Deck is laid progressively away from the crane or access side, so workers advance over deck that is already landed, supported and fastened, and sheets are secured as they go down. O. Reg. 213/91 s. 32 (1) requires temporary or permanent flooring to be installed progressively as the building is erected; the fastening and loading rules in s. 32 (2) are for temporary flooring.
Q10hard
Open-web steel joists have been landed and both bearing ends attached, but the bridging is only partly installed. What may be placed on them?
  • A) Deck bundles, provided each one is landed over a bearing end
  • B) No construction load at all until the bridging is fully anchored
  • C) Loads up to half of the joists' design capacity may be placed
  • D) Anything the joists were designed to carry, once both ends bear
Correct answer: B
IHSA's structural steel chapter states the rule without qualification: no construction loads on steel joists until all bridging is installed and anchored and all joist-bearing ends are attached. A bare open-web joist is a slender member with almost no lateral stiffness. Its design capacity is a figure that assumes the bridging is there to hold the top chord in line; until it is, the joist can roll or buckle sideways under a fraction of that number. That is why half the design capacity is the wrong instinct - the design capacity is not a valid reference point yet, so no fraction of it is safe either. The same reasoning rules out the deck bundle answer: bundles are exactly the construction load the rule is about, and the same chapter requires them to be landed on fully bolted framing beside a main supporting beam at a column or wall, not on joists that are not yet braced.
Key concept: Open-web steel joists carry no construction load until all bridging is installed and anchored and both bearing ends are attached. The published joist capacity assumes the bridging is in place; before that, the joist's real limit is lateral stability, not strength. (IHSA M036, Structural Steel Erection: Ironwork.)
Q11medium
What is the purpose of shear studs welded to the top flange of a steel beam?
  • A) To attach the metal deck to the beam
  • B) To create composite action with the concrete slab
  • C) To increase the buckling resistance of the top flange
  • D) To provide connection points for safety lanyards
Correct answer: B
Shear studs are welded to the beam top flange and embed in the concrete deck above. They transfer horizontal shear forces between the steel beam and slab, creating composite behaviour that significantly increases beam capacity.
Key concept: Shear studs: create composite beam action by transferring horizontal shear between steel beam and concrete slab.
Q12easy
Ontario's Construction Projects regulation sets special rules for hoisting a "multi-tiered load". What is a multi-tiered load?
  • A) Two or three separately rigged pieces flown one above another
  • B) A bundle of steel pieces banded together and hoisted as one lift
  • C) One heavy piece carried by two cranes working the same pick
  • D) A piece raised in stages and rested on each floor on the way up
Correct answer: A
Ontario Regulation 213/91, s. 103.1 (1) defines a multi-tiered load as two or three individually rigged structural steel pieces that are suspended so that they remain horizontal, aligned vertically, and moved simultaneously by a crane. Each part of that definition disposes of one of the other answers. Individually rigged rules out a banded bundle, and s. 103.1 (2) (a) states that a multi-tiered load shall not contain pieces that are bundled together, while (d) requires each piece to be slung back to the main load hook or master link on its own. Two or three pieces rules out a single piece shared between two cranes, which is a tandem lift with its own plan. Moved simultaneously rules out a piece taken up in stages and set down on the way, which is a series of separate lifts. The section also caps the load at three pieces, forbids one piece supporting another, requires power-controlled lowering, limits a crane to one multi-tiered load at a time, and requires written procedures prepared by an engineer before the operation begins. The IHSA ironworkers' chapter sets the same three-piece maximum, states that bundled loads cannot be lifted, and calls for an engineered, dedicated rigging assembly and a minimum clear distance of 2.1 m between the rigged members.
Key concept: Multi-tiered load, O. Reg. 213/91 s. 103.1: two or three individually rigged structural steel pieces, held horizontal, aligned vertically and moved together by one crane. Never bundled, never one piece supporting another, each piece slung back to the hook on its own, lowered under power, one such load per crane at a time, and covered by written procedures prepared by an engineer before the lift begins.
Q13medium
A "column splice" in a steel structure is located:
  • A) At the beam-to-column connection at each floor level
  • B) At an intermediate height where two column pieces meet
  • C) At the top of the column where the roof beam connects
  • D) At the foundation level where the column meets the base plate
Correct answer: B
A column splice is the joint between an upper column section and the one below it, at a height where a single piece would be impractical to fabricate, ship or handle. It is set above a floor level so the connection can be reached and worked from the floor, clear of the beam-to-column connections, and away from points of maximum stress; the splice elevations for any given job are shown on the erection drawings. That is what separates it from the other three answers, which are all real locations on a column but none of them a splice: the beam-to-column connections at each floor are framing connections, the top of the column is where the roof framing lands, and the foot of the column is the base plate on the anchor rods. Ontario's O. Reg. 213/91 uses the splice as a marker for working height. Section 33 (1), subject to s. 33 (2), says work on a building shall not be carried out higher than the higher of two storeys or the first column splice above the temporary or permanent flooring, and s. 33 (2) allows three storeys where the vertical distance between the tiers of column splices exceeds two storeys. Section 33 (3) takes the section off a worker who is on a scaffold, a worker whose fall would be arrested by a safety net without endangering the worker, and a worker using a fall arrest system attached to the project, so on a job where the crew is tied off to the structure this is not the limit that governs.
Key concept: Column splice: the joint between two column pieces at an intermediate height, set above a floor level for access, clear of the beam-to-column connections and away from points of maximum stress. Splice elevations come from the erection drawings. Ontario's O. Reg. 213/91 s. 33 uses the first column splice above the flooring as a working-height marker, subject to s. 33 (2) and to the exemptions in s. 33 (3).
Q14hard
ASTM F3125 Grade A325 and Grade A490 are the two common high-strength structural bolt grades. Which statement about them is correct?
  • A) A490 requires a higher minimum pretension than A325 does
  • B) A490 may be reused after full pretensioning; A325 may not
  • C) Both require the same minimum pretension at a given size
  • D) A325 is stronger than A490 and used for most connections
Correct answer: A
The higher-strength grade carries the higher pretension. Grade A490 has a minimum tensile strength of 150 ksi against 120 ksi for Grade A325, and because the specified minimum pretension is set at 70 percent of the bolt's minimum tensile strength times its tensile stress area, A490 comes out about a quarter higher at every diameter. The RCSC Specification for Structural Joints Using High-Strength Bolts, the United States bolting specification, tabulates it: a 3/4 in bolt is 28 kips for A325 against 35 kips for A490, 7/8 in is 39 against 49, and 1 in is 51 against 64, with A490 higher in every row. The two grades therefore never share a pretension at a given size, and A325 is the lower-strength grade, so it cannot be the stronger one however often it appears on a job. Reuse runs the opposite way from the idea that the higher-strength bolt can be tightened twice. A pretensioned installation stretches the threads between the nut and the thread run-out into the inelastic range, and A490 bolts are not consistently ductile enough to survive a second pretensioning, so RCSC bars any reuse of A490 and of galvanized or coated bolts of either grade; only a plain-finish A325 heavy hex bolt may be reused in a pretensioned joint, and only with the engineer of record's approval. Retightening a bolt that loosened while its neighbours were installed is touching up, not reuse. On Canadian work the design, installation and inspection of bolted joints are governed by CSA S16 for buildings and by CSA S6 or the provincial specification for road bridges; those standards adopt many RCSC provisions but not all of them, and a project specification can be stricter still - Alberta Transportation's Standard Specifications for Bridge Construction has every bolt tensioned once only and permits no reuse at all.
Key concept: A490 (150 ksi) versus A325 (120 ksi): minimum pretension is 70 percent of tensile strength times tensile stress area, so A490 pretension runs about 25 percent higher at every diameter (RCSC Table 5.2: 3/4 in 28 vs 35 kips; 7/8 in 39 vs 49; 1 in 51 vs 64). Reuse: A490 and any galvanized or coated bolt are never reused; a plain-finish A325 heavy hex bolt may be reused in a pretensioned joint only with the engineer of record's approval; touching up a bolt loosened by its neighbours is not reuse. In Canada bolted joints are governed by CSA S16 (buildings) and CSA S6 or the provincial specification (bridges), which adopt RCSC selectively; Alberta's bridge specification allows no reuse of any bolt.
Q15medium
When erecting steel in cold weather (below -20°C), what is the primary concern?
  • A) Weld fumes become more toxic in cold air
  • B) High-strength bolts become over-tensioned due to thermal contraction
  • C) Crane hydraulic systems perform better and can lift more
  • D) Steel becomes brittle and prone to impact fracture
Correct answer: D
Structural steel, especially older or high-strength grades, becomes increasingly brittle and susceptible to impact fracture at low temperatures. Impact loads from erection (drops, hammer blows) can initiate brittle fracture.
Key concept: Cold weather: steel brittleness increases. Avoid impact loads; preheat may be required for welding. Crane capacity also decreases in extreme cold.
Q16easy
What is the purpose of "levelling nuts" used with anchor bolt assemblies?
  • A) To provide the required pretension on the anchor bolt
  • B) To set the base plate elevation before grouting
  • C) To lock the anchor bolt to the foundation
  • D) To prevent the column from rotating during erection
Correct answer: B
Levelling nuts under the base plate allow the ironworker to adjust the plate precisely to exact elevation (plumb and level) before the column is grouted into final position.
Key concept: Levelling nuts: allow precise base plate elevation adjustment before grouting. Removed or incorporated into final grout as per design.
Q17medium
Tension control (TC) bolts are identified by a splined end. The installation is complete when:
  • A) The direct tension indicator gap measures zero
  • B) The bolt has been torqued to the specified value with a calibrated torque wrench
  • C) The splined end shears off during installation
  • D) The bolt head has been rotated 1/2 turn from snug-tight
Correct answer: C
TC bolts have a breakneck groove at the splined end. When minimum pretension is achieved, the torque reaction causes the spline to shear off cleanly, providing visual verification that the required minimum pretension has been reached.
Key concept: TC bolt: splined end shears off when minimum pretension is reached — provides self-indicating installation verification.
Q18hard
A steel erection drawing shows "ASTM A36" for the beam material. What is the minimum yield strength of A36 steel?
  • A) 250 MPa (36 ksi)
  • B) 550 MPa (80 ksi)
  • C) 345 MPa (50 ksi)
  • D) 414 MPa (60 ksi)
Correct answer: A
ASTM A36 has a minimum yield strength of 250 MPa (36 ksi) and a tensile strength of 400–550 MPa (58–80 ksi). Its usual Canadian counterpart grade, CSA G40.21 300W, is a stronger steel at Fy = 300 MPa (44 ksi). Because 300W is stronger, it is generally accepted where A36 is called for; the substitution does not run the other way, and A36 is not an automatic replacement for 300W.
Key concept: A36 steel: Fy = 250 MPa (36 ksi), Fu = 400 MPa minimum. Most common structural steel in older North American buildings.
Q19medium
What does the term "camber" mean when applied to a structural steel beam?
  • A) The vertical angle of the beam connection at the column
  • B) The horizontal curvature of the beam due to lateral wind load
  • C) A pre-set upward bow built into the beam to compensate for deflection under load
  • D) The distance between the top and bottom flanges of the beam
Correct answer: C
Camber is a deliberate upward curve fabricated into a beam so that, once the dead load is in place, the beam deflects down to an approximately level position. It is normally set for all or part of the calculated dead-load deflection, not for live load. Common in long-span or heavily loaded beams.
Key concept: Camber: intentional upward bow in beam that counteracts deflection under dead load (often only part of it), so the beam sits approximately level once the dead load is applied.
Q20hard
A beam has been landed in its connection and the connectors are ready to cut it loose from the crane. What has to be in that connection at that moment?
  • A) Enough bolts to stop rotation, drawn up wrench-tight
  • B) Two bolts run on by hand so the beam can still be shifted
  • C) One bolt wrench-tight and a drift pin in a second hole
  • D) Every bolt run in and torqued to the design drawings
Correct answer: A
IHSA's ironworker chapter puts it in one line: before being cut loose, the beam must be bolted so that it will not rotate, at least two or more bolts should be put in position depending on the engineer's requirements, and a drift pin or a wrench placed in a hole is not to be relied on. Two things therefore have to be true at that moment, and the count is only one of them. Enough fasteners have to be in to take rotation out of the connection, and IHSA's structural steel erection guide supplies the condition that goes with them: bolted and temporary connections are to be wrench-tight, and are torqued later, to the design specification, during bolt-up and detail work. Bolts run on by hand leave the beam free to move in the connection, which is the state the rule exists to prevent. A drift pin is a tool for drawing holes into line; it carries no load and can walk out, which is why the guidance names it as the thing not to trust. Waiting for the whole connection to be torqued keeps the crane tied to one beam - the bolting-up crew follows the erection crew and installs the remaining bolts afterward. How many bolts is not the connector's own call: the number comes from the engineer's requirements and the erection plan, and the same guide sets one bolt per connection for diagonal bracing unless the structural design engineer specifies otherwise, which is a different member and a different number.
Key concept: Before the beam is cut loose: enough fasteners in the connection that the beam cannot rotate, drawn up wrench-tight, with the count coming from the engineer's requirements and the erection plan - IHSA's ironworker chapter gives at least two or more bolts as the practical floor. Torquing to the design specification comes later, during bolt-up, and the bolting-up crew follows the erection crew. A drift pin or a wrench in a hole is a tool for lining up holes, never a connection. Diagonal bracing is the separate case, at one bolt per connection unless the structural design engineer says otherwise.
Q21medium
An anchor rod at a column base is 25 mm out of position. Which statement about correcting it in the field is correct?
  • A) Bending it cold with a rod bender restores its design strength
  • B) Heating or flame-cutting the rod changes its strength properties
  • C) Cutting it off and welding on an extension is a standard field fix
  • D) Reaming the base plate hole oversize keeps the rod's capacity
Correct answer: B
Heat is the thing to be careful of. An anchor rod's strength comes from its steel chemistry and, in the higher grades, from heat treatment; taking a torch to it drives the material through temperatures that alter those properties, and flame-cutting leaves a heat-affected zone and a reduced section in a member designed to carry tension. Neither effect is visible afterward, which is what makes it dangerous - the rod looks fine and is no longer the rod the engineer designed. That is why heating and cutting are not the erector's call, and why any remedy for a misplaced rod comes back with engineering direction. The other three are the field fixes people reach for and none of them is sound. Cold bending does not restore design strength; it works the steel, leaves residual stress at the bend and puts a permanent kink where the load path wanted a straight bar. Welding an extension onto a cut rod assumes the rod steel is weldable and that a field splice can carry the design tension, and neither can be assumed. Reaming the plate hole oversize changes how load transfers between rod and plate and can leave the rod bearing on very little, which is why oversized holes at base plates carry their own plate washer requirements.
Key concept: Anchor rod out of position: heating or flame-cutting alters the rod's strength properties and leaves damage that cannot be seen, so it is never the erector's remedy. Cold bending does not restore design strength, a welded-on extension is not a standard fix, and reaming the plate hole oversize changes the load transfer. A misplaced anchor rod is an engineering item; the erector's job is to stop, not to invent a repair.
Q22medium
An ironworker is erecting a multi-storey steel frame and notices that a column is out of plumb by 25mm in a 6m height (approximately 1:240 ratio). The spec tolerance is 1:500. What action is required?
  • A) Tolerance applies only to the final structure — proceed and adjust at the end
  • B) No action — 25mm is within the typical ±50mm erection tolerance
  • C) Column is within tolerance — 1:240 is acceptable for multi-storey columns per CISC
  • D) Column is out of tolerance — must be plumbed and restrained before the next tier is erected
Correct answer: D
CISC erection tolerances for column plumbness: typically ±1:500 (1mm per 500mm height). At 6m height, allowable deviation is 6000/500 = 12mm. The measured 25mm deviation exceeds this. Out-of-plumb columns must be corrected before adding more load (next tier) because each additional tier multiplies the eccentricity and increases the risk of progressive collapse. Use come-alongs or guy wires to plumb the column.
Key concept: Column plumb tolerance: typically ±1:500 per CISC. Correct out-of-plumb columns BEFORE adding additional loads or erecting higher tiers.
Q23hard
During a concrete pour on a steel-framed floor, an ironworker sees the decking buckling and the frame deflecting far more than expected. What is the correct immediate action?
  • A) Stop the pour, clear the area below and notify the engineer
  • B) Relocate the pump hose to spread the load and carry on pouring
  • C) Speed up the pour so the load sits on the deck for less time
  • D) Treat it as normal elastic deflection and keep placing concrete
Correct answer: A
Unexpected movement during a pour is a warning of a developing failure, and at that moment the cause is not yet known. It could be shoring or falsework under-designed or kicked out, concrete piling up in one place instead of being spread, deck load beyond what the frame was designed to carry, or a connection that has slipped. Working out which one it is while standing on the deck with concrete still going on is guesswork, so the immediate action does not wait on the diagnosis: stop placing concrete, get everyone out from under and beside the affected bay, and call the engineer of record before anything else is done. Moving the pump hose acts on one guess while people remain under a structure that is already behaving abnormally, pouring faster adds load faster, and calling it normal elastic deflection ignores the buckling decking, which elastic deflection does not produce.
Key concept: Unexpected deflection or buckling during a pour: stop the pour, clear the area under and beside it, and get the engineer of record. Never keep placing concrete on a guess about the cause, and never speed up to outrun it.
Q24medium
An ironworker is placing shear studs on a composite steel beam with a drawn-arc stud gun. Studs from the run are bend tested as a check on weld quality. One stud is bent about 30 degrees off its axis and a crack opens in the weld at the base of the stud. What is the required action?
  • A) Cut out and re-weld only the cracked stud base
  • B) Reject the beam and replace every stud on it
  • C) Accept it - minor bend-test cracks are normal
  • D) Replace the stud and raise the test rate
Correct answer: D
A crack in the weld during a bend test is a failed test, not a normal result. Bending the stud off its axis loads one side of the weld collar in tension, and a sound drawn-arc weld takes that without cracking. A crack means the weld metal or the fusion at the base is unsound - commonly from moisture, paint, mill scale or oil on the flange, a damaged or damp ferrule, or wrong current or plunge time. The response is to replace the failed stud, removing it and making good the base metal before welding a replacement with corrected settings, and to widen the sample so the studs put down alongside it under the same conditions are proved as well. Dressing and re-welding the base of a suspect stud proves nothing about that stud, and one failure does not condemn every stud on the beam. How many studs are tested, and how far the sampling is widened after a failure, come from the project specification and the welding inspection procedure for the job.
Key concept: Shear stud quality control: bend the stud off its axis; a crack at the weld base is a failed test, not an acceptable result. A failure means replacing that stud - remove it, make good the base metal, re-weld with corrected settings - and widening the sample so the studs welded alongside it under the same conditions are proved as well. How many studs are tested, and how far the sampling widens after a failure, are set by the project specification. Common causes of an unsound stud weld: surface contamination, moisture, wrong current or plunge time, damaged ferrule.
Rigging & Hoisting 23 questions
Q25easy
What is the Working Load Limit (WLL) of a rigging component?
  • A) The maximum load the component has ever been tested to
  • B) The minimum breaking strength of the component
  • C) The load at which the component begins to permanently deform
  • D) The maximum load it may lift in normal service
Correct answer: D
WLL (also called Safe Working Load) is the maximum load a rigging component is authorized to lift under normal working conditions, accounting for the safety factor from the breaking strength.
Key concept: WLL = maximum authorized lifting load. NOT the same as breaking strength. Never exceed WLL.
Q26medium
A wire rope sling is rated for a working load limit (WLL) of 10,000 kg in a straight-line (vertical) hitch, and the sling tag shows no separate choker rating. What is the effective WLL in a choker hitch at an angle of choke of 120° or greater?
  • A) 8,000 kg — choker hitch reduces capacity by 20%
  • B) 5,000 kg — choker hitch reduces capacity by 50%
  • C) 10,000 kg — choker hitch does not reduce capacity
  • D) 7,500 kg — choker hitch reduces capacity by 25%
Correct answer: D
ASME B30.9-2021, para. 9-2.10.1(d): when the choker hitch rating is not identified on the sling, the choker hitch rating for single-leg and bridle wire rope slings is 75% of the sling's straight-line hitch rating (70% for cable-laid slings). So 10,000 kg × 0.75 = 7,500 kg — a 25% reduction, caused by the bending and pinching of the rope at the choke point. That 75% figure holds only at an angle of choke of 120° or greater: para. 9-2.10.1(e) sends you to Table 9-2.10.1-1 for smaller angles, which gives 87% of the choker rating at 90°–120°, 74% at 60°–89°, 62% at 30°–59°, and 49% at 0°–29°. Although B30.9 is an American standard, it governs Canadian work because occupational health and safety regulation adopts it by reference — Alberta OHS Code Part 21, s.297(1) requires wire rope, alloy steel chain, synthetic fibre rope, metal mesh and synthetic fibre slings manufactured on or after July 1, 2009 to meet ASME B30.9. If the sling tag carries its own choker rating, use the tag.
Key concept: Choker hitch on a WIRE ROPE sling: 75% of the straight-line (vertical) rating — a 25% reduction — where the tag shows no choker rating and the angle of choke is 120° or more (ASME B30.9-2021 para. 9-2.10.1(d); cable-laid slings 70%). Below 120°, reduce further per para. 9-2.10.1(e) and Table 9-2.10.1-1: 87% of the choker rating at 90°–120°, down to 49% at 0°–29°. Basket hitch = 2× vertical WLL at 90°, subject to D/d. Single vertical = 1× WLL. The 75% factor is wire rope only — alloy steel chain (9-1.10.1(d)) and synthetic webbing (9-5.10.1(d)) choke at 80%, metal mesh (9-3.10.1(d)) at 100%, synthetic rope (9-4.10.1(d)) at 75%. B30.9 is adopted by reference into Canadian law: Alberta OHS Code Part 21, s.297 requires slings made on or after July 1, 2009 to meet ASME B30.9-2006. Always read the sling tag first.
Q27medium
Alberta's OHS Code limits how heavily rigging may be loaded. What changes when the rigging is raising or lowering a worker rather than material?
  • A) The limit tightens to 10 percent of the breaking strength
  • B) The limit stays the same, but a second sling must be added
  • C) The limit loosens, because a person weighs far less than steel
  • D) The limit is set by the crane operator for that particular lift
Correct answer: A
Alberta OHS Code (AR 191/2021) s. 292 (1) sets two different ceilings on the same rigging. Under (a), rigging must not be subjected to a load of more than 10 percent of the breaking strength of the weakest part of the rigging if a worker is being raised or lowered. Under (b), the figure for everything else is 20 percent of the ultimate breaking strength of the weakest part. Twenty percent is a design factor of 5 to 1; ten percent is 10 to 1. So the same sling that may take 2,000 kg of steel may take only 1,000 kg when the load is a person. The reason is not that people are heavier - it is that a rigging failure under material is a dropped load and a rigging failure under a worker is a fatality, so the margin is doubled. Nothing in the section lets the operator set the number for a particular lift, and adding a second sling changes the load carried by each leg, not the percentage each leg is permitted to take.
Key concept: Alberta OHS Code s. 292 (1): rigging is limited to 20 percent of the ultimate breaking strength of its weakest part for general lifting, a design factor of 5 to 1, but only 10 percent when a worker is being raised or lowered, which is 10 to 1. Doubling the margin for personnel is a fixed rule, not a judgement call on the day.
Q28easy
During a crane lift, what is the purpose of a tagline?
  • A) To control the rotation and swing of the load
  • B) To measure the length of the lift path
  • C) To provide an extra rigging connection in case the main sling fails
  • D) To attach the load to the crane hook
Correct answer: A
Taglines allow workers to guide and control a suspended load from a safe distance, preventing rotation and swing without placing workers directly under or near the load.
Key concept: Tagline: controls load rotation and swing from a safe distance. Must be long enough to keep workers outside the swing radius.
Q29hard
A wire rope sling is about 300 mm too long for the pick and the rigger wants to take up the slack. Under ASME B30.9, what is permitted?
  • A) Tie a knot in the sling body to take up the extra length
  • B) Only a method approved by the maker or a qualified person
  • C) Fit two wire rope clips to form a temporary shortened eye
  • D) Put a twist in the sling and choke it to take up the slack
Correct answer: B
ASME B30.9-2021, section 9-2.10.4: "(a) Slings shall be shortened or adjusted only by methods approved by the sling manufacturer or a qualified person. (b) Slings shall not be shortened or lengthened by knotting or twisting, or by wire rope clips." All three of the rejected answers are named in that one clause, and they fail for the same physical reason: each puts a sharp local bend or a crushing grip into a rope whose rated load assumes a smooth, unrestrained body. A knot can cut the rope's strength roughly in half at the knot. A twist unbalances the lay and works the strands against one another. Wire rope clips are a termination fitting for a dead end, not a length adjuster in the middle of a loaded sling body, and the same standard bars using them for this. The proper answers are the ones the standard points to: a shorter sling, a sling with a proper adjustable fitting, or a shortening method the manufacturer publishes for that sling. B30.9 is not merely an American reference here - Alberta OHS Code s. 297 (1) requires slings manufactured on or after July 1, 2009 to meet it, and s. 295 states that a worker must not use rigging that does not comply with that Part.
Key concept: Shortening a sling: ASME B30.9 section 9-2.10.4 allows only methods approved by the sling manufacturer or a qualified person, and expressly bars shortening or lengthening by knotting, twisting, or wire rope clips. Each of those puts a sharp bend or a crushing grip into a body whose rated load assumes neither. Adopted into Canadian law by provincial regulation, for example Alberta OHS Code s. 297 (1).
Q30medium
No manufacturer's specification can be found for a winding drum that a wire rope will spool onto. What minimum drum diameter should be used?
  • A) 6 times the rope diameter
  • B) 12 times the rope diameter
  • C) 20 times the rope diameter
  • D) 30 times the rope diameter
Correct answer: C
The binding rule is the manufacturer's figure: Alberta's OHS Code s.302(1) requires that the wire ropes, sheaves, spools and drums used in rigging have a diameter of not less than the diameter specified by the manufacturer for that use. Where no specification can be found, Alberta's published explanation guide to Part 21 gives the working minimum — unless otherwise specified by the manufacturer, the diameter of winding drums should not be less than 20 times the diameter of the rope, which reduces the likelihood of weakened rope caused by excessive bending stresses. Six or twelve times the rope diameter bends the rope far harder than it is built to take; thirty times is generous but is not the published minimum. Bending fatigue, not overload, is what usually kills a rope. Note that there is no single number for a rope running over a sheave: the minimum varies with rope construction, so read the rope manufacturer's table rather than carrying one figure in your head.
Key concept: D:d ratio = drum or sheave diameter divided by rope diameter. Alberta OHS Code s.302(1): not less than the diameter the manufacturer specifies. With no specification, the Part 21 explanation guide gives 20 times the rope diameter for winding drums. Smaller D:d means tighter bending, more stress and faster fatigue; the sheave minimum varies with rope construction.
Q31easy
When installing wire rope clips (U-bolt clips), which way do the U-bolts face?
  • A) Either direction is acceptable if the clips are torqued
  • B) U-bolts on the dead end, saddle bears on the live end
  • C) U-bolts face the direction the load will travel in
  • D) U-bolts on the live (load-bearing) end, saddle on the dead end
Correct answer: B
The saddle, not the U-bolt, must bear on the live rope end, because the U-bolt creates a stress concentration that would crush and weaken the load-bearing part of the rope. Alberta's OHS Code s.300(1) puts it in those words: the U-bolt section of the clip must bear on the short or dead side of the rope, and the saddle of a clip must bear on the long or live side. "Never saddle a dead horse" is the memory hook. Correct torque does not make the orientation optional, and the direction the load travels has nothing to do with it.
Key concept: "Never saddle a dead horse" — saddle on the live (load-bearing) rope, U-bolt on the dead end (Alberta OHS Code s.300(1)). The number of clips is set by rope diameter, not a fixed count: Schedule 5 requires 2 clips up to 11 mm, 3 at 12 to 16 mm, 4 at 19 to 25 mm, 5 at 29 to 32 mm, 6 at 38 mm, 7 at 44 mm and 8 at 50 mm, spaced about 6 rope diameters centre to centre.
Q32medium
A screw-pin shackle is used where:
  • A) Permanent or semi-permanent rigging connections are needed
  • B) A higher rated capacity is needed than a bolt-type shackle offers
  • C) High side-loading conditions exist during the lift
  • D) The rigging will be frequently removed and reattached
Correct answer: D
A screw-pin shackle is opened and closed by hand without tools, which is exactly what temporary or frequently changed rigging needs. It is not rated higher than a bolt-type shackle of the same size and grade — both carry the same working load limit, because the rating comes from the body size and the material, not from how the pin is retained. Side loading does not select a screw-pin either; side loading derates any shackle and the manufacturer's reduction has to be applied. Where the shackle stays in place for a long period, or where the sling or the load can turn against the pin and back it out, the bolt-type shackle with a nut and cotter pin is the correct choice; BC's OHS Regulation s.15.11(2) also requires that the pin of a screw-pin shackle be wired or otherwise secured against rotation in any application that may cause the pin to loosen, and s.15.11(1) requires every shackle pin to be secured against dislodgment.
Key concept: Screw-pin shackle: opened and closed by hand, for temporary or frequently changed rigging. Bolt-type (safety) shackle with nut and cotter pin: for long-term installation or wherever the pin could turn and unscrew. Same size and grade means the same WLL either way — the pin type is about security, not capacity. BC OHSR s.15.11(2): a screw-pin shackle's pin must be secured against rotation where the application may loosen it.
Q33hard
Before a critical lift, the rigger calculates the load center of gravity (CG). If the CG is NOT centered between the sling attachment points, what will happen?
  • A) The load will spin in the direction of the CG offset
  • B) The lift will be stable because slings self-equalize
  • C) The slings will slip to equalize the load automatically
  • D) The load will tilt toward the heavier end
Correct answer: D
When the CG is offset, the load tilts toward the heavier side. The sling leg closer to the CG — the one over the heavier end — carries a disproportionately higher load, which must be accounted for in sling selection.
Key concept: Off-center CG: load tilts toward heavier end; that sling leg carries more load. Use an equalizer beam or adjust pick points to balance.
Q34medium
Which crane hand signal means "STOP"?
  • A) Arm extended, palm facing down, moving arm side to side
  • B) One arm raised, rotating at the elbow
  • C) Both arms raised above head
  • D) Arm extended, palm facing the crane operator, fist closed
Correct answer: A
The universal crane signal for STOP is arm extended horizontally with palm facing down, moved side to side. EMERGENCY STOP uses both arms in this position.
Key concept: Crane STOP signal: arm extended, palm down, move side to side. In an emergency, ANYONE on site can give a stop signal and the operator MUST stop.
Q35easy
What does "two-blocking" mean on a crane?
  • A) Installing two taglines on a single load
  • B) Using two sling blocks to double the crane capacity
  • C) Locking two rigging components together to prevent separation
  • D) The hook block contacts the boom tip sheave
Correct answer: D
Two-blocking occurs when the lower load block — the hook block or the overhaul ball — is drawn up until it strikes the upper block at the boom tip, the boom tip sheave assembly. With no travel left, the hoist drum keeps pulling against a rope that cannot move: the rope can part or the fitting can fail, and the load falls. It has nothing to do with taglines, with locking rigging components together, or with capacity, which is not increased by adding blocks in this sense.
Key concept: Two-blocking: hook block contacts boom tip → catastrophic failure risk. Modern cranes have anti-two-block devices. Operator must watch for this.
Q36medium
Synthetic web slings must be removed from service when:
  • A) There are cuts, tears, or chemical burns visible
  • B) Colour fading or minor surface abrasion is visible
  • C) Only when the rated capacity tag is illegible
  • D) The sling has been used for more than 500 lifts
Correct answer: A
A synthetic web sling comes out of service for damage that has cut, burned, melted or abraded the fibres or the stitching. Alberta's OHS Code s.305(2) requires permanent removal if part of the sling is melted, charred or damaged by chemicals, if stitches in load-bearing splices are broken or worn, or if end fittings are excessively pitted or corroded, cracked, distorted or broken. Section 305(1) adds the measured limits: an edge cut longer than the web thickness, or abrasion deeper than 15 percent of the webbing thickness taken across all plies. Colour fading and light surface scuffing are not by themselves removal criteria. No regulation retires a sling on a lift count. An illegible or missing capacity tag does require removal, but it is one criterion among many rather than the only one.
Key concept: Remove a synthetic web sling for cuts, tears, melting or charring, acid or caustic damage, broken or worn stitching in load-bearing splices, damaged end fittings, or a missing or illegible tag. Measured limits (Alberta OHS Code s.305(1)): edge cut longer than the web thickness; abrasion deeper than 15 percent of the webbing thickness. Do not expose a synthetic web sling above 82°C unless the manufacturer permits (BC OHSR s.15.53). Synthetic slings give less warning before failure than wire rope.
Q37hard
A load weighs 8,000 kg. One sling is rigged under it as a basket hitch, with both legs running to the hook at 45° from horizontal. What is the approximate tension in each sling leg?
  • A) 8,000 kg
  • B) 5,660 kg
  • C) 11,310 kg
  • D) 4,000 kg
Correct answer: B
One sling rigged as a basket puts two legs under the hook, so each leg carries half the load vertically - 4,000 kg - and the sling angle adds to that. At 45° from horizontal the vertical part of a leg's tension is T x sin 45°, so T = 4,000 ÷ 0.707, about 5,660 kg in each leg. Count the legs before touching the trigonometry, because that is where a basket goes wrong. A basket hitch is the sling passed under the load with both ends brought up to the hook, which is two legs from one sling; a second sling basketed alongside it would make four, and the share per leg would halve again. Stopping at 4,000 kg leaves the angle out altogether - that figure is only the vertical share each leg has to carry, and the true pull along the sling is 41 percent higher than that share. Putting the whole 8,000 kg into one leg ignores that there are two of them. Applying the angle factor to the full load instead of to the half load gives about 11,310 kg, which is twice the real tension. What the sling body, the fittings and the hook actually see is the tension along the leg, not the vertical share, so it is the tension that has to sit inside the rated capacity of the hitch.
Key concept: A basket hitch made with one sling has two legs, so each leg's vertical share is half the load. At 45° from horizontal the pull along the leg is that share divided by sin 45°, which is 41 percent more than the share itself: 8,000 kg gives a 4,000 kg vertical share and about 5,660 kg of tension in each leg. Count the legs first, then apply the angle, and rate the hitch on the leg tension rather than on the vertical share.
Q38medium
What is a spreader beam used for in rigging?
  • A) To counterbalance the weight of the crane boom
  • B) To measure the balance point of a long structural member
  • C) To distribute the load over several pick points
  • D) To spread two crane boom sections for tandem lifts
Correct answer: C
A spreader beam is a below-the-hook lifting device that widens the pick points on a load. The beam carries the spread as compression along its own length, so the sling legs hang nearer to vertical and no horizontal squeeze is passed into the load itself. It does not counterbalance anything on the crane, it does not find a balance point, and it has nothing to do with boom sections. Do not confuse it with an equalizer beam, which is a different device: an equalizer beam pivots at a centre point to share load equally between two hoist lines or two cranes. Alberta's OHS Code s.297(2) puts below-the-hook lifting devices other than slings under ASME B30.20, and s.297(3) and (4) allow a spreader bar to be labelled with its rated capacity by a uniquely numbered capacity data sheet. BC's OHS Regulation requires the working load limit of a spreader bar to be certified by a professional engineer or established by the manufacturer (s.15.58), requires a nameplate (s.15.59), and counts the device as part of the lifted load (s.15.60).
Key concept: Spreader beam: widens the pick points, carries the spread as compression, keeps horizontal squeeze out of the load and holds the sling legs nearer vertical. An equalizer beam is a different device — it pivots to share load between two hoist lines or two cranes. A spreader bar counts as part of the lifted load and must carry a certified or manufacturer-established WLL (BC OHSR s.15.58 and s.15.60).
Q39easy
Who is responsible for ensuring a lift plan exists for a critical lift?
  • A) The crane manufacturer's representative
  • B) The certified crane operator only
  • C) The rigging foreman and ironworker in charge
  • D) The project's structural engineer only
Correct answer: C
The rigging crew (foreman/competent rigger) and the ironworker in charge of the lift, in coordination with the site supervisor, are responsible for preparing or implementing the lift plan for critical lifts. The engineer may provide structural input.
Key concept: Critical lift plan: prepared by a competent rigger/supervisor. Includes load weight, CG, sling sizes, crane capacity, ground conditions, and exclusion zone.
Q40hard
A 6x19 IWRC wire rope has a catalogue breaking strength of 50,000 kg. Applied with a safety factor of 5, the WLL is:
  • A) 25,000 kg
  • B) 250,000 kg
  • C) 5,000 kg
  • D) 10,000 kg
Correct answer: D
WLL = breaking strength ÷ design factor = 50,000 ÷ 5 = 10,000 kg. Five is the right divisor here because BC's OHS Regulation Table 15-1 sets a minimum design factor of 5 for conventional wire rope, for wire rope slings and for wire rope sling fittings. Dividing by 2 gives 25,000 kg, multiplying instead of dividing gives 250,000 kg, and a 10:1 factor gives 5,000 kg — none of those is the design factor for wire rope. Five is not a universal figure: the same table sets 4 for alloy steel chain slings and chain fittings, s.15.6(3) requires 10 for any rigging assembly used to support workers, and s.15.7 allows 2.5 to 3.5 for wire rope on a mobile crane depending on the line and on whether the crane is being erected. Alberta's OHS Code s.292.1(1) likewise rates running lines at 3.5 to 1, tugger lines and blocks and pendant or guy lines at 3 to 1, and winch lines at 2 to 1. Read the WLL off the tag whenever the component carries one; dividing breaking strength reproduces the tag only when you have used the design factor that actually governs that component.
Key concept: WLL = breaking strength ÷ design factor. 50,000 ÷ 5 = 10,000 kg. The divisor depends on the component and the use: BC OHSR Table 15-1 gives 5 for wire rope and wire rope slings, 4 for alloy steel chain slings and chain fittings, and s.15.6(3) requires 10 for any rigging assembly supporting workers. Read the tag when the component carries one.
Q41medium
What does IWRC stand for in wire rope classification?
  • A) Independent Wire Rope Core
  • B) Individual Wire Rope Core
  • C) Inner Wound Rope Configuration
  • D) Internal Wire Reinforced Construction
Correct answer: A
IWRC (Independent Wire Rope Core) is a wire rope core made from a separate small wire rope instead of fibre. It resists crushing on drums and sheaves far better than a fibre core and carries a somewhat higher breaking strength, so the rope of the same size and grade is rated for a higher working load limit.
Key concept: IWRC: Independent Wire Rope Core — stronger and much more crush resistant than a fibre core (FC) rope, so it is preferred where the rope is crushed on drums and sheaves, where loads are heavy, and at elevated temperature. Rotation is a separate property: a load free to spin on a single part of line needs rotation-resistant construction (19x7, 35x7), not IWRC.
Q42hard
A rigid steel weldment is picked on a four-leg bridle sling. Under British Columbia's OHS Regulation, the working load limit of the whole sling is limited to the working load limit of how many of its legs?
  • A) Three of them, whichever three are chosen
  • B) All four, since the four legs share the load
  • C) Two of them, the pair on the same diagonal
  • D) Whatever number a professional engineer sets
Correct answer: A
WorkSafeBC's OHS Regulation s. 15.33 (2) is one sentence: the working load limit of a sling with more than three legs is limited to the working load limit of any three legs of the sling. A fourth leg is allowed on the hook; it simply cannot be counted. The mechanics behind that are worth carrying to any jurisdiction. Four legs holding one rigid piece are statically indeterminate - there are more supports than the statics of the lift can define - so which legs are actually tight is decided by millimetres of leg length and by exactly where the pick points sit, not by symmetry. Nothing about the arrangement guarantees that all four come up tight together, so adding four leg capacities describes a lift that may not happen. The section does not stop at two, though: three is the cap it states. An engineer's stamp is the answer people reach for when a rule looks severe, but this subsection sets the cap itself and does not hand the number to anyone to reset. Two further limits ride along in the same section: the working load limit of no individual component of the assembly may be exceeded (15.33 (1)), and the load carried by any single leg of a bridle must not exceed the working load limit of that leg (15.33 (3)).
Key concept: WorkSafeBC OHS Regulation s. 15.33 (2): a sling with more than three legs is rated at the working load limit of any three of its legs, so the fourth leg on a bridle adds no capacity. Four legs on a rigid load are statically indeterminate, and small differences in leg length decide which ones take the pull. Also in the same section: no component of the assembly may be loaded past its own working load limit (15.33 (1)), and no single leg of a bridle may be loaded past its working load limit (15.33 (3)).
Q43hard
An ironworker inspects a 6×19 IWRC wire rope sling before a critical lift and finds 11 randomly distributed broken wires in one rope lay. What action should be taken?
  • A) Tag the sling for monitoring and continued use
  • B) Remove the sling from service immediately
  • C) The sling may be used — the limit is 20 broken wires per rope lay
  • D) The sling may be used if the broken wires are not load-bearing
Correct answer: B
ASME B30.9, para. 9-2.9.5(b)(1): a strand-laid or single-part wire rope sling must be removed from service at 10 randomly distributed broken wires in one rope lay, or 5 broken wires in one strand in one rope lay. Eleven randomly distributed breaks exceeds that limit, so the sling comes out of service immediately — tag it, segregate it so it cannot be picked up again, and report to the rigger-in-charge. Note what the standard does not say: B30.9 sets no broken-wire limit keyed to rope construction, so there is no separate 6×19 or 6×36 figure. Classification governs the minimum clear length of rope between splices (para. 9-2.3.2), not the wire count. The one construction that changes the count is the cable-laid sling, at 20 broken wires per lay. B30.9 is not merely an American reference here — it is adopted by regulation: Alberta OHS Code Part 21, s.297(1) requires wire rope slings manufactured on or after July 1, 2009 to meet ASME B30.9, and s.306 adds further removal triggers, including wear or corrosion affecting individual wires over more than one-third of the original rope diameter, bird-caging, kinking, and heat or arc damage. Beware of carrying figures across: provincial limits for running rope are different and tighter (Alberta s.306(2): 6 randomly distributed broken wires in one rope lay, or 3 in one strand), but a sling is not a running rope. Check the rigging part of your own province's regulation.
Key concept: Wire rope SLING removal (ASME B30.9 para. 9-2.9.5): 10 randomly distributed broken wires in one rope lay, or 5 in one strand in one rope lay. Cable-laid slings: 20 per lay. B30.9 sets no 6×19 or 6×36 broken-wire limit — construction affects clear length between splices, not the count. Also remove for kinking, crushing, bird-caging, heat or arc damage, corrosion, or localized abrasion reducing the nominal diameter by more than 5 percent. In Canada B30.9 is adopted by reference in provincial occupational health and safety regulation (e.g. Alberta OHS Code s.297), and s.306 adds wear or corrosion over more than one-third of the original rope diameter. Running rope uses different, stricter numbers (Alberta s.306(2): 6 per lay, or 3 in one strand) — do not apply them to slings.
Q44hard
A crane is lifting a 20,000 kg load at a 15m radius. The load chart shows maximum lift capacity at 15m is 18,000 kg (with all outriggers fully extended on firm ground). What should the ironworker signalperson communicate to the operator?
  • A) Proceed — crane charts include a 10% safety margin for occasional overloads
  • B) Stop the lift — it exceeds the chart capacity
  • C) Proceed if the crane manufacturer approves in writing
  • D) Proceed if the lift will be completed in under 2 minutes
Correct answer: B
Load chart values are maximums — a working lift must never exceed them. The margin between the chart rating and the crane's tipping or structural limit is not usable capacity. In Ontario, for example, rated capacity is determined to CSA Z150, and a crane may not be loaded beyond it except during load tests required by the manufacturer. Exceeding the chart rating creates an unacceptable risk of crane overturning. The lift must be stopped and re-planned: decrease the lift radius (boom in), reduce the load, or bring in a larger crane.
Key concept: Crane load chart ratings are maximums, and the margin built into them is not extra capacity. Never exceed rated capacity on a working lift. Hook block, slings and other lifting devices count against the rating.
Q45medium
An ironworker is rigging a steel plate that has sharp flame-cut edges, and a polyester web sling will bear directly on one of those edges. What has to be done before the plate is lifted?
  • A) Double the sling so the added ply takes the cutting action
  • B) Cut the rated load in half and lift the plate as it is rigged
  • C) Fit corner protectors between the plate edges and the sling
  • D) Take up the load slowly so the edge cannot saw the webbing
Correct answer: C
WorkSafeBC's rigging Part puts it in one line: 'When a sling is applied to a sharp edge of a load, the edge or the sling must be protected to prevent damage to the sling' (Occupational Health and Safety Regulation, Part 15, s. 15.39). Ontario reaches the same hazard from the other side - O. Reg. 213/91 s. 172 (3) provides that no sling or similar device for rigging or hoisting made of web-type fabric or nylon shall be used if it may be cut, and s. 172 (1) (a) requires rigging to be suitable for its intended use. So the plate does not fly on that sling while the edge can cut it. Corner protectors, edge guards or softeners between the edge and the webbing are what removes the exposure.

None of the other three answers takes the edge away. Doubling the sling lays a second ply against the same edge in the same place, and the edge starts on it as soon as the load comes on. Halving the load does not help either, because a cut is not a strength problem: webbing is severed by pressure concentrated over a small radius, which happens at loads far below the rating, and once the fibres are through, the remaining section lets go without warning. Taking the load up slowly still brings the full weight of the plate onto the edge, and the sling then works against it every time the plate swings or settles.

Note what s. 15.39 is written about - a sling, not webbing alone. Chain and wire rope resist a sharp edge far better than polyester does, but the duty to protect the edge or the sling does not change with the material, so choosing a different sling is a decision about what to rig with, not a way of skipping protection at the corner.
Key concept: A sling applied to a sharp edge of a load: protect the edge or the sling so the sling cannot be damaged (WorkSafeBC OHS Regulation s. 15.39). Ontario bars the use of a web-type fabric or nylon sling that may be cut (O. Reg. 213/91 s. 172 (3)). Corner protectors, edge guards or softeners are the fix; an extra ply, a derated load and a slow pick all leave the sling bearing on the edge, and a cut severs webbing at loads well under the rating. The duty attaches to any sling, so changing sling material does not remove it.
Q46hard
An ironworker must rig a 4,000 kg beam with an unknown centre of gravity. The beam is lifted with a spreader bar and two vertical wire rope slings of equal length. When lifted 150mm off the ground, one end rises higher than the other. What adjustment should be made?
  • A) Use longer slings on the heavy end to compensate
  • B) Add counterweights to the light end
  • C) Increase crane boom angle to redistribute load
  • D) Move the spreader connection point toward the heavy end
Correct answer: D
To balance an uneven lift, move the crane hook attachment (or spreader bar connection point) toward the heavy end — a shorter distance from hook to heavy end balances the lift. With a spreader bar and equal-length slings, the pickup point must align over the centre of gravity for a level lift. Moving the connection toward the heavy end shortens the moment arm on that side, creating balance. A trial lift at low height before full elevation allows safe adjustment.
Key concept: Rigging balance: trial lift 150-300mm off ground to verify balance. Adjust pickup point toward heavy end. Never carry a grossly unbalanced load at full height.
Q47medium
On an Ontario construction project, a mobile crane is lifting near an energized overhead distribution line with a nominal phase-to-phase voltage of 44 kV. The line owner has not installed protective devices or set up its own procedures. Under Ontario's Construction Projects regulation, what is the minimum distance that any part of the crane, its rigging or its load may be brought to the line?
  • A) 1.5 m
  • B) 4.5 m
  • C) 6 m
  • D) 3 m
Correct answer: D
O. Reg. 213/91, s. 188(2) says no object may be brought closer to an energized overhead conductor than the distance set in its Table, based on the conductor's nominal phase-to-phase voltage. The first band covers 750 volts or more, up to 150,000 volts, and requires 3 m. A 44 kV line (44,000 V) falls in that band. The 4.5 m distance is only for lines over 150,000 V up to 250,000 V, and 6 m is only for lines over 250,000 V. Picking either one for a distribution line means using the wrong voltage band. The Table sets no distance smaller than 3 m for any line of 750 V or more, so 1.5 m would put the load inside the legal limit. When a crane or its load could come within this distance, s. 188(4) to (8) also apply. The constructor needs written measures and procedures, warning devices and a sign at the operator's station, and a competent worker assigned as signaller who can see both the conductor and the equipment. The distances vary by province, so this answer is for Ontario only.
Key concept: Ontario O. Reg. 213/91 s. 188(2): minimum approach to energized overhead lines is 3 m for 750 V up to 150 kV, 4.5 m for over 150 kV up to 250 kV, and 6 m above 250 kV (phase-to-phase).
Welding & Cutting 18 questions
Q48easy
Which welding processes are most commonly used for structural steel erection field welds?
  • A) SAW and GTAW
  • B) GMAW and SAW
  • C) GTAW and GMAW
  • D) SMAW and FCAW
Correct answer: D
SMAW (stick) and self-shielded FCAW (flux-cored) are the standard field processes for structural erection. Both carry their own shielding in the electrode, so they tolerate wind, weather and out-of-position work on a steel frame. GMAW (MIG) is a poor field choice because its external gas shield blows away outdoors, and SAW and GTAW are shop processes for structural work — SAW needs a flat or horizontal position and a granular flux bed, and GTAW is far too slow for structural deposition.
Key concept: Structural field welding: SMAW and self-shielded FCAW, because the shielding travels with the electrode. GMAW's gas shield is lost to wind outdoors; SAW and GTAW are shop processes. FCAW is favoured for deposition rate where conditions allow it.
Q49medium
What does CSA W47.1 govern?
  • A) The classification of welding consumables
  • B) The certification of fusion welding companies in Canada
  • C) The testing and inspection of completed structural welds
  • D) The design of structural steel connections
Correct answer: B
CSA W47.1 (Certification of Companies for Fusion Welding of Steel) governs the certification of welding companies — it certifies the company, not individual welders. Certified companies must have qualified welding supervisors, approved welding procedures (WPSs), and a documented quality control system. This is different from: CSA W59 (which governs the design and fabrication requirements for welded steel structures), CSA W178.2 (which certifies individual welding inspectors), and AWS D1.1 (the American Structural Welding Code used as a reference). On a Canadian structural steel project, the fabricator or erector must hold a current CSA W47.1 certification — this is a mandatory contract requirement.
Key concept: CSA W47.1: certification standard for Canadian welding companies. Welding shops must be W47.1-certified to produce structural welds covered by the NBC and provincial building codes.
Q50medium
Why is preheat required when welding high-strength or thick structural steel?
  • A) To speed up the welding process by reducing arc strike difficulties
  • B) To prevent the steel from expanding during welding
  • C) To slow cooling and prevent hydrogen cracking
  • D) To soften the steel so the electrode melts easier
Correct answer: C
Preheating slows the cooling rate after welding, allowing hydrogen to diffuse out of the HAZ and preventing the formation of hard, brittle martensite microstructures in the HAZ that are susceptible to hydrogen-induced cracking.
Key concept: Preheat reduces cooling rate → less hydrogen trapping → less brittle HAZ → lower risk of hydrogen-induced (cold) cracking in high-strength or thick steel.
Q51easy
What weld symbol indicates a fillet weld?
  • A) A right triangle on the reference line
  • B) A circle on the reference line
  • C) A square groove symbol
  • D) A wavy line below the reference line
Correct answer: A
A fillet weld is shown as a right triangle on the weld symbol, with the perpendicular leg always on the left and the hypotenuse facing outward (away from the joint). The weld size is shown to the left of the symbol.
Key concept: Fillet weld symbol: right triangle with vertical leg on left. Size = to left of symbol. Arrow side = below line; other side = above line.
Q52medium
A structural drawing shows a fillet weld with the size designation "10" on the weld symbol. This means:
  • A) The weld is 10 mm long
  • B) The fillet weld leg size is 10 mm
  • C) The weld must withstand 10 kN/mm of force
  • D) There are 10 weld passes required
Correct answer: B
The number to the left of the fillet weld symbol indicates the leg size in millimetres (or inches in imperial drawings). A 10 mm fillet weld has legs of 10 mm on each fusion face.
Key concept: Fillet weld size: leg size in mm shown left of triangle symbol. Throat = 0.707 × leg size. Weld size determines capacity.
Q53hard
What is the effective throat of a 12 mm fillet weld?
  • A) 10 mm
  • B) 12 mm
  • C) 6 mm
  • D) 8.5 mm
Correct answer: D
For a standard fillet weld with equal legs, the theoretical throat = leg × sin(45°) = 12 × 0.707 ≈ 8.5 mm. The effective throat is used to calculate weld strength.
Key concept: Effective throat of fillet weld = 0.707 × leg size. For 12 mm fillet: 12 × 0.707 = 8.5 mm throat.
Q54medium
Carbon arc gouging is used in structural ironwork primarily for:
  • A) Cutting plate to exact dimensions in the fabrication shop only
  • B) Welding thick plates that require deep penetration
  • C) Preheating steel before welding
  • D) Removing defective welds and back-gouging root passes
Correct answer: D
Carbon arc gouging uses a carbon electrode and compressed air to melt and blow away metal. It is the standard method for removing defective welds, back-gouging root passes of groove welds for full penetration, and excavating weld repairs.
Key concept: Carbon arc gouging: removes defective welds, back-gouges root passes. Produces fumes — requires adequate ventilation and PPE.
Q55easy
A complete joint penetration (CJP) groove weld requires:
  • A) Weld metal penetrating the joint's full thickness
  • B) Weld metal to fill the groove at least halfway
  • C) At least three weld passes in the groove
  • D) Post-weld heat treatment regardless of steel grade
Correct answer: A
A CJP weld requires weld metal to completely penetrate the full thickness of the joint, filling the entire cross-section and achieving full fusion. Where a CJP weld is required is set by the design drawings and the applicable welding standard, not by the type of loading alone; the number of passes and any post-weld heat treatment are set by the welding procedure, not by the CJP definition.
Key concept: CJP (Complete Joint Penetration): weld metal through the full thickness of the joint with complete fusion. Where CJP is required, and how the root is prepared, are set by the design and the welding procedure.
Q56medium
What does a "flag" on a welding symbol indicate?
  • A) The weld is a complete joint penetration weld
  • B) The weld is to be made in the field (field weld)
  • C) All welds on the drawing must be made in this location
  • D) The weld must be inspected by UT (ultrasonic testing)
Correct answer: B
A flag on the weld symbol reference line indicates a field weld — one that is to be made during erection at the job site, as opposed to a shop weld made during fabrication.
Key concept: Flag on weld symbol = field weld (made during erection). A circle at the junction of the arrow and the reference line = weld all around. The tail — the forked end of the reference line opposite the arrow — carries the process or specification reference.
Q57hard
Under AWS D1.1, when welding ASTM A572 Grade 50 steel with low-hydrogen SMAW electrodes, the minimum prequalified preheat and interpass temperature for material over 38 mm up to 65 mm thick is approximately:
  • A) 10°C (50°F)
  • B) 107°C (225°F)
  • C) 66°C (150°F)
  • D) No preheat required
Correct answer: C
AWS D1.1 places ASTM A572 Grade 50 in Category B, and Category B welded with low-hydrogen SMAW electrodes calls for 150°F (66°C) on material over 38 mm through 65 mm thick. The full Category B row of the prequalified preheat table (Table 5.8 in the 2020 and later editions; Table 3.2 in earlier ones) reads: 3 to 20 mm = 32°F (0°C); over 20 through 38 mm = 50°F (10°C); over 38 through 65 mm = 150°F (66°C — the metric column of D1.1M rounds this to 65°C); over 65 mm = 225°F (107°C). So 107°C is correct only for plate thicker than 65 mm, and that is the trap in this question. Watch the band edges too: a section exactly 38 mm thick still falls in the 10°C band, because the row reads 'over 38'. On Canadian structural work AWS D1.1 is not the governing document. Building Code Article 4.3.4.1 requires buildings and structural members made of structural steel to conform to CAN/CSA S16, and S16 in turn requires a CSA W47.1 certified fabricator with joint design and quality to CSA W59 — so preheat comes off the CWB-accepted WPS/WPDS, never off a US table from memory. The Canadian counterpart grade is CSA G40.21 350W (350 MPa minimum yield, against 345 MPa for A572 Grade 50), which is what a Canadian mill certificate will normally show.
Key concept: AWS D1.1 prequalified preheat for ASTM A572 Gr.50 (Category B, low-hydrogen SMAW): 3 to 20 mm = 0°C; over 20 to 38 mm = 10°C; over 38 to 65 mm = 66°C (150°F); over 65 mm = 107°C (225°F). Thicker section = higher preheat, and the bands read 'over', so exactly 38 mm is still the 10°C band. In Canada the authority is CSA W59 under a CSA W47.1 certified fabricator, reached through Building Code Article 4.3.4.1 and CSA S16 — always take the preheat from the accepted WPS/WPDS. Canadian counterpart grade: CSA G40.21 350W.
Q58medium
What is the primary cause of porosity in SMAW structural welds?
  • A) Using E7018 electrodes at too low an amperage
  • B) Moisture or oil on the metal or electrode
  • C) Failure to remove slag between weld passes
  • D) Excessive root opening in a groove joint
Correct answer: B
Porosity is gas trapped in the weld metal as it solidifies. Moisture in a low-hydrogen electrode coating and oil, paint or condensation on the base metal are the leading sources — they break down in the arc and release hydrogen and carbon monoxide into the puddle. The other faults listed produce different discontinuities: slag left between passes gives slag inclusions, too wide a root opening gives burn-through and a sagging root, and too little current gives an unstable arc with lack of fusion.
Key concept: Porosity causes: moisture/oil/contamination on base metal or electrode. Prevention: clean metal, dry electrodes, proper preheat.
Q59easy
Plasma arc cutting (PAC) is used by ironworkers primarily because:
  • A) It cuts stainless, aluminum, and non-ferrous metals
  • B) It is slower and more precise than OFC for carbon steel
  • C) It requires no gas supply of any kind
  • D) It is cheaper and safer than oxyfuel cutting
Correct answer: A
OFC relies on oxidation and only works on ferrous metals (carbon steel). PAC uses an ionized gas jet and works on any conductive metal that OFC cannot cut, including stainless steel, aluminum, and copper alloys.
Key concept: PAC cuts any conductive metal including stainless and aluminum — OFC only works on carbon/low-alloy steel by oxidation.
Q60medium
A weld inspection reveals "undercut" along the toe of a fillet weld. What caused this?
  • A) Moisture in the electrode coating
  • B) Insufficient preheat temperature
  • C) Excessive amperage or travel speed
  • D) Electrode too small for the fillet size
Correct answer: C
Undercut is a groove melted into the base metal at the weld toe that is not filled by weld metal. It comes from too much heat at the toe — excessive amperage, too fast a travel speed, too long an arc, or an electrode angle that throws the arc onto the vertical member instead of into the corner. It matters because it removes section from the base metal and leaves a sharp notch at the toe, which is where fatigue cracks start. The other faults listed cause different problems: moisture in the coating causes porosity, too little preheat on heavy or restrained sections invites cracking, and too small an electrode gives an undersized weld rather than a gouged toe.
Key concept: Undercut: a groove melted into the base metal at the weld toe and left unfilled by weld metal, caused by excessive heat, current, travel speed or electrode angle. It removes base metal section and leaves a fatigue-sensitive notch. Undercut deeper than the acceptance limit must be repaired — take that limit from the governing welding standard for the job (CSA W59 for welded steel construction in Canada) and the project inspection criteria, never from memory.
Q61medium
In structural steel work, what does CSA W59 govern?
  • A) The design and fabrication of welded steel structures
  • B) The testing and classification of welding consumables
  • C) The safety requirements for welding fumes and gases
  • D) The certification of individual welders for structural work
Correct answer: A
CSA W59 (Welded Steel Construction — Metal Arc Welding) specifies design, fabrication and erection requirements for welded steel structures in Canada, including joint design, acceptable workmanship and inspection criteria. It is often confused with CSA W47.1. W59 is the construction standard — what must be built and to what quality — while W47.1 certifies a fabricator or erector as a company qualified to do the welding, and CSA W178.2 certifies welding inspectors. Welding consumables belong to the CSA W48 series and welding health and safety to CSA W117.2, so neither of those sits in W59 either. AWS D1.1 is the equivalent American standard; Canadian work is built to W59, and D1.1 governs only where a project specification calls it up. For the Red Seal ironworker exam: W59 is the welded construction standard, W47.1 is company certification, W178.2 is inspector certification.
Key concept: CSA W59: the standard for welded steel construction — joint design, workmanship and inspection. It works alongside CSA W47.1 (certification of companies for fusion welding of steel); consumables sit in the CSA W48 series and welding health and safety in CSA W117.2.
Q62hard
An ironworker is welding a moment connection on a seismic force-resisting frame. What additional requirement applies compared to a regular gravity connection?
  • A) The connection must be welded vertically-up only
  • B) Higher amperage settings must be used to achieve deeper penetration
  • C) Notch-tough weld metal with CVN requirements
  • D) All welds must be made using GTAW process
Correct answer: C
Seismic connections take large cyclic deformations and have to absorb that energy by yielding rather than by fracturing. The weld metal must therefore be notch tough, which is proven by Charpy V-notch (CVN) impact testing at the low temperature and minimum absorbed energy called up by the project specification and the accepted welding procedure. For the same reason the procedure normally sets a maximum heat input and a maximum interpass temperature, because too much heat coarsens the grain and costs the weld its toughness. In Canada the design of seismic force-resisting systems is governed by CSA S16, referenced through the National Building Code; the American equivalents, AISC 341 and AISC 358, apply only on a project whose specification calls them up.
Key concept: Seismic welding: the weld metal must meet Charpy V-notch (CVN) toughness requirements, and the welding procedure normally caps heat input and interpass temperature to protect that toughness. In Canada seismic force-resisting systems are designed to CSA S16 under the National Building Code; AISC 341 and AISC 358 are American standards that apply only where a project specification calls for them.
Q63hard
An ironworker is welding a moment connection on a structural beam using E71T-8 flux-cored wire. The WPS specifies a minimum preheat of 150°C. The ambient temperature is -5°C and the base metal temperature is 4°C. What must be done before welding?
  • A) Increase wire speed to compensate for cold metal temperature
  • B) No preheat needed when ambient is above freezing (-5°C is the ambient air, not metal)
  • C) Preheat the joint to 150°C and verify with temp sticks
  • D) Begin welding immediately — preheat is for thick plate only
Correct answer: C
Preheat requirements are based on base metal temperature, not ambient air temperature. At 4°C base metal temperature with a 150°C preheat requirement, the joint must be heated to 150°C minimum with a heating torch before striking the arc. Cold steel increases the risk of hydrogen-induced cracking (HIC). Verify with temperature sticks or a contact pyrometer immediately before welding and maintain interpass temperature throughout.
Key concept: Preheat: applied to base metal, not air temperature. Verify with temp sticks or pyrometer. E71T-8 is a self-shielded FCAW wire used for structural steel — preheat critical in cold conditions.
Q64hard
An ironworker welds out a multi-pass fillet weld on a structural connection in cold, damp weather. The base metal is A36 and the filler is E7018. The weld passes visual inspection at the end of the shift, but the next morning cracks are found at the weld toe and in the heat-affected zone. What is the MOST likely cause?
  • A) Arc voltage is too high, causing undercutting at the toes
  • B) Base metal carbon content is too high for E7018
  • C) Travel speed is too slow - too much heat input
  • D) Hydrogen cracking from moisture in the electrode
Correct answer: D
Cracking that turns up after the joint has cooled, at the weld toe and in the heat-affected zone, is the signature of hydrogen-induced cracking - which is why the trade also calls it delayed or cold cracking. E7018 is a low-hydrogen electrode, but its coating draws moisture out of the air as soon as the hermetic package is opened. In the arc that moisture breaks down and puts hydrogen into the weld; the hydrogen then diffuses into the hard, highly stressed heat-affected zone and cracks it hours after the arc is out, once the joint has cooled to roughly 100 to 200 degrees Celsius. Cold, damp weather works against you on both counts - more moisture available, and a faster cooling rate that leaves a harder heat-affected zone. Keep opened low-hydrogen electrodes in a rod oven at about 120 degrees Celsius, recondition them once only, throw out any electrode that has been wet, and preheat the joint. Watch the timing, because it separates two different failures: a crack running down the centre of the bead during the pass or as you finish it is solidification, or hot, cracking. High arc voltage produces undercut, not cracking; A36 is a low-carbon steel well inside the range E7018 is made for; and slow travel with high heat input slows the cooling rate, which reduces hydrogen cracking rather than causing it.
Key concept: Low-hydrogen electrodes: keep opened E7018 in a rod oven at about 120 degrees Celsius, recondition once only, and discard any electrode that has been wet. Moisture means hydrogen and hydrogen means delayed cracking. Timing tells the two failures apart - cracks found after the joint has cooled, usually at the toe or in the heat-affected zone, are hydrogen-induced cracking; a centreline crack that shows during or right after the pass is solidification (hot) cracking. Preheat and controlled cooling are the field defences against hydrogen.
Q65medium
An ironworker-welder is completing a structural weld and notices arc blow causing the arc to deflect away from the joint, creating a poor weld profile. The process is SMAW with DC+ polarity. What is the MOST effective corrective action?
  • A) Increase welding current to overcome the arc deflection
  • B) Change to a different electrode classification
  • C) Lengthen the arc to let the deflection settle
  • D) Switch to AC or reposition the work lead
Correct answer: D
Arc blow is a direct-current phenomenon: the magnetic field around the current path pushes the arc off the joint. That field is far weaker with alternating current, so switching the machine to AC and running an electrode classification rated for AC is the standard cure; relocating the work lead, or clamping the work at both ends, redistributes the field and does the same job. Supporting measures are to hold as short an arc as the electrode allows, back the current off, angle the electrode opposite to the direction the arc is being deflected so the arc force opposes the blow, and run heavy tacks at the ends of the joint. Raising the current strengthens the field and makes the blow worse, lengthening the arc only gives it more room to wander, and changing electrode classification while staying on DC does not remove the cause. Arc blow is worst at the ends of joints, in corners, and near heavy sections.
Key concept: Arc blow: a DC phenomenon caused by stray magnetic fields. Primary fixes: switch to AC, or reposition the work lead. Supporting fixes: short arc, lower current, electrode angled opposite to the direction of deflection, heavy end tacks.
You are 65 questions into 121.
All 121 are in one printable PDF — questions first with no answers shown, then the key, then the explanations. Mark it with a pen the week before your exam.
Get the printable bank — CA$19 →
Exam next week? The Exam Revision Notes are the 121 facts these questions test, grouped by topic — CA$12, and included free in the bank above.
Blueprint Reading & Layout 15 questions
Q66easy
On a structural steel drawing, what do "column grid lines" represent?
  • A) Lines showing where expansion joints are required
  • B) The centreline of each floor level in the building
  • C) Reference lines used to locate columns in plan
  • D) The maximum allowable column spacing per code
Correct answer: C
Column grid lines are imaginary intersecting reference lines — numbered along one axis and lettered along the perpendicular axis — that establish the planned column and structural element locations on a structural drawing. The runs follow the building geometry, not the compass: on a rotated or irregular building neither the numbered run nor the lettered run lines up with north or east. Grid lines locate members but say nothing about column size or section, and a column may be deliberately offset from its grid line. Each grid intersection identifies a column by coordinates, so the column where line F meets line 7 is Column F7. This is different from dimension lines (which show actual measurements between members) and elevation marks (which show height). All trades on a project use the same grid reference to coordinate work — the ironworker, the concrete crew and the mechanical contractor all reference Column F7 the same way.
Key concept: Column grid lines: numbered along one axis and lettered along the perpendicular axis, used to locate columns in plan. The column where line F meets line 7 is Column F7. The grid follows the building geometry, not compass directions, and it conveys no column size or section.
Q67easy
On a structural drawing, what does the symbol "EL. 12500" typically mean?
  • A) The point's elevation above the project datum
  • B) The element is 12,500 mm in overall length
  • C) The element has a design load of 12,500 kg
  • D) Element number 12,500 on the fabrication list
Correct answer: A
EL. (Elevation) followed by a number — for example EL. 12500 — gives the finished height of that point in millimetres above the project datum, typically the finished first floor established at EL. 0. So EL. 12500 is 12,500 mm, or 12.5 m, above datum. Elevations above the datum are positive; elevations below it are negative. This is different from a grid coordinate (which locates a point in plan, not in height), a dimension (which measures the distance between two specific points), or a TOS/BOS notation (which gives the elevation of the top or bottom of a specific steel member). When setting anchor bolts or erecting columns, always verify the elevation against the structural drawings — not the architectural drawings, which may use a different datum.
Key concept: EL. = elevation above the project datum, expressed in millimetres. EL. 12500 = 12,500 mm, that is 12.5 m above datum, with the finished first floor typically set at EL. 0.
Q68medium
What is a "piece mark" on a structural drawing?
  • A) A unique identifier for each fabricated member
  • B) A quality mark stamped by the inspector to approve a weld
  • C) The AISC classification number for the steel section
  • D) A mark indicating where a weld is required
Correct answer: A
Piece marks (or erection marks) are unique identifiers (e.g., C1, B7, G12) assigned to each fabricated steel member in the structural steel package for tracking and erection — correlating shop drawings with fabricated pieces and the erection plan.
Key concept: Piece mark: unique identifier on each fabricated steel member. Matches the mark on the erection drawing and painted on the member. Used to place each piece in the correct location.
Q69medium
An ironworker lays out four anchor-rod locations at the corners of a 3000 mm by 4000 mm rectangle taken from the drawing. All four sides tape correctly, but one diagonal measures 4970 mm and the other 5030 mm. What should the ironworker conclude?
  • A) The layout is square, because the two diagonals average out to the required 5000 mm
  • B) One diagonal reading must be wrong, since four correct sides already make a rectangle
  • C) The layout is out of square and its corners must move until both diagonals read 5000 mm
  • D) The layout is acceptable as it stands, because 30 mm on a diagonal is inside tolerance
Correct answer: C
By the 3-4-5 rule a 3000 mm by 4000 mm rectangle has two equal diagonals of exactly 5000 mm. Sides that tape correctly while the diagonals differ by 60 mm mean the figure has racked into a parallelogram, so the corners are shifted until both diagonals read 5000 mm. Averaging the two readings hides the error instead of removing it. Correct side lengths do not guarantee a rectangle: a parallelogram keeps every side length as it leans and only its diagonals change, which is exactly why the diagonal check exists, so unequal diagonals are evidence of the shape, not of a bad tape reading. With these readings the corners sit 37 to 50 mm out of position, depending on which pair of sides is held. The CISC Code of Standard Practice for Structural Steel (8th edition, clause 7.8.1) allows anchor rods to vary from the drawing by only 3 mm centre-to-centre within one anchor rod group and 6 mm centre-to-centre between adjacent groups, so whether these four rods serve one base or four, the layout is many times outside tolerance and cannot be accepted as it stands.
Key concept: Squareness check for a layout: a rectangle's diagonals are equal to each other and equal to the hypotenuse of the sides (3-4-5 rule: 3000 mm by 4000 mm gives 5000 mm). Correct sides with unequal diagonals mean a parallelogram, not a rectangle; shift the corners until the diagonals match, never average the readings or alter the side lengths.
Q70easy
What do the numbers inside the circle at the end of a section cut line on a structural drawing indicate?
  • A) The number of bolts required at that connection
  • B) The magnitude of the load applied at that section
  • C) The column grid number at that point on the plan
  • D) The detail number and the sheet it appears on
Correct answer: D
The bubble at each end of a section cut line carries two numbers: the section or detail number above the dividing line, and the number of the sheet on which that enlarged view is drawn below it. Read together, they let anyone on the job turn straight from the plan to the detail. The cut line itself shows where the section is taken, and the arrowheads or flags on the cut line show the direction the viewer is looking. The bubble says nothing about how many bolts the connection takes, what load it carries, or where it sits on the grid — the bolt count comes from the detail once you turn to it, the load from the design drawings, and the location from the grid callout.
Key concept: Section cut symbol: the cut line shows the cutting plane and its arrowheads show the viewing direction. The numbers in the bubble are the detail number over the sheet number — follow them to the enlarged connection detail.
Q71medium
What information does the "Bill of Materials" (BOM) on a structural drawing provide?
  • A) A list of the subcontractors working on the project
  • B) A list of all members with sizes and quantities
  • C) The estimated cost of the fabricated steel package
  • D) The erection sequence and the crane pick order
Correct answer: B
The BOM (also called a material list or schedule) is a complete list itemizing every steel member on the drawing with its piece mark, designation, size, length and quantity, and it normally carries the material grade and any coating requirement as well — it is what procurement and the shop work from. What it does not carry is the erection sequence or the crane pick order; those belong to the erection drawings and the erection plan, which are built around crane capacity, access and stability rather than around what has to be bought. The BOM is also not a cost estimate, and it does not say who is doing the work.
Key concept: Bill of Materials: lists every steel member (piece mark, designation, size, length, quantity, material grade) for procurement and fabrication tracking. Erection sequence and pick order come from the erection drawings and the erection plan, not from the BOM.
Q72hard
A structural drawing shows "4-M20 A325 bolts" at a beam-to-column shear tab connection. What does this mean?
  • A) Metric bolts, Group 4 size class, rated 20 kN shear capacity each
  • B) 4 machine bolts of 20 mm diameter, Grade A325 galvanized finish
  • C) 4 bolts, metric M20 (20 mm diameter), ASTM A325 high-strength
  • D) A bolt group with a shear capacity of 4,000 N per M20 bolt
Correct answer: C
4-M20 A325 means 4 bolts of M20 size (20 mm nominal diameter) meeting high-strength structural bolt requirements. Since 2016 the governing product specification is ASTM F3125 — ASTM A325 and A325M were withdrawn and consolidated into F3125 as grades, so the metric bolt shown here is properly ASTM F3125 Grade A325M, the metric grade covering sizes M12 to M36. Head markings and drawing callouts were deliberately left unchanged, which is why the drawing and the bolt head still read A325 — an apprentice who goes looking for the standalone ASTM A325 standard will find a withdrawn document. On Canadian work the connection itself is governed by CSA S16, Design and construction of steel structures, which sets the resistance of the bolts and the connection and also the rules for installing and inspecting high-strength bolted joints, including pretensioned assemblies. Work to the clause numbering in the edition of that standard referenced by your provincial building code.
Key concept: Bolt callout: [quantity]-[size] [grade]. 4-M20 A325 = 4 bolts, 20 mm diameter, high-strength structural. Current product specification is ASTM F3125 Grade A325M (A325 and A325M withdrawn 2016; head markings unchanged, so drawings and bolt heads still read A325). On Canadian work, bolt and connection resistance and the installation and inspection of bolted joints are governed by CSA S16. Metric M20 = approximately 3/4 inch imperial.
Q73medium
What does the abbreviation "TOS" mean on a structural steel drawing?
  • A) Tension On Steel — a notation for tension member design
  • B) Top Of Steel — the elevation of the top surface of the steel beam
  • C) Total Overall Span — the beam span between columns
  • D) Type Of Section — indicating the steel section type
Correct answer: B
TOS (Top of Steel) is an elevation reference on structural drawings indicating the height of the top flange of a beam, measured from the project datum. It is used to coordinate with the concrete deck, mechanical, and architectural drawings. Common related notations: BOS (Bottom of Steel — soffit elevation, important for clearance), TOS is NOT the same as finished floor elevation (which is TOS + deck slab thickness + topping if any). Wrong answers often confuse TOS with the beam depth or with the centreline elevation. For steel erection: when setting beam elevation, you level to the TOS — not to the bottom flange or web centreline.
Key concept: TOS = Top of Steel elevation. Used to coordinate beam elevations with slab and architectural finish levels. Contrasted with "BOS" (Bottom of Steel).
Q74easy
On a structural drawing, what does the note "FSBW" refer to?
  • A) Fillet Strength Below Weld line
  • B) Fabricated Steel Bearing Wall
  • C) Full-Strength Butt Weld
  • D) Field Shop Bolt Work
Correct answer: C
FSBW (Full Strength Butt Weld) or CJP (Complete Joint Penetration) groove weld indicates that the weld must develop the full tensile strength of the connected base metal — the weld is not the weak link. This requires 100% penetration through the joint thickness, usually verified by visual inspection plus UT (ultrasonic testing) or radiography. It is different from: a partial joint penetration (PJP) weld, which does not penetrate the full thickness and has reduced capacity; a fillet weld, which joins members at a surface (no groove); and a plug or slot weld. FSBW/CJP welds are required at moment connections (beam-column moment joints) and splice plates carrying tension — they cost more (more prep, more passes, more inspection) than fillet welds.
Key concept: FSBW/FPBW = Full Strength/Penetration Butt Weld = CJP groove weld. Requires full root penetration — back-gouge and back-weld, or use a backing bar.
Q75medium
A structural drawing shows rebar marked as "4-20M @ 200 O.C." in a concrete slab. What does this mean?
  • A) 4 layers of rebar, 20 mm from the bottom, every 200 mm
  • B) 4 bars of 20M size, spaced 200 mm apart on centre
  • C) 4 bars of Grade 20M steel, set 200 mm clear apart
  • D) 40 metric-size bars, rated for a 200 kN service load
Correct answer: B
A rebar callout reads as quantity, then bar size, then spacing: 4 bars in the group shown, of 20M size, placed 200 mm on centre (O.C. means on centre, the same thing as c/c on other drawings). On centre is measured from the centre of one bar to the centre of the next, not as a clear gap between bars, so the clear space between 20M bars at 200 O.C. is about 180 mm. The 20M is a size designation under CSA G30.18, Carbon steel bars for concrete reinforcement, and it is not a grade: the grade is stated separately, most often 400W. The designation number only approximates the bar diameter. The Canada Border Services Agency, in its statement of reasons on concrete reinforcing bar, lists the common Canadian designation numbers with the diameter in millimetres in brackets: 10 (11.3), 15 (16.0), 20 (19.5), 25 (25.2), 30 (29.9), 35 (35.7). A 20M bar therefore measures about 19.5 mm across, with a cross-sectional area of 300 mm². That difference is small on one bar and not small when two mats have to fit inside a stated cover in a stated thickness of concrete. The leading 4 is a count of bars, not a number of layers or a rate per metre, and the 200 after the @ symbol is a spacing in millimetres, never a load.
Key concept: Rebar notation: [quantity]-[bar size] @ [spacing] O.C. So 4-20M @ 200 O.C. means 4 bars of 20M size at 200 mm on centre (centre to centre, not clear spacing; O.C. and c/c mean the same). 20M is a CSA G30.18 size designation, not a grade, and the number only approximates the diameter: 10M is 11.3 mm, 15M is 16.0 mm, 20M is 19.5 mm, 25M is 25.2 mm, 30M is 29.9 mm, 35M is 35.7 mm.
Q76hard
A beam detailed with 25 mm of camber arrives on site with its camber paint mark worn off. How does the crew establish which way up it goes before it is flown?
  • A) Sight along the beam on the ground to find its natural bow
  • B) Measure the depth at both ends and put the deeper end up
  • C) Assume the mill mark stamped on the web is meant to face up
  • D) Fly it either way, since 25 mm is inside erection tolerance
Correct answer: A
Camber is a bow along the length of the beam, so it can be read off the piece itself: lay it on level blocking, sight down the top flange from one end, and the curve shows which way the piece rises at midspan. Twenty-five millimetres over a long span is easy to see once you sight it and nearly invisible if you only look at the beam side on. Check the reading against the shop detail for that piece mark before it leaves the ground, then re-mark it. The wrong answers each fail for a different reason. Depth at the ends says nothing about camber, because camber is put into a beam of constant depth by cold cambering or by heat, so both ends measure the same. The mill mark records the producer, the heat number and the grade; it carries no orientation meaning. And 25 mm is not a tolerance to be shrugged off: it is a deliberate quantity the designer put in to be cancelled by deflection under load, so a beam flown upside down starts 25 mm low and finishes about 50 mm out at midspan, which shows up in the floor and in the deck bearing.
Key concept: A cambered beam that has lost its mark is read off the piece, not guessed: sight along it on the ground to find the upward bow, confirm against the shop detail for that piece mark, and re-mark it before it is flown. Camber is a lengthwise bow in a beam of constant depth, so end depths and mill marks tell you nothing about which way is up. Installed upside down, the built-in camber doubles the error instead of cancelling it.
Q77medium
What does a "North arrow" on a structural plan drawing indicate?
  • A) The plan's orientation relative to project north
  • B) The direction where expansion joints are required
  • C) The direction of the dominant wind load
  • D) The starting point for steel erection sequence
Correct answer: A
The north arrow establishes the plan orientation relative to true north or a project north for layout purposes. Ironworkers use this to orient themselves on site and correctly position structural members per the grid layout.
Key concept: North arrow: establishes plan orientation. "Project north" may differ from true north — always confirm which is used for layout.
Q78easy
What scale is most commonly used for structural steel framing plans?
  • A) 1:5 (full detail scale)
  • B) 1:500 or 1:1000
  • C) 1:50 or 1:100
  • D) 1:1 (actual size)
Correct answer: C
Structural framing plans are typically drawn at 1:50 (showing individual beams) or 1:100 for larger buildings. Connection details may be drawn at 1:10 or 1:5 to show bolt holes and weld sizes clearly.
Key concept: Framing plan scale: 1:50 or 1:100 typical. Connection details: 1:5 to 1:10. Always check the scale before taking measurements from drawings.
Q79hard
On a structural drawing, the connection dimensions for a diagonal brace are run from a mark labelled W.P., the working point. Unless the detail states otherwise, what does that mark locate on the joint?
  • A) The centre of the bolt group joining the brace to the gusset
  • B) Where the centrelines of the connected members intersect
  • C) The corner of the gusset plate nearest the column face
  • D) The point where the brace edge crosses the beam top flange
Correct answer: B
The working point is where the centrelines - the gravity axes - of the members meeting at that joint intersect. The detailer sets the joint out from that point so that the lines of action of the column, the beam and the diagonal brace all meet in one place. When they do, the joint delivers axial force and no member picks up a bending moment from an offset. Shift the brace's line of action away from the working point and an eccentricity is introduced, and the moment that eccentricity produces has to be carried by the connection and by the members framing into it. The choice of working point belongs to the engineer, so a detail that deliberately works to a point away from the member centrelines says so on the drawing and the connection is designed for that eccentricity - which is why the stem says "unless the detail states otherwise".

For the crew the working point is a layout reference, not a piece of hardware. On a brace-to-beam-to-column joint it commonly falls where the column and beam centrelines cross, inside the members themselves, where there is nothing to fasten to; the gusset plate exists precisely because the members cannot all physically meet at that point. That is what separates it from the three wrong answers, each of which is a real feature you can put a tape on. The centre of the bolt group is where the brace is fastened to the gusset, and its position is set out from the working point rather than the other way round. The corner of the gusset and the place where the edge of the brace crosses the beam flange are edges of fabricated plate and shape; they move if the gusset is resized or the brace section is changed, while the working point stays where the member centrelines cross.
Key concept: Working point (W.P.): the point where the centrelines of the members meeting at a joint intersect, unless the detail says otherwise. Connection dimensions are set out from it so the member forces are concurrent and no eccentricity moment is introduced; where a detail works to some other point, the connection is designed for that eccentricity. It is a layout reference, not a physical feature - bolt groups, gusset corners and member edges are located from the working point, not the reverse.
Q80medium
A steel detail on a Canadian drawing calls for an angle marked L102x76x9.5. What does this designation describe?
  • A) A 102 mm long angle with 76 mm and 9.5 mm legs
  • B) 102 mm deep, 76 kg/m, with a 9.5 mm flange thickness
  • C) A 102 mm flange, a 76 mm web, and 9.5 mm long
  • D) Legs of 102 mm and 76 mm, 9.5 mm thick
Correct answer: D
A metric angle designation lists the long leg, then the short leg, then the leg thickness, all in millimetres. L102x76x9.5 is an unequal-leg angle with a 102 mm leg and a 76 mm leg (76.2 mm in the CISC table), 9.5 mm thick (9.53 mm), and it is the metric form of the imperial L4x3x3/8. None of the numbers is the member length, which is given separately on the drawing or cut list. The middle number is not mass per metre: that is the W-shape convention (depth x mass), and this angle weighs about 12.6 kg/m. An angle also has two legs of the same thickness, not a flange and a web.
Key concept: L designation = long leg x short leg x thickness (mm); L102x76x9.5 = L4x3x3/8. Length is called out separately; mass is not in the designation.
Reinforcing Steel 18 questions
Q81easy
In the CSA G30.18 system, what does the "20M" rebar designation mean?
  • A) A metric bar about 19.5 mm in diameter
  • B) The bar has a yield strength of 20 MPa
  • C) A bar used only in 20 MPa concrete
  • D) A bar with a cross-sectional area of 200 mm²
Correct answer: A
In the Canadian metric system, 20M is a deformed metric bar with a nominal diameter of approximately 19.5 mm and a cross-sectional area of 300 mm². The common sizes run 10M (11.3 mm, 100 mm²), 15M (16.0 mm, 200 mm²), 20M (19.5 mm, 300 mm²), 25M (25.2 mm, 500 mm²) and 30M (29.9 mm, 700 mm²). The number in the designation tracks the nominal diameter in millimetres — it is not the area, since 200 mm² is a 15M bar, and it is not a strength, since strength is given separately by the grade, such as 400W. These designations and dimensions come from CSA G30.18, Carbon steel bars for concrete reinforcement; CSA A23.1 is the concrete materials and construction standard and does not set them.
Key concept: CSA G30.18 rebar sizes: 10M (11.3 mm, 100 mm²), 15M (16.0 mm, 200 mm²), 20M (19.5 mm, 300 mm²), 25M (25.2 mm, 500 mm²), 30M (29.9 mm, 700 mm²). The number roughly corresponds to the bar diameter in millimetres, not to the area and not to a strength.
Q82medium
What is the yield strength of Grade 400W rebar per CSA G30.18?
  • A) 400 MPa
  • B) 500 MPa
  • C) 600 MPa
  • D) 300 MPa
Correct answer: A
Grade 400W rebar has a minimum specified yield strength of 400 MPa and is weldable (the "W" designation). It is the most common structural rebar grade in Canadian construction.
Key concept: Grade 400W: Fy = 400 MPa, weldable. Grade 500W: Fy = 500 MPa, weldable. Grade 400R: not weldable. "W" = weldable to CSA W186.
Q83medium
In Canadian practice, what primarily determines the minimum concrete cover required over reinforcing steel?
  • A) The yield strength grade of the reinforcing bars
  • B) The exposure conditions that the concrete will face
  • C) The spacing of the chairs supporting the bar mat
  • D) The clear span of the slab between its end supports
Correct answer: B
Concrete cover is the depth of concrete between the outside face of a bar and the surface of the member, and it is there to keep moisture, chlorides, oxygen and fire away from the steel. Because that is its job, the amount required is governed by what the finished concrete has to live with in service: CSA A23.1, the Canadian standard for concrete materials and methods of construction, tabulates minimum cover by exposure class. Concrete cast against the ground, or exposed to weather and to de-icing chemicals, needs substantially more cover than a protected interior slab. The grade of the bars, the span of the slab and the spacing of the chairs do not set the requirement — chairs and bar supports only hold the steel at the cover already specified, and one that tips or is spaced too far apart lets the mat sag between supports. Take the cover figure from the drawings and the project specification for the exposure class named there, and check it before the pour, because short cover cannot be corrected once concrete is placed.
Key concept: Concrete cover is set by exposure class — the more aggressive the service environment (weather, de-icing chemicals, concrete cast against earth), the greater the cover required. CSA A23.1 tabulates minimum cover by exposure class; chairs and bar supports maintain the specified cover but do not determine it. Read the figure off the drawings and the project specification.
Q84easy
What is a "lap splice" in reinforcing steel?
  • A) A mechanical coupler that joins two rebar end-to-end
  • B) A welded joint fusing two rebar pieces at their ends
  • C) A bar bent into a U-shape hooked around another bar
  • D) An overlap where two parallel bars transfer stress
Correct answer: D
A lap splice is an overlapping zone where two bars run parallel: the bar ends overlap by a specified length (development length × splice factor) so that bar forces transfer through bond with the surrounding concrete.
Key concept: Lap splice: two bars overlap to transfer load through bond. Tension lap length per CSA A23.3 is a Class A splice at 1.0 × ld or a Class B splice at 1.3 × ld, and in no case less than 300 mm. Class A is permitted only where at least twice the required area of steel is provided and less than half the bars are spliced within the lap length.
Q85medium
What is "development length" for reinforcing bars?
  • A) The embedment needed to develop full yield strength
  • B) The distance from the end of a bar to the nearest stirrup
  • C) The length of bar that must be bent into a hook
  • D) The maximum span between bar supports
Correct answer: A
Development length (ld) is the minimum straight embedment length needed for the bar to develop its full yield strength through bond with the concrete. Insufficient development causes bond failure (bar pull-out).
Key concept: Development length (ld): minimum embedment for bar to reach yield. Depends on bar size, grade, concrete strength, and cover. Hooks reduce required development length.
Q86easy
Rebar chairs (bar supports) are used to:
  • A) Mark the location of rebar on the concrete surface after pouring
  • B) Hold vertical rebar in position while tying
  • C) Hold rebar at the correct height for cover
  • D) Splice rebar together at joints
Correct answer: C
Bar chairs and supports are plastic or metal supports placed under rebar to maintain the required concrete cover by holding the bars at the correct height above the form (distance from bottom of rebar to bottom of slab).
Key concept: Bar chairs: maintain concrete cover by supporting rebar at correct height above formwork. Cover is critical for corrosion protection and structural performance.
Q87medium
Standard rebar ties are made using:
  • A) Thin plastic zip ties rated for 50 kg
  • B) Spot welding at each intersection
  • C) 16-16.5 gauge soft annealed steel wire
  • D) Epoxy adhesive at each bar crossing
Correct answer: C
Rebar ties are made from 16 to 16.5 gauge (approximately 1.6 mm diameter) smooth, soft annealed steel wire, twisted with a tier tool. Multiple tie patterns exist for different conditions (snap tie, saddle tie, figure-8 tie).
Key concept: Rebar tie wire: 16-16.5 gauge (≈1.6 mm) soft annealed wire. Function is to HOLD POSITION only — ties do not transfer structural load.
Q88hard
A 25M bar in 30 MPa concrete requires a standard hook. What is the standard 90° hook geometry per CSA A23.1?
  • A) 6-diameter extension, 5-diameter inside bend radius
  • B) 8-diameter extension, 2-diameter inside bend radius
  • C) 12-diameter extension, 3-diameter inside bend radius
  • D) 12-diameter extension, 4-diameter inside bend radius
Correct answer: C
CSA A23.1 defines a standard 90° hook as a 90° bend plus an extension of at least 12 bar diameters at the free end of the bar. The minimum inside bend diameter is taken from the standard's bend-diameter table rather than from a single multiple of db: for a 25M bar it is 150 mm, which on a 25.2 mm bar is about 6db — an inside bend radius of about 3db. Larger bars need proportionally larger bends (30M takes 200 to 250 mm, 55M takes 550 to 600 mm), so the 6db relation does not carry above 25M.
Key concept: Standard 90° hook: 12db extension past the bend. The minimum inside bend diameter comes from the CSA A23.1 bend table, not from a fixed multiple of db — at 25M it is 150 mm, about 6db, giving roughly a 3db bend radius, and the required bend grows faster than db above 25M. Standard 180° hook: a semicircular bend plus an extension of at least 4db, but not less than 60 mm. Hooks reduce the required development length.
Q89medium
According to CSA A23.1, what placement tolerances apply to rebar in a 150 mm slab on grade?
  • A) ±12 mm in depth, ±30 mm in the location of bends and bar ends
  • B) ±8 mm in depth, ±50 mm in the location of bends and bar ends
  • C) ±20 mm in depth, ±50 mm in the location of bends and bar ends
  • D) ±8 mm in depth, ±30 mm in the location of bends and bar ends
Correct answer: B
CSA A23.1 sets placing tolerances dimension by dimension rather than as one blanket figure: concrete cover ±12 mm, and in no case may cover be reduced by more than one third of the specified cover; depth of a flexural member, thickness of a wall or smallest dimension of a column ±8 mm at 200 mm or less, ±12 mm above 200 mm but under 600 mm, ±20 mm at 600 mm and over; lateral spacing of bars ±30 mm; longitudinal location of bends and ends of bars ±50 mm, tightened to ±20 mm at discontinuous ends of members. A 150 mm slab falls in the first depth band, so ±8 mm governs its depth.
Key concept: Rebar placing tolerance per CSA A23.1: ±8 mm on depth for members 200 mm or less, ±50 mm on the longitudinal location of bends and bar ends, ±30 mm on lateral spacing of bars, ±12 mm on cover with cover never reduced by more than one third. Exceeding a tolerance requires engineer review.
Q90easy
What do the deformations (ribs) on deformed rebar do?
  • A) Mechanically interlock with concrete to improve bond and force transfer
  • B) Increase the bar weight to improve resistance to impact loads
  • C) Provide identification markings for the steel mill
  • D) Reduce the bar cross-section to save material at low-stress locations
Correct answer: A
The transverse and longitudinal ribs on deformed bar create mechanical interlock with the surrounding concrete, dramatically improving bond strength compared to smooth bars.
Key concept: Deformations on rebar: provide mechanical interlock with concrete, improving bond. Without deformations, only friction holds bar in place (much weaker).
Q91medium
A column dowel extends from the footing to lap splice with the column bars. The minimum lap splice length is typically:
  • A) Determined by the engineer's calculations
  • B) Equal to the concrete cover thickness × 10
  • C) Always 300 mm for all bar sizes
  • D) Equal to the bar diameter × 10
Correct answer: A
Dowel lap splice length is calculated by the engineer based on development length calculations considering bar size, grade, concrete strength, cover, and splice class. Ironworkers must follow the drawings — never assume a standard splice length.
Key concept: Lap splice length: engineer-specified on drawings. Based on development length × splice factor. Always follow the drawings — do not guess.
Q92hard
Rebar arrives on site carrying tight mill scale and light surface rust. What should the ironworker do before it is placed?
  • A) Apply a rust inhibitor coating before placing in forms
  • B) The bars must be sandblasted clean before placement
  • C) Replace all lightly rusted bars with new material
  • D) Place the bars as is — light rust is acceptable
Correct answer: D
Tight mill scale and light surface rust are acceptable and need not be removed; light rust may slightly improve bond by roughening the surface. Only loose scale and loose, flaking rust have to come off, and the bar must still meet its specified dimensions, mass and deformation height after hand wire brushing. Mill scale and rust are not the same thing: mill scale is the tight blue-black oxide left by hot rolling, while rust is the orange-brown corrosion product that forms afterwards. Canadian project specifications written to CSA A23.1 call for removal of loose scale and loose rust only.
Key concept: Tight mill scale and light surface rust: acceptable, and light rust may improve bond. Loose scale and heavy flaking rust: remove before placing — after hand wire brushing the bar must still meet its dimensions, mass and deformation height.
Q93medium
What is the purpose of "stirrups" or "ties" in a reinforced concrete beam or column?
  • A) To resist longitudinal tension forces along the beam axis
  • B) To resist shear and confine the concrete core
  • C) To provide anchorage for the formwork
  • D) To position the longitudinal bars at the correct concrete cover depth
Correct answer: B
Stirrups (beams) and ties (columns) resist shear and torsion forces, confine the concrete core to increase ductility, and brace the longitudinal bars against buckling under compression load.
Key concept: Stirrups/ties: resist shear force, confine concrete core, and prevent longitudinal bar buckling. Critical for seismic ductility — closer spacing in plastic hinge zones.
Q94hard
An ironworker is placing rebar in a concrete footing. The drawing calls for 20M bars at 200mm c/c each way, top and bottom, with 75mm cover to every face, and shows the footing 200mm thick. After placing the bottom mat, the ironworker finds the top mat cannot fit within the specified cover. What is the CORRECT response?
  • A) Place both mats touching - concrete cover can be eliminated for interior footings
  • B) Notify the superintendent and engineer of the conflict
  • C) Reduce the bottom cover to 50mm to create space for the top mat
  • D) Eliminate the top mat - one layer of rebar is sufficient for footings
Correct answer: B
A section that will not close is a drawing conflict, and it goes to the superintendent and the engineer - the ironworker does not settle it at the bar. Run the numbers: 75mm bottom cover, a bottom mat two bars deep (20M is 19.5mm, so 39mm), a top mat another 39mm, and 75mm top cover comes to 228mm, before any chair height, inside a footing shown as 200mm thick. The section as drawn cannot hold what the schedule calls for, so something is wrong - the thickness, the cover, the bar size or the mat callout - and only the designer can say which. Reducing cover, deleting the top mat, or letting the two mats touch each other all change how the footing carries load and how long it lasts in the ground, and none of them is the ironworker's call to make.
Key concept: Rebar cover is a structural code requirement (CSA A23.1; A23.3 is the design standard and refers to A23.1 for cover) and cannot be reduced without engineer approval, and reinforcement cannot be deleted. Drawing conflicts = stop and notify the superintendent and engineer. Carry the bar table: 20M is 19.5mm in diameter, so a two-way mat is 39mm of steel.
Q95medium
An ironworker is tying rebar for a suspended floor slab. The drawing calls for top bars (negative moment reinforcement) in the vicinity of column supports. The ironworker places these bars at the bottom of the slab instead. What is the structural consequence?
  • A) No consequence — rebar works in tension or compression regardless of position
  • B) The slab loses top tension reinforcement at supports, risking failure
  • C) The extra bottom steel raises midspan capacity, so the slab is still adequate
  • D) Minor consequence — the slab is thin, so the change in depth is negligible
Correct answer: B
Top reinforcement at column supports resists the hogging (negative) bending moment, where the top fibre of the slab is in tension. Moving those bars to the bottom puts steel into concrete that is already in compression and leaves the top fibre over the support with no tension steel at all. Concrete cannot be relied on to carry tension, so the slab is effectively unreinforced at its peak moment location, and cracking opens over the supports under service and live load. Steel added at the bottom does not make up for it, because at the support it sits on the compression side and cannot resist a moment of the opposite sign; nor is the loss a matter of slab thickness — reversing the bars gives away the effective depth that the negative moment capacity depends on.
Key concept: Top bars = negative moment (hogging) reinforcement at supports. Bottom bars = positive moment (sagging) at midspan. Placement is critical — wrong position = unreinforced at the peak moment location.
Q96hard
An ironworker in British Columbia is stressing a post-tensioning tendon. The pump gauge shows the pressure the supervisor expected, but the measured tendon stretch is well short of the expected elongation. Under the BC OHS Regulation, what must the crew do?
  • A) Keep jacking the tendon until the expected elongation is reached
  • B) Accept the tendon, since the pump pressure reached its target
  • C) Record the shortfall and carry on stressing the next tendon
  • D) Stop work on that tendon and consult the engineer in charge
Correct answer: D
BC OHS Regulation s. 20.66(5) says that if there is a significant difference between the expected and measured value of either tendon stretch or hydraulic pressure at the pump, workers must stop operations on that particular tendon and consult the professional engineer in charge for instructions. A stretch shortfall can mean friction, a slipping wedge or a problem in the tendon. Jacking harder to force the elongation risks going past the maximum values the supervisor must give operators under s. 20.66(4). Accepting the tendon because the pressure matched ignores the rule that either reading alone triggers the stop. Logging it and moving on leaves a doubtful tendon in the structure without the engineer's direction.
Key concept: BC OHS Reg. s. 20.66(4)-(5): operators get maximum allowable stretch and pump pressure. A significant expected-vs-measured difference in either one means stop on that tendon and get instructions from the professional engineer in charge.
Q97easy
On an Ontario construction project, vertical rebar dowels stick up out of a footing beside a route where workers walk and could fall onto them. Under O. Reg. 213/91, what must be done about the protruding bars?
  • A) Mark each exposed bar with bright flagging tape so it stands out clearly
  • B) Leave them in place until the next concrete pour has been completed
  • C) Post a warning sign at every entrance to the area where the bars stand
  • D) Remove, cut off at surface or protect them as soon as practicable
Correct answer: D
Ontario's Construction Projects regulation, O. Reg. 213/91 s. 36, says that when reinforcing steel, a formwork tie, a nail or another object sticking out of concrete or another surface may endanger a worker, the protrusion must be removed, cut off at the surface or otherwise protected as soon as practicable. Flagging tape and warning signs only make the bars easier to see. They do nothing to stop a worker who trips or falls from being cut or impaled. Waiting until the next pour is finished leaves the hazard in place, which breaks the "as soon as practicable" requirement.
Key concept: Ontario O. Reg. 213/91 s. 36: a dangerous protruding bar, tie or nail must be removed, cut off at the surface or otherwise protected as soon as practicable. Warning it is not enough.
Q98medium
An ironworker in Ontario is installing reinforcing steel on a wall whose face is made up of horizontal reinforcing bars. Under O. Reg. 213/91 (Construction Projects), a scaffold must be provided for this worker once the worker is working more than what height above the ground or a floor?
  • A) 3 m above the ground or a floor
  • B) 2.4 m above the ground or a floor
  • C) 3.7 m above the ground or a floor
  • D) 4.5 m above the ground or a floor
Correct answer: C
Section 133 of O. Reg. 213/91 covers workers installing reinforcing steel on a vertical surface made of horizontal bars. Section 133(2) requires a scaffold for a worker working more than 3.7 m above the ground or a floor. If a scaffold cannot be erected, the worker must use and wear a work belt (s. 133(3)). No worker climbing that surface may carry reinforcing bars (s. 133(4)). The 3 m figure is a different rule: the general fall-hazard trigger in s. 26, which brings in guardrails or other fall protection. The 2.4 m figure is also from another section. In s. 135 it is the platform height at which planks must be laid tightly side by side, not a scaffold trigger for rebar walls. 4.5 m does not appear in s. 133.
Key concept: Ontario O. Reg. 213/91 s. 133: rebar wall of horizontal bars needs a scaffold above 3.7 m (work belt if a scaffold cannot be erected; no carrying bars while climbing). The 3 m figure is the general s. 26 fall-hazard trigger.
Safety & Fall Protection 14 questions
Q99easy
In most Canadian jurisdictions, at what height does the general fall-protection requirement for construction work begin?
  • A) 3 m (10 ft)
  • B) 2.4 m (8 ft)
  • C) 1.2 m (4 ft)
  • D) 4.5 m (15 ft)
Correct answer: A
Most Canadian construction OH&S regulations set the general fall-protection trigger at 3 m: Ontario O. Reg. 213/91 s. 26 (falling more than 3 metres), Alberta OHS Code s. 139(1)(a) and WorkSafeBC OHS Regulation 11.2(1) (3 m or more) all use that figure. Do not treat 3 m as the only number on the job. Ontario separately requires a guardrail system wherever a worker has access to the perimeter or an open side of certain work surfaces, such as a floor, scaffold platform, runway or ramp, and may fall 2.4 m or more, and Alberta requires protection above 1.2 m at a permanent work area. All three regulations also require protection below the trigger height in hazard-based cases: Ontario where a worker could fall into operating machinery, into water or another liquid, into or onto a hazardous substance or object, or through an opening; Alberta where a worker could fall into or onto a hazardous substance or object, through an opening, or where there is an unusual possibility of injury; and BC where the risk of injury is greater than from impact on a flat surface.
Key concept: General fall-protection trigger: 3 m in most Canadian jurisdictions. Protection is ranked, not a single method: guardrails (or similar fall restraint) come first, and each jurisdiction's regulation sets the order of the alternatives, such as travel restraint and fall arrest. Lower thresholds and hazard-based rules can require protection below 3 m, so check the regulation that governs the project.
Q100easy
What does a "Personal Fall Arrest System" (PFAS) consist of?
  • A) Body belt, rope grab, and vertical lifeline
  • B) Safety net and horizontal lifeline only
  • C) Full body harness, connecting lanyard, and anchor point
  • D) Safety boots, hard hat, and safety glasses
Correct answer: C
A PFAS has three essential components: (1) full-body harness, (2) connecting means (lanyard, self-retracting lifeline, rope grab + lifeline), and (3) an anchor point with sufficient strength.
Key concept: PFAS = full-body harness + connecting means (lanyard/SRL) + anchor. Body belts are NOT acceptable as PFAS — only full-body harnesses.
Q101medium
What sets the minimum strength required of a personal fall arrest anchor on a Canadian construction project?
  • A) A single national requirement of 22.2 kN per worker
  • B) The OH&S regulation of the province or territory
  • C) The rating stamped on the worker's harness D-ring
  • D) Four times the combined weight of worker and tools
Correct answer: B
The number comes from the OH&S regulation of the jurisdiction where the work is being done, and the jurisdictions do not agree, so an ironworker who carries one figure across a provincial line can be badly wrong. Three examples, each read in the regulation itself. Alberta requires a permanent anchor to have a minimum breaking strength per attached worker of 16 kilonewtons, or 2 times the maximum arresting force, in any direction the load may be applied (OHS Code s. 152 (1)); a temporary anchor in a personal fall arrest system carries the same figure (s. 152.1 (2) (a)). British Columbia requires a permanent anchor to have an ultimate load capacity of at least 22 kilonewtons, and a temporary fall arrest anchor 22 kilonewtons or two times the maximum arrest force (OHS Regulation 11.6 (4) and 11.6 (3)). Ontario is built differently again: where a permanent anchor system installed under the Building Code is available and it is safe and practical to use it, that system must be the fixed support, and only where it is not does a figure appear - a temporary fixed support in a fall arrest system must be capable of supporting a static force of at least 8 kilonewtons, or at least 6 kilonewtons where a shock absorber is also used (O. Reg. 213/91 s. 26.7 (1) and (2)), and even that may be replaced by dynamic testing to good engineering practice under s. 26.7 (3). Read that Ontario figure carefully: it is what the support has to be able to take, and it is a different requirement from the 8 kilonewton cap s. 26.6 (5) puts on the peak force felt by the falling worker. Three jurisdictions, three different anchor requirements - there is no single national figure to memorize, which is what rules out the 22.2 kN answer. The harness D-ring is rated as a harness component and says nothing about what the steel overhead can take. Four times the worker's weight is a real multiplier in the wrong place: British Columbia offers it as one of the two ways to qualify a temporary anchor in a fall restraint system (11.6 (1)), where nobody is meant to fall at all.
Key concept: Fall arrest anchor strength is set by the OH&S regulation of the province or territory, not by one national number: Alberta 16 kN per attached worker or 2 times the maximum arresting force (OHS Code s. 152 (1), s. 152.1 (2) (a)); British Columbia 22 kN (OHSR 11.6 (3) and (4)); Ontario 8 kN static, or 6 kN with a shock absorber, and only for a temporary fixed support, because a Building Code permanent anchor system must be used where one is available and practical (O. Reg. 213/91 s. 26.7). Travel restraint anchors are rated far lower - Alberta 3.5 kN per worker attached and marked travel restraint only (s. 152.1 (1) (a)) - and must never carry a fall. Confirm the governing regulation before rigging an anchor.
Q102medium
A US-trained ironworker proposes running a "controlled decking zone" for deck placement on a Canadian project. Which statement is correct?
  • A) It applies in Canada wherever the erector marks the zone out
  • B) It has no force in Canada; deck placement needs fall protection
  • C) It replaces the Canadian control zone on steel erection projects
  • D) It applies in Canada once a floor is more than two storeys up
Correct answer: B
On a Canadian project the deck gang is protected the same as anyone else working an open edge: no Canadian OH&S regulation contains a controlled decking zone, and none exempts deck placement from fall protection. IHSA's structural steel chapter says so flatly in its metal decking job safety analysis - "Fall arrest/protection systems must be used. Placing deck sheets will always be 'open' or leading-edge work." The controlled decking zone belongs to the United States steel erection standard, 29 CFR 1926 Subpart R; the relief it creates exists only under that foreign standard, so marking a zone out on a Canadian deck changes nothing a worker here is owed. The Canadian term that sounds like it is a different animal. A control zone is an access-controlled strip along an unguarded edge - IHSA describes it as the area within 2 m of an unguarded edge, or an area whose risk requires control of access and entry - kept with barricades, bump lines and signage, and Alberta's Code requires a worker who must work inside one to use a travel restraint system or an equally effective means of being kept from the edge. Alberta answers this proposal directly as well: an employer must not use a control zone to protect workers from falling from a skeletal structure that is a work area.
Key concept: The controlled decking zone is a United States device with no counterpart in Canadian OH&S regulation, so it gives nothing here: placing deck sheets is leading-edge work and the gang works on a fall protection system (IHSA M036, metal decking JSA). Canada's control zone is a different thing - an access-controlled strip along an unguarded edge, worked on travel restraint or an equally effective means of keeping clear of the edge - and Alberta's OHS Code s. 161(2) forbids using one to protect workers from falling from a skeletal structure that is a work area.
Q103easy
An ironworker inspects a full-body harness before the shift. Which finding takes that harness out of service?
  • A) Chalk dust and dried mud ground into the webbing surface
  • B) Broken stitching where the leg strap webbing is sewn
  • C) A chest strap adjusted too loose for the worker's build
  • D) A label that has faded but can still be read in daylight
Correct answer: B
Broken stitching at a sewn joint is structural damage, not cosmetic. The stitch pattern is what transfers load from one piece of webbing to the next, so a harness with stitching let go at the leg strap is defective and comes off the job. Alberta OHS Code s. 150.2 (1) (a) requires equipment used as part of a fall protection system to be removed from service and either returned to the manufacturer or destroyed if it is defective, and Ontario Regulation 213/91 s. 26.6 (7) requires a defective component of a fall arrest system to be taken out of service immediately. The other three findings are all things to deal with and none of them is a removal. Dirt is cleaned off - Alberta s. 150.1 (b) requires the equipment to be kept free of substances that could contribute to deterioration, which is a housekeeping duty, not a condemnation. A loose chest strap is adjusted; fit is checked at every donning and corrected on the spot. A faded but readable label is still legible, and legibility is the test. What a harness inspection looks for that a general damage rule does not spell out: cuts, fraying, abrasion, burns and chemical staining in the webbing, broken or pulled stitching at every sewn joint, cracked, distorted or corroded D-rings and buckles, and correct adjustment on the wearer.
Key concept: Pre-use harness inspection, run over the whole harness: webbing for cuts, fraying, abrasion, burns and chemical staining; every sewn joint for broken or pulled stitching; D-rings, buckles and keepers for cracks, distortion and corrosion; then fit and adjustment on the wearer. A defective component is removed from service immediately (Alberta OHS Code s. 150.2 (1) (a); Ontario O. Reg. 213/91 s. 26.6 (7)). Inspection is done by the worker before use on each shift (Alberta s. 150.1 (a); Ontario s. 26.6 (6)). After any fall the system comes out of service and does not go back without certification.
Q104hard
An ironworker is about to work on fall arrest at the top of a column. What must the employer have in place before that system is used at all?
  • A) A spare harness and lanyard staged at grade for the rescuer
  • B) A signed waiver acknowledging the risk of suspension trauma
  • C) Written rescue procedures for a worker whose fall is arrested
  • D) A second worker at the base ready to lower the crane's hook
Correct answer: C
Ontario Regulation 213/91 s. 26.1 (4): "Before any use of a fall arrest system or a safety net by a worker at a project, the worker's employer shall develop written procedures for rescuing the worker after his or her fall has been arrested." The requirement is a precondition, not an afterthought - it bites before any use of the system, so a crew that ties off without a rescue plan is offside from the first connection. The reason is that arresting the fall is only half the event. A worker hanging in a harness is held by leg straps that restrict blood return, and suspension becomes dangerous in a time frame measured in minutes, so a rescue that has to be invented on the spot is a rescue that arrives late. Staging spare equipment, or posting someone at the base, may well form part of a procedure, but neither is the requirement and neither is any use without a plan that says who does what, with what, and how fast. A waiver is not a control and does not discharge a duty under the regulation.
Key concept: Before any use of a fall arrest system or safety net, the employer must have developed written procedures for rescuing a worker after a fall has been arrested (Ontario O. Reg. 213/91 s. 26.1 (4)). Arresting the fall is half the job; a suspended worker is on a clock. Equipment staged at grade is part of a plan, not a substitute for one.
Q105medium
Under the Alberta OHS Code, what is the maximum free-fall distance permitted for a personal fall arrest system that has no shock absorber?
  • A) 3 m (10 ft)
  • B) 0.6 m (2 ft)
  • C) 1.2 m (4 ft)
  • D) 1.8 m (6 ft)
Correct answer: C
The Alberta OHS Code requires a personal fall arrest system without a shock absorber to limit a worker's free-fall distance to 1.2 m. A shock absorber is normally required in the first place; a system without one is allowed only where it meets that free-fall limit and the rest of the same section. Where a shock absorber is used, the permitted free fall is the maximum free-fall distance the absorber is labelled and rated for, and the system must still be arranged so the worker cannot strike the ground or a level below, and must limit the maximum arresting force on the worker to 6 kN, or 8 kN with an E6 shock absorber used to the manufacturer's specifications. The practical control on free fall is anchor height: the Code requires the lanyard to be secured to an anchor no lower than the worker's shoulder height, or as high as reasonably practicable.
Key concept: Free fall in a personal fall arrest system with no shock absorber: maximum 1.2 m under the Alberta OHS Code. With an absorber, the rated free-fall distance on its label governs, subject to the clearance requirement and to the 6 kN / 8 kN limits on arresting force. Anchor at or above shoulder height to keep free fall short; a self-retracting lifeline gives near-zero free fall.
Q106medium
On an Ontario steel erection project, a safety net used as a fall protection system must be designed, tested, and installed in accordance with:
  • A) ANSI/ASSE A10.11, adopted by Ontario's construction regulation
  • B) OSHA 1926.502, which Canada adopts by reference for steel erection
  • C) CSA Z259.10, the CSA standard that covers full body harnesses
  • D) The net manufacturer's instructions alone, with no referenced standard
Correct answer: A
Ontario Regulation 213/91 (Construction Projects) s. 26.8 (1) requires a safety net to be designed, tested and installed in accordance with ANSI/ASSE Standard A10.11-2010, Safety Requirements for Personnel and Debris Nets. The rest of the section is worth knowing subsection by subsection, because each one lands on a different person. Under s. 26.8 (2) the net is installed by a competent worker. Under s. 26.8 (3) an engineer, or a competent person under the engineer's supervision, inspects and tests the installation before it is put in service. Under s. 26.8 (4) the engineer documents that inspection and testing. Under s. 26.8 (5) a copy of the document is kept at the project while the net is in service. OSHA 1926.502 is a United States regulation, and Ontario's s. 26.8 does not reference it. It carries force in a Canadian province only where that province's own law names it, as Alberta's OHS Code s. 158 (d) (i) does for one narrow case: drop-testing the fabric or netting of a leading edge fall protection system, with certification by a professional engineer as the alternative. The CSA Z259 standards listed in s. 26.1 (3) cover the parts of a personal system - Z259.10 is the full body harness standard - and none of them covers nets. Note also that it is the provincial regulation that decides which edition of the net standard applies and what else the net must do: Alberta's OHS Code s. 320 (1) (a) adopts the older ANSI A10.11-1989 (R1998) and then adds its own dimensions, requiring the net to extend not less than 2.4 metres beyond the work area (s. 320 (1) (d)) and not more than 6 metres below it (s. 320 (1) (e)). Ontario's s. 26.8, read through all five subsections, prints no such distance and leaves it to the referenced standard and to the engineer's inspection.
Key concept: Safety nets are governed by the provincial occupational health and safety regulation, not by OSHA. Ontario O. Reg. 213/91 s. 26.8 adopts ANSI/ASSE A10.11-2010, has a competent worker install the net (26.8 (2)), an engineer or a competent person under the engineer's supervision inspect and test it before service (26.8 (3)), the engineer document that (26.8 (4)), and a copy kept at the project while the net is in service (26.8 (5)). A net ranks last among the fall protection methods in s. 26.1 (2), used only where guardrail, travel restraint, fall restricting and fall arrest are all impracticable. Which edition of the standard applies is provincial too: Alberta adopts ANSI A10.11-1989 (R1998) and adds its own 2.4 m and 6 m dimensions (s. 320 (1) (a), (d), (e)).
Q107medium
What does "100% tie-off" mean for ironworkers during structural steel erection?
  • A) 100% of the rigging must be secured before erection begins
  • B) The ironworker must use a full 100-foot lifeline at all times
  • C) The ironworker must be tied off for 100% of the workday
  • D) At least one PFAS connection at all times, even when moving
Correct answer: D
100% tie-off means continuous connection — the ironworker must have at least one PFAS connection at all times, including while moving or transitioning their tie-off point. A double-lanyard or SRL with a second connection allows transitioning without a gap.
Key concept: 100% tie-off: never unclipped. Use dual lanyards or SRL to maintain connection while transitioning between anchor points.
Q108easy
On an Ontario construction project a worker has taken a fall while wearing a personal fall arrest harness. What is the correct procedure for the harness and lanyard?
  • A) If the worker is unhurt, the harness can be put back in service immediately
  • B) Perform a 10-minute visual inspection and return to service if no visible damage
  • C) Remove from service; reuse only if the manufacturer certifies it safe
  • D) Only the lanyard needs to be replaced after a fall; the harness can be reused
Correct answer: C
Ontario O. Reg. 213/91, Section 26.6(8): if a worker using the fall arrest system falls, the system shall be immediately removed from service and shall not be used again by a worker unless all components of the system have been certified by the manufacturer as being safe for re-use. Every component that took the arrest force goes out of service, not just the lanyard - webbing fibres, stitching and hardware can be damaged internally with nothing showing on the outside, which is why a visual check settles nothing. Alberta is built the same way: OHS Code Section 150.2(2) removes a personal fall arrest system from service once it has stopped a fall, and Section 150.2(3) returns it only if a professional engineer or the manufacturer certifies that it is safe to use. A worker's own inspection is the pre-use check required before the equipment is used on each shift; it is not what puts arrested equipment back to work.
Key concept: After a fall, every component of the personal fall arrest system comes out of service immediately - the damage is often internal and invisible. In Ontario it goes back only on the manufacturer's certification that it is safe for re-use (O. Reg. 213/91 s. 26.6(8)); in Alberta on certification by a professional engineer or the manufacturer (OHS Code s. 150.2(3)). A worker's pre-use inspection does not return arrested equipment to service. When in doubt, destroy it.
Q109hard
A horizontal lifeline is rigged between two anchors 10 m apart and sags 0.3 m at midspan. A 100 kg worker falls from midspan. What can be said about the force at the anchors?
  • A) The lifeline cancels anchor force because the load hangs straight down
  • B) The anchor force is many times the worker weight because sag is shallow
  • C) Each anchor carries exactly 490 N, which is half the worker body weight
  • D) Anchor force is the worker weight plus the lanyard weight, and no more
Correct answer: B
A shallow sag turns a small vertical load into a very large line tension. Treat the line as two straight legs meeting at midspan: each leg rises only 0.3 m over the 5 m half span, so the legs are nearly horizontal and most of the tension acts along the line rather than upward. Static equilibrium at midspan gives tension ≈ (W × L) / (4 × sag), where L is the FULL span between the anchors, not the half span: (980 N × 10 m) / (4 × 0.3 m) ≈ 8,200 N, more than eight times the worker weight — and that is the static figure, before any dynamic effect of arresting a fall. Letting the line sag more lowers the tension; pulling it tight raises it sharply. That is why a horizontal lifeline and its end anchors are an engineered system and are never improvised on site.
Key concept: Horizontal lifeline tension ≈ (W × L) / (4 × sag), with L the full span between anchors. Shallow sag means anchor loads far above body weight, so the line and its end anchors must be engineered.
Q110hard
An ironworker 8 m above grade must temporarily remove a section of guardrail to swing a beam into position, and no overhead tie-off point exists at that spot. What must happen before the guardrail comes off?
  • A) Alternate protection at least equal to the guardrail is in place
  • B) A signaller below keeping everyone out of the area beneath the work
  • C) Nothing more, because the opening will be left open for five minutes
  • D) An entry in the site log book recording that the guardrail came off
Correct answer: A
The guardrail IS the protection at that edge, so taking it out creates an unprotected edge unless something equal to or better than the guardrail is already protecting the worker. The substitute has to be working before the rail comes off, not arranged afterwards: a personal fall arrest system connected to a temporary engineered anchor installed for the purpose, a safety net rigged below the work level, or a personnel platform that carries its own guardrails. If none of those can be provided at that location, the rail stays and the beam is swung another way, or the work waits until an anchor is installed — waiting is one way of satisfying the requirement, not an exception to it. How briefly the opening is exposed makes no difference, workers or signallers below are not fall protection, and logging the removal records a hazard without controlling it.
Key concept: Never remove a guardrail until equal or better protection is already in use at that edge: engineered anchor and fall arrest, a net below, or a platform with its own rails. Short duration, spotters and paperwork are not substitutes.
Q111medium
An ironworker on a steel beam is tied off to a self-retracting lifeline anchored overhead. Before work starts, the fall clearance needed below the working surface must be worked out. Which distances are added together?
  • A) Only the length of lifeline paid out when the worker steps off the beam
  • B) Nothing, because a retracting lifeline removes the need for clearance
  • C) Free fall before lockup, deceleration, D-ring to feet, safety margin
  • D) Only the arresting force rating divided by the total worker weight
Correct answer: C
A self-retracting lifeline shortens a fall but does not remove the need for clearance below. The clearance is a sum, built the same way as for a shock-absorbing lanyard: the short free fall that happens before the brake engages, plus the deceleration distance travelled while the brake brings the worker to a stop, plus the distance from the harness D-ring down to the feet, plus a safety margin so the feet come to rest clear of the nearest surface or obstruction. Anchoring overhead rather than at foot level keeps the free-fall term small, but it never drives the total to zero. Add the terms, then compare the result against the distance actually available below the work; if the space is not there, that connector is the wrong choice for that position.
Key concept: Fall clearance for a self-retracting lifeline is a sum, never zero: free fall before lockup + deceleration distance + D-ring to feet + safety margin, measured down from the anchor and checked against the space actually available.
Q112hard
An opening is left in a steel deck for a duct and, instead of a guardrail, the crew covers it. Under Ontario's Construction Projects Regulation, which of these must that covering satisfy?
  • A) It is used only where a guardrail cannot be installed
  • B) It is left liftable so materials can be passed through
  • C) It is inspected and certified by an engineer before use
  • D) It is fastened so it cannot be moved off the opening
Correct answer: D
O. Reg. 213/91 s. 26.3 (2) gives two ways to stop a worker falling through an opening on a work surface - a guardrail system, or a protective covering - and it sets out what the covering has to be: it completely covers the opening, is securely fastened, is adequately identified as covering an opening, is made from material adequate to support all loads to which it may be subjected, and is capable of supporting a live load of at least 2.4 kilonewtons per square metre. Fastening is the one that site practice most often skips. A sheet lying loose over a hole is moved by the very traffic it is there to protect: kicked aside, slid off as material is dragged over it, or lifted by wind. The worker who then steps on the edge of a shifted cover goes through it.

That is also why a cover left deliberately liftable for access is not a compliant cover. Where work has to be done in or around the opening, s. 26.3 (3) allows the covering or the guardrail to be removed temporarily, but only while the worker is adequately protected and danger signs are posted in accordance with s. 44 (1) and (2) - a planned removal under protection, not a cover that anybody can pick up.

The other two answers borrow rules that belong elsewhere. Inspection and testing by an engineer, or by a competent person under the engineer's supervision, before the system goes into service is the safety net requirement in s. 26.8 (3); nothing in s. 26.3 puts an engineer on a deck cover. And the covering is not a fallback that first needs a guardrail to be impracticable: s. 26.3 (2) sets the two out as alternative precautions for an opening, so a covering that meets all five requirements is protection in its own right. Note also that this duty does not wait on a height - section 26 lists falling through an opening on a work surface as a hazard in itself, alongside falling more than 3 metres.
Key concept: A covering over an opening in a work surface is fall protection only if it meets every requirement of O. Reg. 213/91 s. 26.3 (2): completely covers the opening, is securely fastened, is adequately identified as covering an opening, is made of material adequate for all loads it may be subjected to, and can support a live load of at least 2.4 kilonewtons per square metre. A guardrail system is the alternative to it, not a precondition for it. It may be removed temporarily to work in or around the opening only while the worker is adequately protected and danger signs are posted (s. 26.3 (3) with s. 44). The opening hazard is listed in section 26 in its own right, so it is not tied to the 3 metre trigger.
Tools & Equipment 9 questions
Q113easy
What is an "ironworker machine" (also called a hydraulic ironworker)?
  • A) A mobile crane specifically designed for steel erection
  • B) A hydraulic machine that shears, punches, and bends steel
  • C) A hydraulic torque wrench for high-strength bolt installation
  • D) A portable wire rope swaging machine for rigging
Correct answer: B
An ironworker machine is a multi-function hydraulic bench-top or freestanding machine used in fabrication shops and on site for shearing plate, punching bolt holes, notching angle iron, and bending bar stock.
Key concept: Ironworker machine: hydraulic multi-function tool for shearing, punching, notching, and bending steel. Common in fabrication shops and ironworker tool trailers.
Q114easy
What is the difference between a "drift pin" and a "spud wrench"?
  • A) A spud wrench is used only for rigging; a drift pin is used only for concrete work
  • B) A spud wrench adds a wrench end; a drift pin only aligns
  • C) They are the same tool — different regional names
  • D) A drift pin can tighten bolts; a spud wrench cannot
Correct answer: B
A drift pin is only a tapered alignment tool for bolt holes. A spud wrench combines a wrench (typically open-end or box) on one end with a tapered shank for alignment on the other, allowing both alignment and bolt tightening in one tool.
Key concept: Drift pin: alignment only. Spud wrench: wrench end + tapered shank = alignment + bolt snugging in one tool.
Q115medium
A hydraulic bolt tensioner is used instead of a torque wrench for high-strength bolt installation. What is the key advantage?
  • A) It is lighter and cheaper than a torque wrench
  • B) It applies direct tension, eliminating torque variability
  • C) It can install bolts in confined spaces where a torque wrench cannot fit
  • D) It works on all bolt grades including stainless steel and aluminum
Correct answer: B
Hydraulic tensioners apply direct tensile load to the bolt by pulling the threaded end rather than applying torque, eliminating the torque-to-tension variability that comes from lubrication, thread condition, and technique. This achieves more consistent and accurate pretension.
Key concept: Hydraulic tensioner: applies direct tension (not torque). Eliminates torque-tension variability. Used for critical or high-volume installations.
Q116medium
An explosive actuated fastening tool misfires while an ironworker is shooting deck fasteners, and the load does not go off. Under Ontario's Construction Projects regulation, what happens to that load?
  • A) It goes into a water-filled container on site until removed
  • B) It goes back into the load container with the unused loads
  • C) It is re-chambered and fired into scrap steel to spend it
  • D) It goes into the day's construction waste at the end of shift
Correct answer: A
Ontario Regulation 213/91 s. 121 (3): "A misfired explosive load removed from an explosive actuated fastening tool shall be placed in a water-filled container on the project until the misfired explosive load is removed from the project." A misfire is not a dud - it is a live charge that failed to initiate, and it may initiate later under heat, friction or impact. Water kills that possibility and keeps the load identifiable and contained until it leaves the site. Returning it to the load container is the worst of the wrong answers, because the same Part keeps loads of different strengths separated and stored in a locked container, and a live misfire mixed back into good stock will be picked up and chambered by the next worker. Firing it into scrap puts an unpredictable charge behind a fastener with no control over where it goes. Binning it hands a live charge to whoever handles the waste. The same Part also requires the worker to be adequately trained and to carry proof of that training (s. 117 (1) and (2)), to wear adequate personal protective equipment including eye protection (s. 117 (3)), and to inspect the tool before use for cleanliness, free movement, an unobstructed barrel and defects (s. 118).
Key concept: Explosive actuated fastening tools, Ontario O. Reg. 213/91: a misfired load goes into a water-filled container on the project until it is removed from the project (s. 121 (3)) - never back into stock, never fired off, never binned. The worker must be trained and carry proof of training (s. 117), must wear eye protection (s. 117 (3)), and must inspect the tool before use (s. 118). Loads are stored in a locked container and loads of different strengths are not stored together (s. 121).
Q117easy
What is a "beam clamp" used for in ironworking?
  • A) To hold a beam in plumb during erection until it is bolted
  • B) To attach rigging to a beam flange without welding
  • C) To permanently connect two beams at a splice
  • D) To clamp the welding electrode holder to the beam during welding
Correct answer: B
Beam clamps attach to a beam flange by clamping action, providing a temporary rigging point for hooks, slings, and blocks — for hoisting, pulling, or hanging equipment without welding, drilling, or otherwise permanently modifying the beam.
Key concept: Beam clamp: attaches to beam flange without welding/drilling. Provides temporary rigging point. Must be rated for the load and installed per manufacturer instructions.
Q118medium
A "burning bar" (thermic lance) is used in ironwork for:
  • A) Preheating weld areas to prevent hydrogen cracking
  • B) Heating structural steel for straightening or hot bending
  • C) Cutting hard materials like steel, concrete, and rock
  • D) Marking cut lines on structural steel by burning shallow grooves
Correct answer: C
A burning bar, or thermic lance, is a steel tube packed with steel or alloy wires and fed with oxygen; once lit, the iron itself burns in the oxygen stream and the bar washes its way through the work. The reaction is hot enough to melt concrete and rock as well as steel, so a burning bar gets through material an oxy-fuel torch cannot cut at all - heavily reinforced concrete, very thick or hardened sections, seized pins and frozen anchor bolts - which is why it turns up in demolition and emergency access work. It is not a preheating or heat-straightening tool: those call for a rosebud or heating torch with controlled, even heat, and a burning bar destroys the material instead of warming it. It does not lay out cut lines either. The bar is consumed as it burns and throws molten slag, so it demands hot work precautions and a fire watch.
Key concept: Burning bar (thermic lance): a steel tube packed with wires and fed with oxygen; the burning iron cuts steel, concrete and rock that conventional oxy-fuel cutting cannot touch. Used for demolition and emergency access, not for preheat or heat straightening. Extreme heat, molten slag and heavy sparks - a serious fire and burn hazard needing hot work precautions and a fire watch.
Q119medium
An optical level or builder's level is used during structural steel erection to:
  • A) Check the alignment of bolt holes in connections
  • B) Read the crane load chart to determine crane capacity
  • C) Measure the plumb of columns using the level bubble
  • D) Establish level reference elevations across the structure
Correct answer: D
A builder's level (optical or laser) establishes and verifies a horizontal datum plane across the site. It is used to set column base plate elevations, check beam levelness, and verify floor deck elevations.
Key concept: Builder's level: establishes horizontal reference. Used to set base plate elevations and verify that beams are level. Must be set on a stable base and calibrated.
Q120hard
A crew snug-tightens high-strength bolts in a slip-critical connection using a pneumatic impact wrench. Which statement about this work is correct?
  • A) Snugging with an impact wrench is fine, but the joint must then be pretensioned
  • B) The impact wrench must be calibrated daily so snugging cannot exceed a set tension
  • C) A torque multiplier must be used with all impact wrenches on structural connections
  • D) Impact wrenches cannot be used on high-strength bolts under any circumstances
Correct answer: A
Snug tight is the condition in which the plies of the joint are brought into firm contact - the tightness reached after a few impacts of an impact wrench, or the full effort of an ironworker on an ordinary spud wrench. The impact wrench is the normal tool for it. Snugging is not a controlled-tension operation. No tension value is specified for a snug-tightened joint, so there is nothing for the wrench to be calibrated against and no such thing as over-snugging to guard against. What matters is sequence and technique: work from the most rigid part of the joint outward and re-snug as needed until every ply is in firm contact. A slip-critical or pretensioned joint must then be brought to full pretension by one of the verified installation methods - turn-of-nut, twist-off (tension-control) bolt, direct-tension-indicator washer, or calibrated wrench. Only the calibrated-wrench method needs a wrench calibrated daily in a tension calibrator, and that is a pretensioning control, not a snugging control. A torque multiplier is a hand-torque device with no place in this operation. High-strength bolted connections on Canadian projects are designed and installed to CSA S16.
Key concept: Snug tight = all plies drawn into firm contact, reached with a few impacts of an impact wrench or the full effort of a spud wrench. There is no specified snug tension, so there is nothing to calibrate for snugging. Slip-critical and pretensioned joints must then be pretensioned by turn-of-nut, twist-off bolt, direct-tension-indicator washer or calibrated wrench - and only that last method needs daily calibration in a tension calibrator. Governing standard in Canada: CSA S16.
Q121medium
Before using any rigging hardware (shackles, hooks, chains) on a job site, the ironworker should:
  • A) The equipment only requires inspection during the annual company audit
  • B) Test each piece by applying twice the WLL to check for deformation
  • C) Visually inspect for damage and verify adequate WLL
  • D) Apply a fresh coat of oil to all moving parts
Correct answer: C
Pre-use inspection of rigging hardware is mandatory. Visually inspect for cracks, deformation (hooks opening, shackle bowing), corrosion reducing cross-section, missing or illegible load ratings, and pin security — and verify the WLL is adequate for the lift.
Key concept: Pre-use rigging inspection: check for cracks, deformation, corrosion, and verify WLL marking is legible and adequate. Remove any questionable hardware from service.