Q25easy
What is the Working Load Limit (WLL) of a rigging component?
- A) The maximum load the component has ever been tested to
- B) The minimum breaking strength of the component
- C) The load at which the component begins to permanently deform
- D) The maximum load it may lift in normal service
Correct answer: D
WLL (also called Safe Working Load) is the maximum load a rigging component is authorized to lift under normal working conditions, accounting for the safety factor from the breaking strength.
Key concept: WLL = maximum authorized lifting load. NOT the same as breaking strength. Never exceed WLL.
Q26medium
A wire rope sling is rated for a working load limit (WLL) of 10,000 kg in a straight-line (vertical) hitch, and the sling tag shows no separate choker rating. What is the effective WLL in a choker hitch at an angle of choke of 120° or greater?
- A) 8,000 kg — choker hitch reduces capacity by 20%
- B) 5,000 kg — choker hitch reduces capacity by 50%
- C) 10,000 kg — choker hitch does not reduce capacity
- D) 7,500 kg — choker hitch reduces capacity by 25%
Correct answer: D
ASME B30.9-2021, para. 9-2.10.1(d): when the choker hitch rating is not identified on the sling, the choker hitch rating for single-leg and bridle wire rope slings is 75% of the sling's straight-line hitch rating (70% for cable-laid slings). So 10,000 kg × 0.75 = 7,500 kg — a 25% reduction, caused by the bending and pinching of the rope at the choke point. That 75% figure holds only at an angle of choke of 120° or greater: para. 9-2.10.1(e) sends you to Table 9-2.10.1-1 for smaller angles, which gives 87% of the choker rating at 90°–120°, 74% at 60°–89°, 62% at 30°–59°, and 49% at 0°–29°. Although B30.9 is an American standard, it governs Canadian work because occupational health and safety regulation adopts it by reference — Alberta OHS Code Part 21, s.297(1) requires wire rope, alloy steel chain, synthetic fibre rope, metal mesh and synthetic fibre slings manufactured on or after July 1, 2009 to meet ASME B30.9. If the sling tag carries its own choker rating, use the tag.
Key concept: Choker hitch on a WIRE ROPE sling: 75% of the straight-line (vertical) rating — a 25% reduction — where the tag shows no choker rating and the angle of choke is 120° or more (ASME B30.9-2021 para. 9-2.10.1(d); cable-laid slings 70%). Below 120°, reduce further per para. 9-2.10.1(e) and Table 9-2.10.1-1: 87% of the choker rating at 90°–120°, down to 49% at 0°–29°. Basket hitch = 2× vertical WLL at 90°, subject to D/d. Single vertical = 1× WLL. The 75% factor is wire rope only — alloy steel chain (9-1.10.1(d)) and synthetic webbing (9-5.10.1(d)) choke at 80%, metal mesh (9-3.10.1(d)) at 100%, synthetic rope (9-4.10.1(d)) at 75%. B30.9 is adopted by reference into Canadian law: Alberta OHS Code Part 21, s.297 requires slings made on or after July 1, 2009 to meet ASME B30.9-2006. Always read the sling tag first.
Q27medium
Alberta's OHS Code limits how heavily rigging may be loaded. What changes when the rigging is raising or lowering a worker rather than material?
- A) The limit tightens to 10 percent of the breaking strength
- B) The limit stays the same, but a second sling must be added
- C) The limit loosens, because a person weighs far less than steel
- D) The limit is set by the crane operator for that particular lift
Correct answer: A
Alberta OHS Code (AR 191/2021) s. 292 (1) sets two different ceilings on the same rigging. Under (a), rigging must not be subjected to a load of more than 10 percent of the breaking strength of the weakest part of the rigging if a worker is being raised or lowered. Under (b), the figure for everything else is 20 percent of the ultimate breaking strength of the weakest part. Twenty percent is a design factor of 5 to 1; ten percent is 10 to 1. So the same sling that may take 2,000 kg of steel may take only 1,000 kg when the load is a person. The reason is not that people are heavier - it is that a rigging failure under material is a dropped load and a rigging failure under a worker is a fatality, so the margin is doubled. Nothing in the section lets the operator set the number for a particular lift, and adding a second sling changes the load carried by each leg, not the percentage each leg is permitted to take.
Key concept: Alberta OHS Code s. 292 (1): rigging is limited to 20 percent of the ultimate breaking strength of its weakest part for general lifting, a design factor of 5 to 1, but only 10 percent when a worker is being raised or lowered, which is 10 to 1. Doubling the margin for personnel is a fixed rule, not a judgement call on the day.
Q28easy
During a crane lift, what is the purpose of a tagline?
- A) To control the rotation and swing of the load
- B) To measure the length of the lift path
- C) To provide an extra rigging connection in case the main sling fails
- D) To attach the load to the crane hook
Correct answer: A
Taglines allow workers to guide and control a suspended load from a safe distance, preventing rotation and swing without placing workers directly under or near the load.
Key concept: Tagline: controls load rotation and swing from a safe distance. Must be long enough to keep workers outside the swing radius.
Q29hard
A wire rope sling is about 300 mm too long for the pick and the rigger wants to take up the slack. Under ASME B30.9, what is permitted?
- A) Tie a knot in the sling body to take up the extra length
- B) Only a method approved by the maker or a qualified person
- C) Fit two wire rope clips to form a temporary shortened eye
- D) Put a twist in the sling and choke it to take up the slack
Correct answer: B
ASME B30.9-2021, section 9-2.10.4: "(a) Slings shall be shortened or adjusted only by methods approved by the sling manufacturer or a qualified person. (b) Slings shall not be shortened or lengthened by knotting or twisting, or by wire rope clips." All three of the rejected answers are named in that one clause, and they fail for the same physical reason: each puts a sharp local bend or a crushing grip into a rope whose rated load assumes a smooth, unrestrained body. A knot can cut the rope's strength roughly in half at the knot. A twist unbalances the lay and works the strands against one another. Wire rope clips are a termination fitting for a dead end, not a length adjuster in the middle of a loaded sling body, and the same standard bars using them for this. The proper answers are the ones the standard points to: a shorter sling, a sling with a proper adjustable fitting, or a shortening method the manufacturer publishes for that sling. B30.9 is not merely an American reference here - Alberta OHS Code s. 297 (1) requires slings manufactured on or after July 1, 2009 to meet it, and s. 295 states that a worker must not use rigging that does not comply with that Part.
Key concept: Shortening a sling: ASME B30.9 section 9-2.10.4 allows only methods approved by the sling manufacturer or a qualified person, and expressly bars shortening or lengthening by knotting, twisting, or wire rope clips. Each of those puts a sharp bend or a crushing grip into a body whose rated load assumes neither. Adopted into Canadian law by provincial regulation, for example Alberta OHS Code s. 297 (1).
Q30medium
No manufacturer's specification can be found for a winding drum that a wire rope will spool onto. What minimum drum diameter should be used?
- A) 6 times the rope diameter
- B) 12 times the rope diameter
- C) 20 times the rope diameter
- D) 30 times the rope diameter
Correct answer: C
The binding rule is the manufacturer's figure: Alberta's OHS Code s.302(1) requires that the wire ropes, sheaves, spools and drums used in rigging have a diameter of not less than the diameter specified by the manufacturer for that use. Where no specification can be found, Alberta's published explanation guide to Part 21 gives the working minimum — unless otherwise specified by the manufacturer, the diameter of winding drums should not be less than 20 times the diameter of the rope, which reduces the likelihood of weakened rope caused by excessive bending stresses. Six or twelve times the rope diameter bends the rope far harder than it is built to take; thirty times is generous but is not the published minimum. Bending fatigue, not overload, is what usually kills a rope. Note that there is no single number for a rope running over a sheave: the minimum varies with rope construction, so read the rope manufacturer's table rather than carrying one figure in your head.
Key concept: D:d ratio = drum or sheave diameter divided by rope diameter. Alberta OHS Code s.302(1): not less than the diameter the manufacturer specifies. With no specification, the Part 21 explanation guide gives 20 times the rope diameter for winding drums. Smaller D:d means tighter bending, more stress and faster fatigue; the sheave minimum varies with rope construction.
Q31easy
When installing wire rope clips (U-bolt clips), which way do the U-bolts face?
- A) Either direction is acceptable if the clips are torqued
- B) U-bolts on the dead end, saddle bears on the live end
- C) U-bolts face the direction the load will travel in
- D) U-bolts on the live (load-bearing) end, saddle on the dead end
Correct answer: B
The saddle, not the U-bolt, must bear on the live rope end, because the U-bolt creates a stress concentration that would crush and weaken the load-bearing part of the rope. Alberta's OHS Code s.300(1) puts it in those words: the U-bolt section of the clip must bear on the short or dead side of the rope, and the saddle of a clip must bear on the long or live side. "Never saddle a dead horse" is the memory hook. Correct torque does not make the orientation optional, and the direction the load travels has nothing to do with it.
Key concept: "Never saddle a dead horse" — saddle on the live (load-bearing) rope, U-bolt on the dead end (Alberta OHS Code s.300(1)). The number of clips is set by rope diameter, not a fixed count: Schedule 5 requires 2 clips up to 11 mm, 3 at 12 to 16 mm, 4 at 19 to 25 mm, 5 at 29 to 32 mm, 6 at 38 mm, 7 at 44 mm and 8 at 50 mm, spaced about 6 rope diameters centre to centre.
Q32medium
A screw-pin shackle is used where:
- A) Permanent or semi-permanent rigging connections are needed
- B) A higher rated capacity is needed than a bolt-type shackle offers
- C) High side-loading conditions exist during the lift
- D) The rigging will be frequently removed and reattached
Correct answer: D
A screw-pin shackle is opened and closed by hand without tools, which is exactly what temporary or frequently changed rigging needs. It is not rated higher than a bolt-type shackle of the same size and grade — both carry the same working load limit, because the rating comes from the body size and the material, not from how the pin is retained. Side loading does not select a screw-pin either; side loading derates any shackle and the manufacturer's reduction has to be applied. Where the shackle stays in place for a long period, or where the sling or the load can turn against the pin and back it out, the bolt-type shackle with a nut and cotter pin is the correct choice; BC's OHS Regulation s.15.11(2) also requires that the pin of a screw-pin shackle be wired or otherwise secured against rotation in any application that may cause the pin to loosen, and s.15.11(1) requires every shackle pin to be secured against dislodgment.
Key concept: Screw-pin shackle: opened and closed by hand, for temporary or frequently changed rigging. Bolt-type (safety) shackle with nut and cotter pin: for long-term installation or wherever the pin could turn and unscrew. Same size and grade means the same WLL either way — the pin type is about security, not capacity. BC OHSR s.15.11(2): a screw-pin shackle's pin must be secured against rotation where the application may loosen it.
Q33hard
Before a critical lift, the rigger calculates the load center of gravity (CG). If the CG is NOT centered between the sling attachment points, what will happen?
- A) The load will spin in the direction of the CG offset
- B) The lift will be stable because slings self-equalize
- C) The slings will slip to equalize the load automatically
- D) The load will tilt toward the heavier end
Correct answer: D
When the CG is offset, the load tilts toward the heavier side. The sling leg closer to the CG — the one over the heavier end — carries a disproportionately higher load, which must be accounted for in sling selection.
Key concept: Off-center CG: load tilts toward heavier end; that sling leg carries more load. Use an equalizer beam or adjust pick points to balance.
Q34medium
Which crane hand signal means "STOP"?
- A) Arm extended, palm facing down, moving arm side to side
- B) One arm raised, rotating at the elbow
- C) Both arms raised above head
- D) Arm extended, palm facing the crane operator, fist closed
Correct answer: A
The universal crane signal for STOP is arm extended horizontally with palm facing down, moved side to side. EMERGENCY STOP uses both arms in this position.
Key concept: Crane STOP signal: arm extended, palm down, move side to side. In an emergency, ANYONE on site can give a stop signal and the operator MUST stop.
Q35easy
What does "two-blocking" mean on a crane?
- A) Installing two taglines on a single load
- B) Using two sling blocks to double the crane capacity
- C) Locking two rigging components together to prevent separation
- D) The hook block contacts the boom tip sheave
Correct answer: D
Two-blocking occurs when the lower load block — the hook block or the overhaul ball — is drawn up until it strikes the upper block at the boom tip, the boom tip sheave assembly. With no travel left, the hoist drum keeps pulling against a rope that cannot move: the rope can part or the fitting can fail, and the load falls. It has nothing to do with taglines, with locking rigging components together, or with capacity, which is not increased by adding blocks in this sense.
Key concept: Two-blocking: hook block contacts boom tip → catastrophic failure risk. Modern cranes have anti-two-block devices. Operator must watch for this.
Q36medium
Synthetic web slings must be removed from service when:
- A) There are cuts, tears, or chemical burns visible
- B) Colour fading or minor surface abrasion is visible
- C) Only when the rated capacity tag is illegible
- D) The sling has been used for more than 500 lifts
Correct answer: A
A synthetic web sling comes out of service for damage that has cut, burned, melted or abraded the fibres or the stitching. Alberta's OHS Code s.305(2) requires permanent removal if part of the sling is melted, charred or damaged by chemicals, if stitches in load-bearing splices are broken or worn, or if end fittings are excessively pitted or corroded, cracked, distorted or broken. Section 305(1) adds the measured limits: an edge cut longer than the web thickness, or abrasion deeper than 15 percent of the webbing thickness taken across all plies. Colour fading and light surface scuffing are not by themselves removal criteria. No regulation retires a sling on a lift count. An illegible or missing capacity tag does require removal, but it is one criterion among many rather than the only one.
Key concept: Remove a synthetic web sling for cuts, tears, melting or charring, acid or caustic damage, broken or worn stitching in load-bearing splices, damaged end fittings, or a missing or illegible tag. Measured limits (Alberta OHS Code s.305(1)): edge cut longer than the web thickness; abrasion deeper than 15 percent of the webbing thickness. Do not expose a synthetic web sling above 82°C unless the manufacturer permits (BC OHSR s.15.53). Synthetic slings give less warning before failure than wire rope.
Q37hard
A load weighs 8,000 kg. One sling is rigged under it as a basket hitch, with both legs running to the hook at 45° from horizontal. What is the approximate tension in each sling leg?
- A) 8,000 kg
- B) 5,660 kg
- C) 11,310 kg
- D) 4,000 kg
Correct answer: B
One sling rigged as a basket puts two legs under the hook, so each leg carries half the load vertically - 4,000 kg - and the sling angle adds to that. At 45° from horizontal the vertical part of a leg's tension is T x sin 45°, so T = 4,000 ÷ 0.707, about 5,660 kg in each leg. Count the legs before touching the trigonometry, because that is where a basket goes wrong. A basket hitch is the sling passed under the load with both ends brought up to the hook, which is two legs from one sling; a second sling basketed alongside it would make four, and the share per leg would halve again. Stopping at 4,000 kg leaves the angle out altogether - that figure is only the vertical share each leg has to carry, and the true pull along the sling is 41 percent higher than that share. Putting the whole 8,000 kg into one leg ignores that there are two of them. Applying the angle factor to the full load instead of to the half load gives about 11,310 kg, which is twice the real tension. What the sling body, the fittings and the hook actually see is the tension along the leg, not the vertical share, so it is the tension that has to sit inside the rated capacity of the hitch.
Key concept: A basket hitch made with one sling has two legs, so each leg's vertical share is half the load. At 45° from horizontal the pull along the leg is that share divided by sin 45°, which is 41 percent more than the share itself: 8,000 kg gives a 4,000 kg vertical share and about 5,660 kg of tension in each leg. Count the legs first, then apply the angle, and rate the hitch on the leg tension rather than on the vertical share.
Q38medium
What is a spreader beam used for in rigging?
- A) To counterbalance the weight of the crane boom
- B) To measure the balance point of a long structural member
- C) To distribute the load over several pick points
- D) To spread two crane boom sections for tandem lifts
Correct answer: C
A spreader beam is a below-the-hook lifting device that widens the pick points on a load. The beam carries the spread as compression along its own length, so the sling legs hang nearer to vertical and no horizontal squeeze is passed into the load itself. It does not counterbalance anything on the crane, it does not find a balance point, and it has nothing to do with boom sections. Do not confuse it with an equalizer beam, which is a different device: an equalizer beam pivots at a centre point to share load equally between two hoist lines or two cranes. Alberta's OHS Code s.297(2) puts below-the-hook lifting devices other than slings under ASME B30.20, and s.297(3) and (4) allow a spreader bar to be labelled with its rated capacity by a uniquely numbered capacity data sheet. BC's OHS Regulation requires the working load limit of a spreader bar to be certified by a professional engineer or established by the manufacturer (s.15.58), requires a nameplate (s.15.59), and counts the device as part of the lifted load (s.15.60).
Key concept: Spreader beam: widens the pick points, carries the spread as compression, keeps horizontal squeeze out of the load and holds the sling legs nearer vertical. An equalizer beam is a different device — it pivots to share load between two hoist lines or two cranes. A spreader bar counts as part of the lifted load and must carry a certified or manufacturer-established WLL (BC OHSR s.15.58 and s.15.60).
Q39easy
Who is responsible for ensuring a lift plan exists for a critical lift?
- A) The crane manufacturer's representative
- B) The certified crane operator only
- C) The rigging foreman and ironworker in charge
- D) The project's structural engineer only
Correct answer: C
The rigging crew (foreman/competent rigger) and the ironworker in charge of the lift, in coordination with the site supervisor, are responsible for preparing or implementing the lift plan for critical lifts. The engineer may provide structural input.
Key concept: Critical lift plan: prepared by a competent rigger/supervisor. Includes load weight, CG, sling sizes, crane capacity, ground conditions, and exclusion zone.
Q40hard
A 6x19 IWRC wire rope has a catalogue breaking strength of 50,000 kg. Applied with a safety factor of 5, the WLL is:
- A) 25,000 kg
- B) 250,000 kg
- C) 5,000 kg
- D) 10,000 kg
Correct answer: D
WLL = breaking strength ÷ design factor = 50,000 ÷ 5 = 10,000 kg. Five is the right divisor here because BC's OHS Regulation Table 15-1 sets a minimum design factor of 5 for conventional wire rope, for wire rope slings and for wire rope sling fittings. Dividing by 2 gives 25,000 kg, multiplying instead of dividing gives 250,000 kg, and a 10:1 factor gives 5,000 kg — none of those is the design factor for wire rope. Five is not a universal figure: the same table sets 4 for alloy steel chain slings and chain fittings, s.15.6(3) requires 10 for any rigging assembly used to support workers, and s.15.7 allows 2.5 to 3.5 for wire rope on a mobile crane depending on the line and on whether the crane is being erected. Alberta's OHS Code s.292.1(1) likewise rates running lines at 3.5 to 1, tugger lines and blocks and pendant or guy lines at 3 to 1, and winch lines at 2 to 1. Read the WLL off the tag whenever the component carries one; dividing breaking strength reproduces the tag only when you have used the design factor that actually governs that component.
Key concept: WLL = breaking strength ÷ design factor. 50,000 ÷ 5 = 10,000 kg. The divisor depends on the component and the use: BC OHSR Table 15-1 gives 5 for wire rope and wire rope slings, 4 for alloy steel chain slings and chain fittings, and s.15.6(3) requires 10 for any rigging assembly supporting workers. Read the tag when the component carries one.
Q41medium
What does IWRC stand for in wire rope classification?
- A) Independent Wire Rope Core
- B) Individual Wire Rope Core
- C) Inner Wound Rope Configuration
- D) Internal Wire Reinforced Construction
Correct answer: A
IWRC (Independent Wire Rope Core) is a wire rope core made from a separate small wire rope instead of fibre. It resists crushing on drums and sheaves far better than a fibre core and carries a somewhat higher breaking strength, so the rope of the same size and grade is rated for a higher working load limit.
Key concept: IWRC: Independent Wire Rope Core — stronger and much more crush resistant than a fibre core (FC) rope, so it is preferred where the rope is crushed on drums and sheaves, where loads are heavy, and at elevated temperature. Rotation is a separate property: a load free to spin on a single part of line needs rotation-resistant construction (19x7, 35x7), not IWRC.
Q42hard
A rigid steel weldment is picked on a four-leg bridle sling. Under British Columbia's OHS Regulation, the working load limit of the whole sling is limited to the working load limit of how many of its legs?
- A) Three of them, whichever three are chosen
- B) All four, since the four legs share the load
- C) Two of them, the pair on the same diagonal
- D) Whatever number a professional engineer sets
Correct answer: A
WorkSafeBC's OHS Regulation s. 15.33 (2) is one sentence: the working load limit of a sling with more than three legs is limited to the working load limit of any three legs of the sling. A fourth leg is allowed on the hook; it simply cannot be counted. The mechanics behind that are worth carrying to any jurisdiction. Four legs holding one rigid piece are statically indeterminate - there are more supports than the statics of the lift can define - so which legs are actually tight is decided by millimetres of leg length and by exactly where the pick points sit, not by symmetry. Nothing about the arrangement guarantees that all four come up tight together, so adding four leg capacities describes a lift that may not happen. The section does not stop at two, though: three is the cap it states. An engineer's stamp is the answer people reach for when a rule looks severe, but this subsection sets the cap itself and does not hand the number to anyone to reset. Two further limits ride along in the same section: the working load limit of no individual component of the assembly may be exceeded (15.33 (1)), and the load carried by any single leg of a bridle must not exceed the working load limit of that leg (15.33 (3)).
Key concept: WorkSafeBC OHS Regulation s. 15.33 (2): a sling with more than three legs is rated at the working load limit of any three of its legs, so the fourth leg on a bridle adds no capacity. Four legs on a rigid load are statically indeterminate, and small differences in leg length decide which ones take the pull. Also in the same section: no component of the assembly may be loaded past its own working load limit (15.33 (1)), and no single leg of a bridle may be loaded past its working load limit (15.33 (3)).
Q43hard
An ironworker inspects a 6×19 IWRC wire rope sling before a critical lift and finds 11 randomly distributed broken wires in one rope lay. What action should be taken?
- A) Tag the sling for monitoring and continued use
- B) Remove the sling from service immediately
- C) The sling may be used — the limit is 20 broken wires per rope lay
- D) The sling may be used if the broken wires are not load-bearing
Correct answer: B
ASME B30.9, para. 9-2.9.5(b)(1): a strand-laid or single-part wire rope sling must be removed from service at 10 randomly distributed broken wires in one rope lay, or 5 broken wires in one strand in one rope lay. Eleven randomly distributed breaks exceeds that limit, so the sling comes out of service immediately — tag it, segregate it so it cannot be picked up again, and report to the rigger-in-charge. Note what the standard does not say: B30.9 sets no broken-wire limit keyed to rope construction, so there is no separate 6×19 or 6×36 figure. Classification governs the minimum clear length of rope between splices (para. 9-2.3.2), not the wire count. The one construction that changes the count is the cable-laid sling, at 20 broken wires per lay. B30.9 is not merely an American reference here — it is adopted by regulation: Alberta OHS Code Part 21, s.297(1) requires wire rope slings manufactured on or after July 1, 2009 to meet ASME B30.9, and s.306 adds further removal triggers, including wear or corrosion affecting individual wires over more than one-third of the original rope diameter, bird-caging, kinking, and heat or arc damage. Beware of carrying figures across: provincial limits for running rope are different and tighter (Alberta s.306(2): 6 randomly distributed broken wires in one rope lay, or 3 in one strand), but a sling is not a running rope. Check the rigging part of your own province's regulation.
Key concept: Wire rope SLING removal (ASME B30.9 para. 9-2.9.5): 10 randomly distributed broken wires in one rope lay, or 5 in one strand in one rope lay. Cable-laid slings: 20 per lay. B30.9 sets no 6×19 or 6×36 broken-wire limit — construction affects clear length between splices, not the count. Also remove for kinking, crushing, bird-caging, heat or arc damage, corrosion, or localized abrasion reducing the nominal diameter by more than 5 percent. In Canada B30.9 is adopted by reference in provincial occupational health and safety regulation (e.g. Alberta OHS Code s.297), and s.306 adds wear or corrosion over more than one-third of the original rope diameter. Running rope uses different, stricter numbers (Alberta s.306(2): 6 per lay, or 3 in one strand) — do not apply them to slings.
Q44hard
A crane is lifting a 20,000 kg load at a 15m radius. The load chart shows maximum lift capacity at 15m is 18,000 kg (with all outriggers fully extended on firm ground). What should the ironworker signalperson communicate to the operator?
- A) Proceed — crane charts include a 10% safety margin for occasional overloads
- B) Stop the lift — it exceeds the chart capacity
- C) Proceed if the crane manufacturer approves in writing
- D) Proceed if the lift will be completed in under 2 minutes
Correct answer: B
Load chart values are maximums — a working lift must never exceed them. The margin between the chart rating and the crane's tipping or structural limit is not usable capacity. In Ontario, for example, rated capacity is determined to CSA Z150, and a crane may not be loaded beyond it except during load tests required by the manufacturer. Exceeding the chart rating creates an unacceptable risk of crane overturning. The lift must be stopped and re-planned: decrease the lift radius (boom in), reduce the load, or bring in a larger crane.
Key concept: Crane load chart ratings are maximums, and the margin built into them is not extra capacity. Never exceed rated capacity on a working lift. Hook block, slings and other lifting devices count against the rating.
Q45medium
An ironworker is rigging a steel plate that has sharp flame-cut edges, and a polyester web sling will bear directly on one of those edges. What has to be done before the plate is lifted?
- A) Double the sling so the added ply takes the cutting action
- B) Cut the rated load in half and lift the plate as it is rigged
- C) Fit corner protectors between the plate edges and the sling
- D) Take up the load slowly so the edge cannot saw the webbing
Correct answer: C
WorkSafeBC's rigging Part puts it in one line: 'When a sling is applied to a sharp edge of a load, the edge or the sling must be protected to prevent damage to the sling' (Occupational Health and Safety Regulation, Part 15, s. 15.39). Ontario reaches the same hazard from the other side - O. Reg. 213/91 s. 172 (3) provides that no sling or similar device for rigging or hoisting made of web-type fabric or nylon shall be used if it may be cut, and s. 172 (1) (a) requires rigging to be suitable for its intended use. So the plate does not fly on that sling while the edge can cut it. Corner protectors, edge guards or softeners between the edge and the webbing are what removes the exposure.
None of the other three answers takes the edge away. Doubling the sling lays a second ply against the same edge in the same place, and the edge starts on it as soon as the load comes on. Halving the load does not help either, because a cut is not a strength problem: webbing is severed by pressure concentrated over a small radius, which happens at loads far below the rating, and once the fibres are through, the remaining section lets go without warning. Taking the load up slowly still brings the full weight of the plate onto the edge, and the sling then works against it every time the plate swings or settles.
Note what s. 15.39 is written about - a sling, not webbing alone. Chain and wire rope resist a sharp edge far better than polyester does, but the duty to protect the edge or the sling does not change with the material, so choosing a different sling is a decision about what to rig with, not a way of skipping protection at the corner.
Key concept: A sling applied to a sharp edge of a load: protect the edge or the sling so the sling cannot be damaged (WorkSafeBC OHS Regulation s. 15.39). Ontario bars the use of a web-type fabric or nylon sling that may be cut (O. Reg. 213/91 s. 172 (3)). Corner protectors, edge guards or softeners are the fix; an extra ply, a derated load and a slow pick all leave the sling bearing on the edge, and a cut severs webbing at loads well under the rating. The duty attaches to any sling, so changing sling material does not remove it.
Q46hard
An ironworker must rig a 4,000 kg beam with an unknown centre of gravity. The beam is lifted with a spreader bar and two vertical wire rope slings of equal length. When lifted 150mm off the ground, one end rises higher than the other. What adjustment should be made?
- A) Use longer slings on the heavy end to compensate
- B) Add counterweights to the light end
- C) Increase crane boom angle to redistribute load
- D) Move the spreader connection point toward the heavy end
Correct answer: D
To balance an uneven lift, move the crane hook attachment (or spreader bar connection point) toward the heavy end — a shorter distance from hook to heavy end balances the lift. With a spreader bar and equal-length slings, the pickup point must align over the centre of gravity for a level lift. Moving the connection toward the heavy end shortens the moment arm on that side, creating balance. A trial lift at low height before full elevation allows safe adjustment.
Key concept: Rigging balance: trial lift 150-300mm off ground to verify balance. Adjust pickup point toward heavy end. Never carry a grossly unbalanced load at full height.
Q47medium
On an Ontario construction project, a mobile crane is lifting near an energized overhead distribution line with a nominal phase-to-phase voltage of 44 kV. The line owner has not installed protective devices or set up its own procedures. Under Ontario's Construction Projects regulation, what is the minimum distance that any part of the crane, its rigging or its load may be brought to the line?
- A) 1.5 m
- B) 4.5 m
- C) 6 m
- D) 3 m
Correct answer: D
O. Reg. 213/91, s. 188(2) says no object may be brought closer to an energized overhead conductor than the distance set in its Table, based on the conductor's nominal phase-to-phase voltage. The first band covers 750 volts or more, up to 150,000 volts, and requires 3 m. A 44 kV line (44,000 V) falls in that band. The 4.5 m distance is only for lines over 150,000 V up to 250,000 V, and 6 m is only for lines over 250,000 V. Picking either one for a distribution line means using the wrong voltage band. The Table sets no distance smaller than 3 m for any line of 750 V or more, so 1.5 m would put the load inside the legal limit. When a crane or its load could come within this distance, s. 188(4) to (8) also apply. The constructor needs written measures and procedures, warning devices and a sign at the operator's station, and a competent worker assigned as signaller who can see both the conductor and the equipment. The distances vary by province, so this answer is for Ontario only.
Key concept: Ontario O. Reg. 213/91 s. 188(2): minimum approach to energized overhead lines is 3 m for 750 V up to 150 kV, 4.5 m for over 150 kV up to 250 kV, and 6 m above 250 kV (phase-to-phase).