About this page
This is the complete written list of our free 420B Ironworker (Generalist) practice questions
— all 120 of them, with the correct answer marked, an explanation of
why it is correct, and a one-line key concept for revision.
Questions are grouped by the occupational standard topic areas used on the exam:
Structural Steel Erection, Rigging & Hoisting, Welding & Cutting, Blueprint Reading & Layout, Reinforcing Steel, Safety & Fall Protection, Tools & Equipment.
Reading is useful, but recall is what the exam tests — work through the
timed 420B quiz as well, which shuffles the questions
and saves the ones you get wrong.
Want these 120 questions offline?
The 420B Complete Question Bank
is the same 120 questions with full explanations in one printable PDF — study without a signal.
Get the 420B Question Bank — CA$13 →
Structural Steel Erection — 25 questions
Q1easy
What is the purpose of a base plate in a steel column installation?
- A) To hold the anchor bolts
- B) To spread the column load over the foundation
- C) To prevent corrosion of the column base
- D) To allow lateral adjustment after erection
Correct answer: B
A base plate distributes the concentrated column load over a larger bearing area on the concrete foundation, reducing bearing stress to within allowable limits.
Key concept: Base plate: distributes column point load over bearing area. Size determined by concrete bearing capacity.
Q2easy
A spud wrench is primarily used during steel erection to:
- A) Tighten high-strength bolts to final torque
- B) Align bolt holes and hold members in place
- C) Measure the plumb of columns
- D) Drive shear studs into decking
Correct answer: B
The tapered end of a spud wrench is inserted into misaligned bolt holes in connections to align them so bolts can be inserted, temporarily holding members in place. The wrench end is used to snug bolts temporarily.
Key concept: Spud wrench: tapered end aligns holes, wrench end snugs bolts. NOT used for final high-strength bolt tightening.
Q3medium
When installing high-strength bolts using the turn-of-nut method, what is the first step?
- A) Apply full final torque immediately
- B) Bring all bolts to snug-tight first
- C) Install all bolts finger-tight only
- D) Apply lubricant to all bolt threads
Correct answer: B
Turn-of-nut requires all bolts in the connection to be brought to the snug-tight condition first (full effort of an ironworker with a spud wrench), then a specified rotation is applied to achieve the minimum pretension.
Key concept: Turn-of-nut sequence: ALL bolts snug-tight first → then apply specified rotation (typically 1/3 to 2/3 turn depending on bolt length).
Q4medium
What is the minimum number of bolts that must be installed before erection bolts can be removed from a connection?
- A) At least one bolt installed in the connection
- B) At least two bolts or 25% of the bolt count, whichever is greater
- C) At least 50% of the total bolt count in the connection
- D) All bolts must be snug-tight before erection bolts can be removed
Correct answer: B
Per AISC and CISC requirements, a minimum of two bolts or 25% of the bolt group (whichever is greater) must be installed and snug-tight before erection bolts are removed.
Key concept: Minimum 2 bolts OR 25% of bolt group (whichever greater) must be installed before removing erection bolts.
Q5easy
What does "plumbing up" a steel structure mean?
- A) Installing the water supply lines before steel is covered
- B) Adjusting columns and beams to vertical and level
- C) Applying anti-corrosion primer to exposed steel
- D) Installing floor deck drainage systems
Correct answer: B
Plumbing up involves checking and adjusting the structure so columns are perfectly plumb (vertical) and beams are level before making final bolted or welded connections.
Key concept: Plumbing up: establishing plumb columns and level beams before final connections — done with theodolite/transit and turnbuckle bracing.
Q6medium
Direct Tension Indicators (DTIs) are small washers with raised bumps. A connection is properly pretensioned when:
- A) All bumps on the DTI are still fully raised
- B) The bumps compress to a specified feeler-gauge gap
- C) The DTI is cracked and the bumps disappear
- D) The bolt head has been rotated exactly 1/2 turn from snug-tight
Correct answer: B
DTIs work by compressing their raised protrusions as bolt pretension increases. When sufficient tension is reached, the gaps between the protrusions and the contact surface fall below the specified maximum refusal value, verified with a feeler gauge.
Key concept: DTI: bumps compress as bolt is tensioned. Feeler gauge checks that refuse (gap) is below specified value — indicates minimum pretension achieved.
Q7hard
According to AISC standards, what is the maximum anchor bolt tolerance for location in plan?
- A) ±3 mm (1/8 inch)
- B) ±6 mm (1/4 inch)
- C) ±13 mm (1/2 inch)
- D) ±25 mm (1 inch)
Correct answer: B
AISC Code of Standard Practice allows ±6 mm (±1/4 inch) tolerance for anchor bolt location in plan. Significant deviations require engineered repair or replacement.
Key concept: Anchor bolt location tolerance: ±6 mm (±1/4 in) in plan per AISC. Exceeding this requires engineer review before erection proceeds.
Q8medium
Temporary bracing during steel erection serves which primary purpose?
- A) To permanently resist wind loads in the finished structure
- B) To stabilize the partial structure against erection loads
- C) To support the weight of the ironworkers on the steel
- D) To mark the locations where permanent connections will be made
Correct answer: B
During erection, the structure is not yet a complete load-resisting system. Temporary bracing stabilizes the partially erected structure against gravity, wind, and erection equipment loads before permanent connections are complete.
Key concept: Temporary bracing: stabilizes structure before permanent connections are complete — the erector is responsible until structure is self-supporting.
Q9easy
What is a drift pin used for in steel erection?
- A) Hammering shear studs into floor decking
- B) Aligning bolt holes in steel connections
- C) Measuring the level of beam flanges
- D) Cutting steel members to length
Correct answer: B
A drift pin is a tapered steel pin driven through misaligned holes to align them so bolts can be inserted. It is similar in function to the tapered end of a spud wrench.
Key concept: Drift pin: tapered tool driven into misaligned bolt holes to align them. Never used as a permanent fastener.
Q10medium
Steel decking (floor deck) must be placed in what sequence relative to the beam below?
- A) It can be placed in any convenient order
- B) From the crane or access side outward
- C) Starting from the center of the bay and working outward
- D) Always starting at the column and working toward the beam midspan
Correct answer: B
Decking must be placed from the crane or access side outward, never placing unsupported deck ahead of the safe access limit. OSHA/OHS regulations prohibit placing loose decking more than two beam spans ahead of secured decking.
Key concept: Decking placement: crane side outward. Limits on loose decking ahead of secured decking — typically no more than 2 spans.
Q11hard
A column has a piece mark of W250x89. What does this designation mean?
- A) The column is 250 mm wide and weighs 89 kg total
- B) W-shape, 250 mm nominal depth, 89 kg per lineal metre
- C) Wide flange, 250 mm flange width, 89 mm web thickness
- D) The column is in grid line W, 250 mm from grid 8, 9th piece
Correct answer: B
W250x89 is a W-shape (wide flange) with approximately 250 mm nominal depth and a mass of 89 kg per metre of length. This is the CSA/metric designation for structural steel sections.
Key concept: W-shape designation: W[depth]x[mass per metre]. W250x89 = W-shape, ~250 mm deep, 89 kg/m.
Q12medium
What is the purpose of shear studs welded to the top flange of a steel beam?
- A) To provide connection points for safety lanyards
- B) To create composite action with the concrete slab
- C) To increase the buckling resistance of the top flange
- D) To attach the metal deck to the beam
Correct answer: B
Shear studs are welded to the beam top flange and embed in the concrete deck above. They transfer horizontal shear forces between the steel beam and slab, creating composite behaviour that significantly increases beam capacity.
Key concept: Shear studs: create composite beam action by transferring horizontal shear between steel beam and concrete slab.
Q13easy
Before making the final connection of a lifted steel member, a minimum of how many safety hooks or bolts must be in place?
- A) One safety hook or bolt
- B) Two safety hooks or bolts
- C) Three safety hooks or bolts
- D) The entire bolt group must be installed before releasing the crane
Correct answer: B
Per AISC erection safety requirements, at least two bolts or equivalent connections must be in place before releasing the crane hook from the member.
Key concept: Minimum two connections (bolts/hooks) required before releasing crane hook — prevents member from rotating or falling.
Q14medium
A "column splice" in a steel structure is located:
- A) At the foundation level where the column meets the base plate
- B) At an intermediate height of the column where two column pieces are joined
- C) At the beam-to-column connection at each floor level
- D) At the top of the column where the roof beam connects
Correct answer: B
Column splices join upper and lower column sections in tall buildings where a single column piece would be impractical to handle. They are typically located about 600 mm above a floor level for access.
Key concept: Column splice: joins column pieces at intermediate height — typically 600 mm above floor for access. Located away from points of maximum stress.
Q15hard
A325 and A490 are designations for high-strength structural bolts. Which statement is correct?
- A) A325 is stronger than A490 and preferred for most structural connections
- B) A490 has a higher proof load and minimum pretension than A325
- C) Both have identical minimum pretension requirements
- D) A490 bolts can be reused after being fully tensioned; A325 cannot
Correct answer: B
A490 bolts have higher yield and tensile strength than A325, resulting in higher minimum pretension requirements. Neither bolt type should be reused once fully tensioned (especially A490).
Key concept: A490 > A325 in strength and pretension requirements. A325: medium carbon steel. A490: alloy steel. Neither type should be reused after full tensioning.
Q16medium
When erecting steel in cold weather (below -20°C), what is the primary concern?
- A) High-strength bolts become over-tensioned due to thermal contraction
- B) Steel becomes brittle and prone to impact fracture
- C) Weld fumes become more toxic in cold air
- D) Crane hydraulic systems perform better and can lift more
Correct answer: B
Structural steel, especially older or high-strength grades, becomes increasingly brittle and susceptible to impact fracture at low temperatures. Impact loads from erection (drops, hammer blows) can initiate brittle fracture.
Key concept: Cold weather: steel brittleness increases. Avoid impact loads; preheat may be required for welding. Crane capacity also decreases in extreme cold.
Q17easy
What is the purpose of "levelling nuts" used with anchor bolt assemblies?
- A) To lock the anchor bolt to the foundation
- B) To set the base plate elevation before grouting
- C) To prevent the column from rotating during erection
- D) To provide the required pretension on the anchor bolt
Correct answer: B
Levelling nuts under the base plate allow the ironworker to adjust the plate precisely to exact elevation (plumb and level) before the column is grouted into final position.
Key concept: Levelling nuts: allow precise base plate elevation adjustment before grouting. Removed or incorporated into final grout as per design.
Q18medium
Tension control (TC) bolts are identified by a splined end. The installation is complete when:
- A) The bolt has been torqued to the specified value with a calibrated torque wrench
- B) The splined end shears off during installation
- C) The bolt head has been rotated 1/2 turn from snug-tight
- D) The direct tension indicator gap measures zero
Correct answer: B
TC bolts have a breakneck groove at the splined end. When minimum pretension is achieved, the torque reaction causes the spline to shear off cleanly, providing visual verification that the required minimum pretension has been reached.
Key concept: TC bolt: splined end shears off when minimum pretension is reached — provides self-indicating installation verification.
Q19hard
A steel erection drawing shows "ASTM A36" for the beam material. What is the minimum yield strength of A36 steel?
- A) 250 MPa (36 ksi)
- B) 345 MPa (50 ksi)
- C) 414 MPa (60 ksi)
- D) 550 MPa (80 ksi)
Correct answer: A
ASTM A36 (equivalent to CSA G40.21 Grade 300W) has a minimum yield strength of 250 MPa (36 ksi) and minimum tensile strength of 400–550 MPa (58–80 ksi).
Key concept: A36 steel: Fy = 250 MPa (36 ksi), Fu = 400 MPa minimum. Most common structural steel in older North American buildings.
Q20medium
What does the term "camber" mean when applied to a structural steel beam?
- A) The horizontal curvature of the beam due to lateral wind load
- B) A pre-set upward bow built into the beam to compensate for deflection under load
- C) The vertical angle of the beam connection at the column
- D) The distance between the top and bottom flanges of the beam
Correct answer: B
Camber is a deliberate upward curve fabricated into a beam so that under design load, the beam deflects back to a level position. Common in long-span or heavily loaded beams.
Key concept: Camber: intentional upward bow in beam that counteracts deflection under dead load, resulting in approximately level beam under service conditions.
Q21hard
During structural steel erection, an ironworker is bolting a beam connection. The engineer specifies A325 3/4" bolts in a slip-critical connection. What minimum number of bolts must be installed before the crane can release the member?
- A) One bolt per connection — sufficient for temporary stability
- B) All bolts must be installed and tightened before crane release
- C) Minimum 2 bolts per end, per the erection procedure
- D) 50% of final bolt count, installed hand-tight only
Correct answer: C
CISC and AISC erection guidelines require a minimum of 2 bolts per connection — or enough to safely support erection loads, as specified in the erection procedure or by the engineer — before the crane can release a member. One bolt provides insufficient rotation restraint — the connection can pivot. With 2 bolts at each end, the member is stable against rotation. Full bolt tightening follows per the erection sequence after multiple members create a stable structure.
Key concept: Erection bolting: minimum 2 bolts per connection before crane release. Final tightening follows erection sequence. Never release crane on a single-bolt connection.
Q22medium
An ironworker is connecting a steel column base plate to an anchor bolt pattern. Three of four anchor bolts are plumb and aligned, but the fourth is out of position by 25mm. What is the CORRECT course of action?
- A) Force the base plate onto all four bolts by driving with a sledgehammer
- B) Flame cut the misaligned bolt and re-drill the base plate
- C) Notify the engineer and GC for an engineering assessment
- D) Weld the base plate to the three correctly positioned bolts and leave the fourth unused
Correct answer: C
Anchor bolt misalignment is a structural deficiency that requires engineering assessment before proceeding — notify the engineer and general contractor. Forcing the base plate distorts the anchor bolt, potentially cracking the grout and concrete embedment. Flame cutting a structural anchor bolt changes its material properties and may be prohibited. The engineer must determine if the misalignment is within tolerance, whether repositioning is possible, or if redesign is needed.
Key concept: Anchor bolt misalignment: STOP and notify engineer. Never force base plates or cut structural anchor bolts without engineering direction.
Q23medium
An ironworker is erecting a multi-storey steel frame and notices that a column is out of plumb by 25mm in a 6m height (approximately 1:240 ratio). The spec tolerance is 1:500. What action is required?
- A) No action — 25mm is within the typical ±50mm erection tolerance
- B) Column is within tolerance — 1:240 is acceptable for multi-storey columns per CISC
- C) Column is out of tolerance — must be plumbed and restrained before the next tier is erected
- D) Tolerance applies only to the final structure — proceed and adjust at the end
Correct answer: C
CISC erection tolerances for column plumbness: typically ±1:500 (1mm per 500mm height). At 6m height, allowable deviation is 6000/500 = 12mm. The measured 25mm deviation exceeds this. Out-of-plumb columns must be corrected before adding more load (next tier) because each additional tier multiplies the eccentricity and increases the risk of progressive collapse. Use come-alongs or guy wires to plumb the column.
Key concept: Column plumb tolerance: typically ±1:500 per CISC. Correct out-of-plumb columns BEFORE adding additional loads or erecting higher tiers.
Q24hard
During erection of a steel structure, an ironworker notices the decking is buckling and the frame is deflecting more than expected as a concrete pour proceeds. What is the MOST likely cause and immediate action?
- A) Normal elastic deflection — continue the pour
- B) Concrete pump hose is creating point loads — relocate pump hose and check shoring plan
- C) Stop the pour, evacuate, and notify the engineer
- D) Speed up the pour to reduce load duration
Correct answer: C
Unexpected structural movement during a concrete pour is a serious warning sign of potential collapse — the structure may be overloaded or shores may be inadequate. Possible causes: shores inadequate for design load, concrete piling up (not spreading), formwork props kicked out, or deck load exceeding design. The safe action is to immediately stop the pour, ensure workers are clear of the affected area, and contact the engineer of record before proceeding. Progressive collapse can occur rapidly.
Key concept: Concrete pour monitoring: any unexpected deflection or movement = STOP immediately. Evacuate the area under and adjacent to the affected structure. Never accelerate a pour to outrun a developing problem.
Q25medium
An ironworker is placing shear studs on a composite steel beam using a drawn-arc stud gun. After welding, the inspection requires a bend test on 1% of studs per CSA S16. A stud is bent 30° and then straightened. The stud shows a cracked weld at the base. What is the required action?
- A) Accept the stud — bend testing is destructive and minor cracks are expected
- B) Replace the failed stud and test more studs at double rate
- C) Reject the entire beam — all studs must be replaced
- D) Cut and re-weld the cracked stud base only
Correct answer: B
CSA S16 shear stud inspection: a failed bend test requires replacement of the failed stud and an increased testing rate. If a stud cracks at the weld during a 30° bend test, the weld quality is suspect. Replace the failed stud with a new one welded with correct parameters, and test additional studs at twice the original rate to verify that adjacent studs are acceptable. A full beam replacement is not required for an isolated failure.
Key concept: Shear stud QC: 30° bend test, 1% per CSA S16. Failure = replace that stud + increase inspection rate. Weld failure causes: contamination, moisture, wrong current, worn ferrule.
Rigging & Hoisting — 23 questions
Q26easy
What is the Working Load Limit (WLL) of a rigging component?
- A) The maximum load the component has ever been tested to
- B) The maximum load it may lift in normal service
- C) The breaking strength of the component divided by 5
- D) The load at which the component begins to permanently deform
Correct answer: B
WLL (also called Safe Working Load) is the maximum load a rigging component is authorized to lift under normal working conditions, accounting for the safety factor from the breaking strength.
Key concept: WLL = maximum authorized lifting load. NOT the same as breaking strength. Never exceed WLL.
Q27medium
A wire rope sling has a WLL of 10,000 kg at 90°. What is the effective WLL when used as a choker hitch?
- A) 10,000 kg — choker hitch does not reduce capacity
- B) 8,000 kg — choker hitch reduces capacity by 20%
- C) 7,500 kg — choker hitch reduces capacity by 25%
- D) 5,000 kg — choker hitch reduces capacity by 50%
Correct answer: C
A standard choker hitch reduces the rated capacity of a wire rope sling to 75% of its vertical rating — a 25% reduction — when the angle of choke is 120° or greater, due to the bending and pinching of the rope at the choke point (10,000 kg × 0.75 = 7,500 kg). At choke angles below 120° the capacity is reduced further.
Key concept: Choker hitch: reduces WLL by approximately 25% (0.75 factor) at choke angles ≥120° per ASME B30.9. Basket hitch = 2× vertical WLL (at 90°). Single vertical = 1× WLL.
Q28medium
Two slings of equal length are used in a two-leg bridle hitch to lift a 4,000 kg load. The angle between each sling and the horizontal is 60°. What is the approximate load on each sling leg?
- A) 2,000 kg
- B) 2,310 kg
- C) 2,830 kg
- D) 4,000 kg
Correct answer: B
Each sling carries half the load adjusted for angle. Half load = 2,000 kg. At 60° from horizontal, efficiency factor = 0.866. Leg tension = 2,000 / 0.866 ≈ 2,310 kg.
Key concept: Two-leg bridle sling leg tension = (Total load / 2) ÷ sin(angle from horizontal). At 60°: 2,000 ÷ 0.866 ≈ 2,310 kg per leg.
Q29easy
During a crane lift, what is the purpose of a tagline?
- A) To provide an extra rigging connection in case the main sling fails
- B) To control the rotation and swing of the load
- C) To measure the length of the lift path
- D) To attach the load to the crane hook
Correct answer: B
Taglines allow workers to guide and control a suspended load from a safe distance, preventing rotation and swing without placing workers directly under or near the load.
Key concept: Tagline: controls load rotation and swing from a safe distance. Must be long enough to keep workers outside the swing radius.
Q30hard
Wire rope condition requires removal from service when the number of broken wires in one lay length exceeds:
- A) 2 randomly distributed broken wires in any rope strand
- B) 10 randomly distributed broken wires in one rope lay length, or 5 in one strand
- C) Any broken wire — the rope must be replaced immediately
- D) 20% of the total number of wires in the rope cross-section
Correct answer: B
ASME B30.2 and most jurisdictional codes specify removal when there are 10+ randomly distributed broken wires in one lay length, or 5+ in a single strand. Visual inspection must also check for kinking, corrosion, and reduction in diameter.
Key concept: Wire rope removal criteria: 10 broken wires in one lay length (random) or 5 in one strand. Also remove for kinks, bird-caging, corrosion, or >1/3 diameter reduction in wire.
Q31medium
What is the minimum D:d ratio (sheave diameter to wire rope diameter) recommended for standard wire rope?
- A) 6:1
- B) 12:1
- C) 18:1
- D) 26:1
Correct answer: D
The standard minimum D:d ratio for wire rope on a sheave is 26:1 for 6×19 construction and varies by rope construction. Using smaller sheaves causes excessive bending fatigue and reduces rope life.
Key concept: D:d ratio: minimum 26:1 for most wire rope. Smaller D:d = more bending stress = faster fatigue. ALWAYS check manufacturer specifications.
Q32easy
When installing wire rope clips (U-bolt clips), which way do the U-bolts face?
- A) U-bolts on the live (load-bearing) end, saddle on the dead end
- B) U-bolts on the dead end, saddle bears on the live end
- C) Either direction is acceptable
- D) U-bolts face the direction of load travel
Correct answer: B
The saddle (not the U-bolt) must bear on the live rope end because the U-bolt creates a stress concentration that would damage the load-bearing rope. "Never saddle a dead horse" — saddle on live end, U-bolt on dead end.
Key concept: "Never saddle a dead horse" — saddle on live (load-bearing) rope, U-bolt on dead end. Minimum 3 clips; spacing = 6× rope diameter.
Q33medium
A screw-pin shackle is used where:
- A) Permanent or semi-permanent rigging connections are needed
- B) The rigging will be frequently removed and reattached
- C) High side-loading conditions exist
- D) No shackle pin rotation is expected
Correct answer: B
Screw-pin shackles can be assembled and disassembled quickly without tools, making them the correct choice for temporary or frequently changed rigging configurations. The other options are incorrect: screw-pin shackles should NOT be used in applications where the pin can rotate or unscrew under load (such as running rigging or slings that rotate) — bolt-type (cotter-pin) shackles are required there. Screw-pin shackles are not rated higher than bolt-type shackles of the same size; they are simply easier to open and close. For permanent installations or overhead lifts with load movement, always use bolt-type shackles with cotter pins.
Key concept: Screw-pin shackle: easy to install/remove — for temporary or frequently changed rigging. Bolt-type (safety) shackle: for permanent or semi-permanent rigging where pin could unscrew.
Q34hard
Before a critical lift, the rigger calculates the load center of gravity (CG). If the CG is NOT centered between the sling attachment points, what will happen?
- A) The lift will be stable because slings self-equalize
- B) The load will tilt toward the heavier end
- C) The load will spin in the direction of the CG offset
- D) The slings will slip to equalize the load automatically
Correct answer: B
When the CG is offset, the load tilts toward the heavier side. The sling leg closer to the CG — the one over the heavier end — carries a disproportionately higher load, which must be accounted for in sling selection.
Key concept: Off-center CG: load tilts toward heavier end; that sling leg carries more load. Use an equalizer beam or adjust pick points to balance.
Q35medium
Which crane hand signal means "STOP"?
- A) Arm extended, palm facing down, moving arm side to side
- B) Arm extended, palm facing the crane operator, fist closed
- C) Both arms raised above head
- D) One arm raised, rotating at the elbow
Correct answer: A
The universal crane signal for STOP is arm extended horizontally with palm facing down, moved side to side. EMERGENCY STOP uses both arms in this position.
Key concept: Crane STOP signal: arm extended, palm down, move side to side. In an emergency, ANYONE on site can give a stop signal and the operator MUST stop.
Q36easy
What does "two-blocking" mean on a crane?
- A) Using two sling blocks to double the crane capacity
- B) The hook block contacts the boom tip sheave
- C) Locking two rigging components together to prevent separation
- D) Installing two taglines on a single load
Correct answer: B
Two-blocking occurs when the hook block rises and contacts the boom tip sheave block or lower load block assembly. The resulting shock load can snap the rope or cause the load to fall — a catastrophic failure.
Key concept: Two-blocking: hook block contacts boom tip — catastrophic failure risk. Modern cranes have anti-two-block devices. Operator must watch for this.
Q37medium
Synthetic web slings must be removed from service when:
- A) Colour fading or minor surface abrasion is visible
- B) There are cuts, tears, or chemical burns visible
- C) The sling has been used for more than 500 lifts
- D) Only when the rated capacity tag is illegible
Correct answer: B
Synthetic slings are removed from service for any cuts or tears that penetrate fibres, acid or caustic burns, heat damage above 90°C, loss of more than 10% of sling width, distorted hardware, or missing/illegible capacity tags.
Key concept: Remove synthetic sling for: cuts, tears, burns (chemical/heat), loss of width >10%, missing tag, or distorted hardware. They show less warning before failure than wire rope.
Q38hard
A load weighs 8,000 kg. Two slings of equal length are rigged in a basket hitch, each at 45° from horizontal. What is the approximate tension in each sling leg?
- A) 4,000 kg
- B) 5,660 kg
- C) 8,000 kg
- D) 11,310 kg
Correct answer: B
Each sling leg carries half the load but at 45°, the tension increases. Leg tension = (Total load / 2) ÷ sin(45°) = 4,000 ÷ 0.707 ≈ 5,660 kg per sling.
Key concept: Basket hitch leg tension at 45°: (W/2) ÷ sin(45°) = (W/2) ÷ 0.707. At 45° each leg carries 141% of the load it would carry vertically.
Q39medium
What is an equalizer beam (spreader beam) used for in rigging?
- A) To balance the weight of the crane boom
- B) To distribute the load between multiple pick points
- C) To spread two crane boom sections for tandem lifts
- D) To measure the balance point of a long structural member
Correct answer: B
An equalizer beam distributes the load between multiple sling attachment points, controls sling angles to prevent sling angle problems, and prevents horizontal compressive forces from being transmitted into the load.
Key concept: Equalizer/spreader beam: distributes load over multiple pick points, controls sling angles, prevents horizontal compression forces in the load.
Q40easy
Who is responsible for ensuring a lift plan exists for a critical lift?
- A) The certified crane operator only
- B) The rigging foreman and ironworker in charge
- C) The project's structural engineer only
- D) The crane manufacturer's representative
Correct answer: B
The rigging crew (foreman/competent rigger) and the ironworker in charge of the lift, in coordination with the site supervisor, are responsible for preparing or implementing the lift plan for critical lifts. The engineer may provide structural input.
Key concept: Critical lift plan: prepared by a competent rigger/supervisor. Includes load weight, CG, sling sizes, crane capacity, ground conditions, and exclusion zone.
Q41medium
What is the minimum safety factor (design factor) for rigging hardware in most Canadian jurisdictions?
Correct answer: D
Most Canadian OHS regulations and ASME B30 standards specify a minimum safety factor (breaking strength ÷ WLL) of 5:1 for rigging hardware including wire rope, shackles, and hooks.
Key concept: Rigging hardware safety factor: 5:1 (breaking strength ÷ WLL). Higher factors apply for personnel lifting (10:1 minimum).
Q42hard
A 6x19 IWRC wire rope has a catalogue breaking strength of 50,000 kg. Applied with a safety factor of 5, the WLL is:
- A) 5,000 kg
- B) 10,000 kg
- C) 25,000 kg
- D) 250,000 kg
Correct answer: B
WLL = Breaking Strength ÷ Safety Factor = 50,000 ÷ 5 = 10,000 kg. The 5:1 safety factor (design factor) is the minimum required by Canadian OH&S regulations and ASME B30 standards for rigging hardware, and it accounts for dynamic loading, shock loading, fatigue, wear, and inspection intervals. Common wrong answers: using 4:1 (which is the factor for some overhead hoisting equipment under specific standards, not general rigging) or 3:1 (which is far too low and not acceptable for any rigging hardware under Canadian codes). Always verify WLL on the component’s tag — never calculate from breaking strength alone without confirming the applicable standard.
Key concept: WLL = Breaking strength ÷ Safety factor. With SF=5: WLL = 50,000 ÷ 5 = 10,000 kg.
Q43medium
What does IWRC stand for in wire rope classification?
- A) Individual Wire Rope Core
- B) Independent Wire Rope Core
- C) Internal Wire Reinforced Construction
- D) Inner Wound Rope Configuration
Correct answer: B
IWRC (Independent Wire Rope Core) is a wire rope core made from a separate wire rope instead of fibre. It provides better crush resistance and allows slightly higher WLL compared to a fibre core rope.
Key concept: IWRC: Independent Wire Rope Core — stronger, more crush resistant than fibre core (FC/FSWR). Preferred for use with rotating or compression loads.
Q44hard
An ironworker needs to lift a 6,000 kg steel beam using a two-leg wire rope sling with each leg at 45° from vertical. What is the tension in each sling leg?
- A) 3,000 kg — equal half the total load
- B) 4,243 kg — tension increases with sling angle
- C) 6,000 kg — each leg carries the full load at 45°
- D) 2,121 kg — angle reduces load per leg
Correct answer: B
Sling leg tension = (Load / number of legs) × (1 / cos θ). θ = 45° from vertical. Tension = (6,000/2) × (1/cos 45°) = 3,000 × 1.414 = 4,243 kg per leg. The load on each sling leg INCREASES as the angle from vertical increases. At 60°, the factor is 2.0 — each leg carries the full load. This is why angles beyond 60° from vertical are generally avoided.
Key concept: Sling tension formula: T = (W/n) × (1/cos θ). At 30°: factor=1.15. At 45°: 1.41. At 60°: 2.0. Never exceed 60° from vertical for general lifts.
Q45hard
An ironworker inspects a wire rope sling before a critical lift and finds 4 broken wires in one rope lay of a 6×19 IWRC wire rope. What action should be taken?
- A) The sling may be used — limit is 6 broken wires per lay
- B) Remove the sling from service immediately
- C) Tag the sling for monitoring and continued use
- D) The sling may be used if the broken wires are not load-bearing
Correct answer: B
ASME B30.9 discard criteria for 6×19 wire rope: 3 broken wires in one rope lay or 6 in any rope lay length of 6 times the rope diameter. Finding 4 broken wires in one lay exceeds the 3-wire limit — remove from service immediately, cut into short pieces to prevent reuse, and report to the rigger-in-charge. All wires in a sling assembly must remain serviceable — there are no partial-use allowances.
Key concept: Wire rope inspection (ASME B30.9): 6×19 rope discard at ≥3 broken wires/lay. 6×37 rope: ≥6/lay. Also discard for: kinking, crushing, heat damage, corrosion, reduction >1/3 original diameter.
Q46hard
A crane is lifting a 20,000 kg load at a 15m radius. The load chart shows maximum lift capacity at 15m is 18,000 kg (with all outriggers fully extended on firm ground). What should the ironworker signalperson communicate to the operator?
- A) Proceed — crane charts include a 10% safety margin for occasional overloads
- B) Stop the lift — it exceeds the chart capacity
- C) Proceed if the lift will be completed in under 2 minutes
- D) Proceed if the crane manufacturer approves in writing
Correct answer: B
Load chart values are maximums — they MUST NOT be exceeded under any circumstances. Crane load charts already include safety factors per CSA Z150. Exceeding the chart rating voids the chart, creates an unacceptable risk of crane overturning, and is a criminal liability. The lift must be stopped and re-planned: decrease the lift radius (boom in), improve ground bearing with outrigger pads, or bring in a larger crane.
Key concept: Crane load charts are absolute maximums including all safety factors. NEVER exceed rated capacity. Load = hook load + rigging weight + load block weight.
Q47medium
An ironworker is using a synthetic web sling to lift a steel plate. The plate has sharp edges that could contact the sling. What protection MUST be used?
- A) No protection needed — synthetic slings are rated for contact with steel
- B) Use edge protection softeners or switch to a chain sling
- C) Reduce the Working Load Limit by 25% and proceed without edge protection
- D) Double the synthetic sling to add strength against cutting
Correct answer: B
Sharp edges will cut synthetic web slings even at loads well below the WLL. Synthetic slings (nylon, polyester) have no resistance to sharp metal edges. Use edge protection — corner protectors, edge guards, softeners — or switch to chain slings or wire rope when lifting objects with sharp edges. This is not a load-reduction issue — a cut sling fails catastrophically regardless of load.
Key concept: Synthetic slings + sharp edges = prohibited without corner protection. Chain slings or wire rope slings are appropriate for sharp-edged loads without protection.
Q48hard
An ironworker must rig a 4,000 kg beam with an unknown centre of gravity. The beam is lifted with a spreader bar and two vertical wire rope slings of equal length. When lifted 150mm off the ground, one end rises higher than the other. What adjustment should be made?
- A) Add counterweights to the light end
- B) Move the spreader connection point toward the heavy end
- C) Use longer slings on the heavy end to compensate
- D) Increase crane boom angle to redistribute load
Correct answer: B
To balance an uneven lift, move the crane hook attachment (or spreader bar connection point) toward the heavy end — a shorter distance from hook to heavy end balances the lift. With a spreader bar and equal-length slings, the pickup point must align over the centre of gravity for a level lift. Moving the connection toward the heavy end shortens the moment arm on that side, creating balance. A trial lift at low height before full elevation allows safe adjustment.
Key concept: Rigging balance: trial lift 150-300mm off ground to verify balance. Adjust pickup point toward heavy end. Never carry a grossly unbalanced load at full height.
Welding & Cutting — 18 questions
Q49easy
Which welding process is most commonly used for structural steel erection field welds?
- A) GTAW (TIG welding)
- B) GMAW (MIG welding)
- C) SMAW and FCAW
- D) Submerged Arc Welding (SAW)
Correct answer: C
SMAW (stick) and FCAW (flux-cored) are the standard field welding processes for structural work due to their tolerance for wind, outdoor conditions, and out-of-position welding capability.
Key concept: Structural field welding: SMAW and FCAW. GTAW and SAW are shop processes. FCAW is increasingly preferred for productivity in favourable conditions.
Q50medium
What does CSA W47.1 govern?
- A) The testing and inspection of completed structural welds
- B) The certification of fusion welding companies in Canada
- C) The classification of welding consumables
- D) The design of structural steel connections
Correct answer: B
CSA W47.1 (Certification of Companies for Fusion Welding of Steel) governs the certification of welding companies — it certifies the company, not individual welders. Certified companies must have qualified welding supervisors, approved welding procedures (WPSs), and a documented quality control system. This is different from: CSA W59 (which governs the design and fabrication requirements for welded steel structures), CSA W178.2 (which certifies individual welding inspectors), and AWS D1.1 (the American Structural Welding Code used as a reference). On a Canadian structural steel project, the fabricator or erector must hold a current CSA W47.1 certification — this is a mandatory contract requirement.
Key concept: CSA W47.1: certification standard for Canadian welding companies. Welding shops must be W47.1-certified to produce structural welds covered by the NBC and provincial building codes.
Q51medium
Why is preheat required when welding high-strength or thick structural steel?
- A) To speed up the welding process by reducing arc strike difficulties
- B) To slow cooling and prevent hydrogen cracking
- C) To soften the steel so the electrode melts easier
- D) To prevent the steel from expanding during welding
Correct answer: B
Preheating slows the cooling rate after welding, allowing hydrogen to diffuse out of the HAZ and preventing the formation of hard, brittle martensite microstructures in the HAZ that are susceptible to hydrogen-induced cracking.
Key concept: Preheat reduces cooling rate → less hydrogen trapping → less brittle HAZ → lower risk of hydrogen-induced (cold) cracking in high-strength or thick steel.
Q52easy
What weld symbol indicates a fillet weld?
- A) A right triangle on the reference line
- B) A circle on the reference line
- C) A square groove symbol
- D) A wavy line below the reference line
Correct answer: A
A fillet weld is shown as a right triangle on the weld symbol, with the perpendicular leg always on the left and the hypotenuse facing outward (away from the joint). The weld size is shown to the left of the symbol.
Key concept: Fillet weld symbol: right triangle with vertical leg on left. Size = to left of symbol. Arrow side = below line; other side = above line.
Q53medium
A structural drawing shows a fillet weld with the size designation "10" on the weld symbol. This means:
- A) The weld is 10 mm long
- B) The fillet weld leg size is 10 mm
- C) There are 10 weld passes required
- D) The weld must withstand 10 kN/mm of force
Correct answer: B
The number to the left of the fillet weld symbol indicates the leg size in millimetres (or inches in imperial drawings). A 10 mm fillet weld has legs of 10 mm on each fusion face.
Key concept: Fillet weld size: leg size in mm shown left of triangle symbol. Throat = 0.707 × leg size. Weld size determines capacity.
Q54hard
What is the effective throat of a 12 mm fillet weld?
- A) 6 mm
- B) 8.5 mm
- C) 10 mm
- D) 12 mm
Correct answer: B
For a standard fillet weld with equal legs, the theoretical throat = leg × sin(45°) = 12 × 0.707 ≈ 8.5 mm. The effective throat is used to calculate weld strength.
Key concept: Effective throat of fillet weld = 0.707 × leg size. For 12 mm fillet: 12 × 0.707 = 8.5 mm throat.
Q55medium
Carbon arc gouging is used in structural ironwork primarily for:
- A) Cutting plate to exact dimensions in the fabrication shop only
- B) Removing defective welds and back-gouging root passes
- C) Welding thick plates that require deep penetration
- D) Preheating steel before welding
Correct answer: B
Carbon arc gouging uses a carbon electrode and compressed air to melt and blow away metal. It is the standard method for removing defective welds, back-gouging root passes of groove welds for full penetration, and excavating weld repairs.
Key concept: Carbon arc gouging: removes defective welds, back-gouges root passes. Produces fumes — requires adequate ventilation and PPE.
Q56easy
A complete joint penetration (CJP) groove weld requires:
- A) Weld metal to fill the groove at least halfway
- B) Weld metal penetrating the joint's full thickness
- C) At least three weld passes in the groove
- D) Post-weld heat treatment regardless of steel grade
Correct answer: B
A CJP weld requires weld metal to completely penetrate the full thickness of the joint, filling the entire cross-section and achieving full fusion. It is required in joints subject to tension, cyclic, or seismic loading.
Key concept: CJP (Complete Joint Penetration): weld metal through full thickness. Required for tension-loaded joints and seismic connections. Back-gouging or backing bar needed.
Q57medium
What does a "flag" on a welding symbol indicate?
- A) The weld must be inspected by UT (ultrasonic testing)
- B) The weld is to be made in the field (field weld)
- C) The weld is a complete joint penetration weld
- D) All welds on the drawing must be made in this location
Correct answer: B
A flag on the weld symbol reference line indicates a field weld — one that is to be made during erection at the job site, as opposed to a shop weld made during fabrication.
Key concept: Flag on weld symbol = field weld (made during erection). Circle at arrow/tail junction = weld all around.
Q58hard
When welding ASTM A572 Grade 50 steel with SMAW, the minimum preheat temperature for material 38 mm thick or greater is approximately:
- A) No preheat required
- B) 10°C (50°F)
- C) 66°C (150°F)
- D) 107°C (225°F)
Correct answer: D
Per AWS D1.1 Table 4.2, for A572 Gr.50 (Group II steel) and material thickness over 38 mm (1.5 in), the minimum preheat temperature is 107°C (225°F).
Key concept: Preheat for A572 Gr.50 at >38 mm: 107°C (225°F) per AWS D1.1. Higher-strength steel and greater thickness = higher preheat requirement.
Q59medium
What is the primary cause of porosity in SMAW structural welds?
- A) Excessive arc length causing nitrogen absorption from air
- B) Moisture or oil contamination on metal or electrode
- C) Using E7018 electrodes at too low an amperage
- D) Welding on galvanized steel without preheat
Correct answer: B
Porosity is caused by gas trapped in the solidifying weld metal. Moisture and oil on the base metal or electrode coating are the most common sources — they decompose under the arc heat and produce hydrogen and CO gases.
Key concept: Porosity causes: moisture/oil/contamination on base metal or electrode. Prevention: clean metal, dry electrodes, proper preheat.
Q60easy
Plasma arc cutting (PAC) is used by ironworkers primarily because:
- A) It is slower and more precise than OFC for carbon steel
- B) It cuts stainless, aluminum, and non-ferrous metals
- C) It is cheaper and safer than oxyfuel cutting
- D) It requires no gas supply of any kind
Correct answer: B
OFC relies on oxidation and only works on ferrous metals (carbon steel). PAC uses an ionized gas jet and works on any conductive metal that OFC cannot cut, including stainless steel, aluminum, and copper alloys.
Key concept: PAC cuts any conductive metal including stainless and aluminum — OFC only works on carbon/low-alloy steel by oxidation.
Q61medium
A weld inspection reveals "undercut" along the toe of a fillet weld. What caused this?
- A) Insufficient preheat temperature
- B) Excessive travel speed or amperage at the toe
- C) Moisture in the electrode coating
- D) Insufficient root opening in the groove
Correct answer: B
Undercut is a groove melted into the base metal at the weld toe that is not filled by weld metal. It is caused by excessive heat, amperage, or travel speed melting the base metal at the toe, or an improper electrode angle.
Key concept: Undercut: groove at weld toe from excessive heat/speed. Reduces effective thickness of base metal. Must be repaired if depth exceeds 1 mm or 25% of base metal thickness.
Q62medium
In structural steel work, what does CSA W59 govern?
- A) The certification of welders for structural work
- B) The design requirements for welded steel construction
- C) The testing of welding consumables
- D) The safety requirements for welding fumes
Correct answer: B
CSA W59 (Welded Steel Construction — Metal Arc Welding) specifies design, fabrication, and erection requirements for welded steel structures in Canada, including joint design, acceptable workmanship, and inspection criteria. It is often confused with: CSA W47.1 (which certifies welding companies — not design requirements), CSA W59 is the structural welding CODE (what must be built and to what standard), while W47.1 is the company CERTIFICATION standard (who is allowed to build it). AWS D1.1 is the equivalent American standard; many Canadian projects reference both. For Red Seal ironworker exam: know that W59 = fabrication and design standard; W47.1 = company certification; W178.2 = inspector certification.
Key concept: CSA W59: standard for welded steel construction — specifies joint design, workmanship, and inspection. Works in conjunction with CSA W47.1 (company certification).
Q63hard
An ironworker is welding a moment connection on a seismic force-resisting frame. What additional requirement applies compared to a regular gravity connection?
- A) Higher amperage settings must be used to achieve deeper penetration
- B) Notch-tough weld metal with CVN requirements
- C) All welds must be made using GTAW process
- D) The connection must be welded vertically-up only
Correct answer: B
Seismic connections experience large cyclic deformations and must absorb energy through plastic deformation without fracture. Weld metal must meet notch-toughness requirements verified by CVN (Charpy V-notch) impact testing at -29°C or lower to prevent brittle fracture.
Key concept: Seismic welding: weld metal must meet Charpy V-notch (CVN) toughness requirements. Higher heat input and preheat may be specified. AISC 358/CSA S16 govern seismic connections.
Q64hard
An ironworker is welding a moment connection on a structural beam using E71T-8 flux-cored wire. The WPS specifies a minimum preheat of 150°C. The ambient temperature is -5°C and the base metal temperature is 4°C. What must be done before welding?
- A) Begin welding immediately — preheat is for thick plate only
- B) Preheat the joint to 150°C and verify with temp sticks
- C) No preheat needed when ambient is above freezing (-5°C is the ambient air, not metal)
- D) Increase wire speed to compensate for cold metal temperature
Correct answer: B
Preheat requirements are based on base metal temperature, not ambient air temperature. At 4°C base metal temperature with a 150°C preheat requirement, the joint must be heated to 150°C minimum with a heating torch before striking the arc. Cold steel increases the risk of hydrogen-induced cracking (HIC). Verify with temperature sticks or a contact pyrometer immediately before welding and maintain interpass temperature throughout.
Key concept: Preheat: applied to base metal, not air temperature. Verify with temp sticks or pyrometer. E71T-8 is a self-shielded FCAW wire used for structural steel — preheat critical in cold conditions.
Q65hard
An ironworker performing a fillet weld on a structural connection notices the weld is developing longitudinal cracking in the weld bead shortly after each pass. The base metal is A36 and filler is E7018. What is the MOST likely cause?
- A) Travel speed is too slow — too much heat input
- B) Hydrogen cracking from moisture in the electrode
- C) Base metal carbon content is too high for E7018
- D) Arc voltage is too high, causing undercutting at the toes
Correct answer: B
Longitudinal (centreline) cracking shortly after welding indicates hydrogen-induced cracking (HIC). E7018 is a low-hydrogen electrode that must be kept in a rod oven at 120-150°C after opening the package — an electrode left out of the oven absorbs moisture. Moisture absorbed by the flux releases hydrogen into the weld pool; hydrogen migrates to areas of high residual stress (weld centreline) and causes cracking — sometimes hours after welding. Re-dry electrodes at 370°C for 1 hour if moisture absorption is suspected.
Key concept: E7018 low-hydrogen electrode: must be stored at 120°C in rod oven. Moisture = HIC risk. Redry at 370°C/1hr max 3 times. Longitudinal cracking = HIC until proven otherwise.
Q66medium
An ironworker-welder is completing a structural weld and notices arc blow causing the arc to deflect away from the joint, creating a poor weld profile. The process is SMAW with DC+ polarity. What is the MOST effective corrective action?
- A) Increase welding current to overcome the arc deflection
- B) Switch to AC or reposition the work lead
- C) Change to a different electrode classification
- D) Reduce arc length to compensate for deflection
Correct answer: B
Arc blow occurs in DC welding when magnetic fields deflect the arc. Corrective actions: 1) Switch to AC polarity (AC does not produce arc blow). 2) Move the work ground clamp closer to the weld, or place it on both ends. 3) Angle the electrode toward the direction of blow. 4) Weld toward the ground connection. 5) Reduce current. Arc blow is most common at ends of joints and near heavy metal sections.
Key concept: Arc blow: DC phenomenon caused by stray magnetic fields. Fix: switch to AC, reposition ground lead, angle electrode into blow direction, or weld toward ground.
Blueprint Reading & Layout — 15 questions
Q67easy
On a structural steel drawing, what do "column grid lines" represent?
- A) The centreline of each floor level in the building
- B) Reference lines used to locate columns in plan
- C) The maximum allowable column spacing per code
- D) Lines showing where expansion joints are required
Correct answer: B
Column grid lines are imaginary intersecting reference lines (typically numbered 1, 2, 3… in one direction and lettered A, B, C… in the other) that establish the planned column and structural element locations on a structural drawing. They are NOT column centre-lines in the sense of indicating column size or section — they are location references only. Grid line intersections identify each column by coordinates (e.g., Column B-3). This is different from dimension lines (which show actual measurements between members) and elevation marks (which show height). All trades on a project use the same grid reference to coordinate work — so an ironworker, concrete crew, and mechanical contractor all reference Column B-3 the same way.
Key concept: Column grid lines: numbered (N-S) and lettered (E-W) reference lines used to identify column locations. Column at intersection of line B and 3 = "B3".
Q68easy
On a structural drawing, what does the symbol "EL. 12500" typically mean?
- A) The element has a design load of 12,500 kg
- B) The point's elevation above the project datum
- C) Element number 12,500 on the fabrication list
- D) The element is 12,500 mm in length
Correct answer: B
EL. (Elevation) followed by a number (e.g., EL. 12500) indicates the finished height of that point in millimetres above the project datum — typically the finished first floor (FF) established at EL. 0.000. Elevations above datum are positive; below datum are negative. This is different from: a grid coordinate (which locates a point in plan, not in height), a dimension (which measures distance between two specific points), or a TOS/BOS notation (which is a specific elevation of the top or bottom of a steel member). When setting anchor bolts or erecting columns, always verify the elevation against the structural drawings — not the architectural drawings, which may use a different datum.
Key concept: EL. = elevation above project datum. EL. 12500 = 12.5 metres above datum (first floor 0.000 typically set as datum).
Q69medium
What is a "piece mark" on a structural drawing?
- A) A quality mark stamped by the inspector to approve a weld
- B) A unique identifier for each fabricated member
- C) A mark indicating where a weld is required
- D) The AISC classification number for the steel section
Correct answer: B
Piece marks (or erection marks) are unique identifiers (e.g., C1, B7, G12) assigned to each fabricated steel member in the structural steel package for tracking and erection — correlating shop drawings with fabricated pieces and the erection plan.
Key concept: Piece mark: unique identifier on each fabricated steel member. Matches the mark on the erection drawing and painted on the member. Used to place each piece in the correct location.
Q70medium
On a structural drawing, the designation "W460x97" refers to:
- A) A wide flange beam with 460 mm nominal depth and 97 kg/m linear mass
- B) A welded plate girder with 460 mm web and 97 mm flange
- C) A wind-load beam in grid W, 460 mm from column 9, 7th floor
- D) A W-shape bolt with 460 kN shear capacity
Correct answer: A
CSA metric designation: W-shape, approximately 460 mm nominal depth, 97 kg per lineal metre. This is standard Canadian structural steel notation.
Key concept: W[depth]x[mass/m] — e.g., W460x97 = W-shape, ~460 mm deep, 97 kg/m. US standard uses W18x65 (depth in inches, weight in lb/ft).
Q71easy
What does a "circle with a number" at the end of a section cut line on a structural drawing indicate?
- A) The column grid number at that location
- B) The sheet number where the section detail is drawn
- C) The load applied at that section
- D) The number of bolts required at that connection
Correct answer: B
Section cut symbols have two components: the circle/flag at the ends of the cut line, and the number(s) inside refer to the detail number and sheet number where that section view is shown.
Key concept: Section cut symbol: lines show cut plane; circle/triangle shows viewing direction. Numbers inside = detail # / sheet #. Follow to find the detailed connection drawing.
Q72medium
What information does the "Bill of Materials" (BOM) on a structural drawing provide?
- A) The estimated cost of the steel package
- B) A list of all members with sizes and quantities
- C) The material specifications and steel grades required
- D) A list of the subcontractors on the project
Correct answer: B
The BOM (also called a material list or schedule) is a complete list itemizing every steel member on the drawing with its designation, size, length, quantity, and piece mark — used for procurement and shop fabrication.
Key concept: Bill of Materials: lists all steel members (piece mark, designation, size, length, quantity) for procurement and fabrication tracking.
Q73hard
A structural drawing shows "4-M20 A325 bolts" at a beam-to-column shear tab connection. What does this mean?
- A) 4 machine bolts, 20 mm diameter, Grade A325 high-strength bolts
- B) The connection uses 4 bolts, metric size M20 (20 mm diameter), ASTM A325 high-strength
- C) The bolt group has a shear capacity of 4,000 N per M20 bolt per A325 standard
- D) The bolts are metric, Group 4 size, 20 kN capacity
Correct answer: B
4-M20 A325 means 4 bolts of M20 size (20 mm nominal diameter) meeting ASTM A325 high-strength structural bolt requirements.
Key concept: Bolt callout: [quantity]-[size] [grade]. 4-M20 A325 = 4 bolts, 20 mm diameter, A325 high-strength. Metric M20 = approximately 3/4-inch imperial.
Q74medium
What does the abbreviation "TOS" mean on a structural steel drawing?
- A) Top Of Steel — the elevation of the top surface of the steel beam
- B) Type Of Section — indicating the steel section type
- C) Total Overall Span — the beam span between columns
- D) Tension On Steel — a notation for tension member design
Correct answer: A
TOS (Top of Steel) is an elevation reference on structural drawings indicating the height of the top flange of a beam, measured from the project datum. It is used to coordinate with the concrete deck, mechanical, and architectural drawings. Common related notations: BOS (Bottom of Steel — soffit elevation, important for clearance), TOS is NOT the same as finished floor elevation (which is TOS + deck slab thickness + topping if any). Wrong answers often confuse TOS with the beam depth or with the centreline elevation. For steel erection: when setting beam elevation, you level to the TOS — not to the bottom flange or web centreline.
Key concept: TOS = Top of Steel elevation. Used to coordinate beam elevations with slab and architectural finish levels. Contrasted with "BOS" (Bottom of Steel).
Q75easy
On a structural drawing, what does the note "FSBW" refer to?
- A) Field Shop Bolt Work
- B) Full-Strength Butt Weld
- C) Fillet Strength Below Weld line
- D) Fabricated Steel Bearing Wall
Correct answer: B
FSBW (Full Strength Butt Weld) or CJP (Complete Joint Penetration) groove weld indicates that the weld must develop the full tensile strength of the connected base metal — the weld is not the weak link. This requires 100% penetration through the joint thickness, usually verified by visual inspection plus UT (ultrasonic testing) or radiography. It is different from: a partial joint penetration (PJP) weld, which does not penetrate the full thickness and has reduced capacity; a fillet weld, which joins members at a surface (no groove); and a plug or slot weld. FSBW/CJP welds are required at moment connections (beam-column moment joints) and splice plates carrying tension — they cost more (more prep, more passes, more inspection) than fillet welds.
Key concept: FSBW/FPBW = Full Strength/Penetration Butt Weld = CJP groove weld. Requires full root penetration — back-gouge and back-weld, or use a backing bar.
Q76medium
A structural drawing shows rebar marked as "4-20M @ 200 O.C." in a concrete slab. What does this mean?
- A) 4 bars, 20 mm diameter, spaced 200 mm apart on centre
- B) 4 layers of rebar, 20 mm from the bottom, every 200 mm
- C) Grade 20M bars, 4 per metre, in groups of 200 bars
- D) 40 bars, metric size, at 200 kN service load
Correct answer: A
The notation means 4 rebar in the group shown, 20M designation (approximately 20 mm diameter in CSA A23.1), spaced 200 mm on centre (O.C. = on centre).
Key concept: Rebar notation: [quantity]-[bar size] @ [spacing] O.C. 4-20M @ 200 O.C. = 4 bars of 20M size, spaced 200 mm apart on centre.
Q77hard
On an erection drawing, a beam is shown with a dashed "camber" indicator. The note says "Camber 25 mm". What action does the ironworker take?
- A) Add 25 mm shim plates under the beam at midspan
- B) Install the beam with the upward bow facing up
- C) Request the beam be re-fabricated to remove the camber
- D) Apply a 25 mm offset at the beam end connections
Correct answer: B
Camber is built into the beam at the fabrication shop, so no field action is required beyond correct orientation. The ironworker must install the beam with the camber (upward bow) oriented correctly — the camber marking (typically a paint mark) faces up.
Key concept: Camber: install beam with upward bow facing UP. The camber mark (kink point) identifies the correct orientation. Never flip a cambered beam upside down.
Q78medium
What does a "North arrow" on a structural plan drawing indicate?
- A) The direction of the dominant wind load
- B) The plan's orientation relative to project north
- C) The starting point for steel erection sequence
- D) The direction where expansion joints are required
Correct answer: B
The north arrow establishes the plan orientation relative to true north or a project north for layout purposes. Ironworkers use this to orient themselves on site and correctly position structural members per the grid layout.
Key concept: North arrow: establishes plan orientation. "Project north" may differ from true north — always confirm which is used for layout.
Q79easy
What scale is most commonly used for structural steel framing plans?
- A) 1:5 (full detail scale)
- B) 1:50 or 1:100
- C) 1:500 or 1:1000
- D) 1:1 (actual size)
Correct answer: B
Structural framing plans are typically drawn at 1:50 (showing individual beams) or 1:100 for larger buildings. Connection details may be drawn at 1:10 or 1:5 to show bolt holes and weld sizes clearly.
Key concept: Framing plan scale: 1:50 or 1:100 typical. Connection details: 1:5 to 1:10. Always check the scale before taking measurements from drawings.
Q80hard
An ironworker reads a structural drawing showing a W310×129 beam. What does this designation tell the ironworker about the section?
- A) A wide-flange section: 310mm deep, 129 kg per metre
- B) A 310mm square hollow section weighing 129 kg
- C) A welded plate girder: 310mm web height, 129mm flange width
- D) A cold-formed channel: 310mm leg, 129mm base
Correct answer: A
W-shape designation: W = Wide Flange. First number = nominal depth in mm (310mm). Second number = mass in kg/m (129 kg/m). This is a standard AISC/CISC wide-flange designation used throughout Canadian structural steel practice. The actual depth may vary slightly from nominal. W310×129 is a heavy section used for heavily loaded beams and columns.
Key concept: Wide-flange designation: W[depth mm]×[mass kg/m]. W310×129 = ~310mm deep, 129 kg per metre of length. Used for structural beams, columns, bracing.
Q81medium
A structural drawing shows the symbol ↑ with a triangle pointing downward (▽) beside a weld symbol on a fillet weld callout. What does the downward triangle indicate?
- A) The weld is on the near side (arrow side) of the joint
- B) The weld must be ground flush
- C) The weld is a field weld, made at the job site
- D) The weld requires non-destructive testing (NDT)
Correct answer: C
A flag symbol (pennant/triangle on the reference line) indicates a field weld in AWS/CWB welding symbol notation. Field welds are performed at the erection site after steel is delivered, not at the fabrication shop where shop welds are completed. The flag at the reference line-tail junction distinguishes site-welded connections from pre-fabricated connections, critical for erection sequencing.
Key concept: Welding symbol flags: Flag/pennant at reference line = field weld (on-site). All-around symbol (circle at flag junction) = weld continues all around. No flag = shop weld.
Reinforcing Steel — 15 questions
Q82easy
In the CSA A23.1 system, what does "20M" rebar designation mean?
- A) The bar has a yield strength of 20 MPa
- B) A metric bar about 19.5 mm in diameter
- C) The bar is 20 metres long
- D) A bar used only in 20 MPa concrete
Correct answer: B
In the CSA metric system, 20M refers to a deformed metric rebar with a nominal diameter of approximately 19.5 mm and a cross-sectional area of 300 mm². Common sizes: 10M (100 mm²), 15M (200 mm²), 20M (300 mm²), 25M (500 mm²), 30M (700 mm²).
Key concept: CSA rebar sizes: 10M (100 mm²), 15M (200 mm²), 20M (300 mm²), 25M (500 mm²), 30M (700 mm²). The number roughly corresponds to bar diameter in mm.
Q83medium
What is the yield strength of Grade 400W rebar per CSA G30.18?
- A) 300 MPa
- B) 400 MPa
- C) 500 MPa
- D) 600 MPa
Correct answer: B
Grade 400W rebar has a minimum specified yield strength of 400 MPa and is weldable (the "W" designation). It is the most common structural rebar grade in Canadian construction.
Key concept: Grade 400W: Fy = 400 MPa, weldable. Grade 500W: Fy = 500 MPa, weldable. Grade 400R: not weldable. "W" = weldable to CSA W186.
Q84medium
What is the minimum concrete cover required for reinforcing steel in a concrete slab exposed to weather, per CSA A23.1?
- A) 20 mm
- B) 40 mm
- C) 50 mm
- D) 75 mm
Correct answer: B
CSA A23.1 requires a minimum 40 mm concrete cover for steel reinforcement in slabs exposed to weather (exterior exposure). Cover protects rebar from corrosion.
Key concept: Concrete cover for rebar: 40 mm for weather-exposed slabs (CSA A23.1). Greater cover required for aggressive environments. Cover maintained by plastic chairs/bar supports.
Q85easy
What is a "lap splice" in reinforcing steel?
- A) A mechanical coupler that joins two rebar end-to-end
- B) An overlap where two parallel bars transfer stress
- C) A weld joining two rebar pieces at their ends
- D) A bar bent into a U-shape around another bar
Correct answer: B
A lap splice is an overlapping zone where two bars run parallel: the bar ends overlap by a specified length (development length × splice factor) so that bar forces transfer through bond with the surrounding concrete.
Key concept: Lap splice: two bars overlap to transfer load through bond. Minimum lap length per CSA A23.1 = development length × splice class factor (typically 1.3 or 1.7 × ld).
Q86medium
What is "development length" for reinforcing bars?
- A) The maximum span between bar supports
- B) The embedment needed to develop full yield strength
- C) The length of bar that must be bent into a hook
- D) The distance from the end of a bar to the nearest stirrup
Correct answer: B
Development length (ld) is the minimum straight embedment length needed for the bar to develop its full yield strength through bond with the concrete. Insufficient development causes bond failure (bar pull-out).
Key concept: Development length (ld): minimum embedment for bar to reach yield. Depends on bar size, grade, concrete strength, and cover. Hooks reduce required development length.
Q87easy
Rebar chairs (bar supports) are used to:
- A) Hold vertical rebar in position while tying
- B) Hold rebar at the correct height for cover
- C) Splice rebar together at joints
- D) Mark the location of rebar on the concrete surface after pouring
Correct answer: B
Bar chairs and supports are plastic or metal supports placed under rebar to maintain the required concrete cover by holding the bars at the correct height above the form (distance from bottom of rebar to bottom of slab).
Key concept: Bar chairs: maintain concrete cover by supporting rebar at correct height above formwork. Cover is critical for corrosion protection and structural performance.
Q88medium
Standard rebar ties are made using:
- A) 16-16.5 gauge soft annealed steel wire
- B) Thin plastic zip ties rated for 50 kg
- C) Spot welding at each intersection
- D) Epoxy adhesive at each bar crossing
Correct answer: A
Rebar ties are made from 16 to 16.5 gauge (approximately 1.6 mm diameter) smooth, soft annealed steel wire, twisted with a tier tool. Multiple tie patterns exist for different conditions (snap tie, saddle tie, figure-8 tie).
Key concept: Rebar tie wire: 16-16.5 gauge (≈1.6 mm) soft annealed wire. Function is to HOLD POSITION only — ties do not transfer structural load.
Q89hard
A 25M bar in 30 MPa concrete requires a standard hook. What is the standard 90° hook geometry per CSA A23.1?
- A) 12-diameter extension, 4-diameter inside bend radius
- B) 12-diameter extension, 3-diameter minimum inside bend radius
- C) 6-diameter extension, 5-diameter inside bend radius
- D) 8-diameter extension, 2-diameter inside bend radius
Correct answer: B
A standard 90° hook per CSA A23.1: the tail extension beyond the bend is a minimum 12 bar diameters (12db), with inside bend diameter of 6db for 25M and larger bars (3× db minimum bend radius).
Key concept: Standard 90° hook: 12db tail extension, inside bend diameter 6db (25M and larger). Standard 180° hook: 4db extension past the bend. Hooks reduce required development length.
Q90medium
According to CSA A23.1, what is the allowable placement tolerance for rebar in a slab on grade?
- A) ±3 mm in any direction
- B) ±10 mm in depth, ±30 mm in length
- C) ±25 mm in any direction
- D) ±50 mm in length, ±5 mm in depth
Correct answer: B
CSA A23.1 permits ±10 mm tolerance on effective depth (d) for members ≤200 mm deep, and ±30 mm tolerance on bar length. Clear cover tolerance is typically −5 mm to +10 mm.
Key concept: Rebar placement tolerance: ±10 mm in d (effective depth), ±30 mm in length per CSA A23.1. Exceeding tolerances requires engineer review.
Q91easy
What do the deformations (ribs) on deformed rebar do?
- A) Increase the bar weight to improve resistance to impact loads
- B) Mechanically interlock with concrete to improve bond and force transfer
- C) Reduce the bar cross-section to save material at low-stress locations
- D) Provide identification markings for the steel mill
Correct answer: B
The transverse and longitudinal ribs on deformed bar create mechanical interlock with the surrounding concrete, dramatically improving bond strength compared to smooth bars.
Key concept: Deformations on rebar: provide mechanical interlock with concrete, improving bond. Without deformations, only friction holds bar in place (much weaker).
Q92medium
A column dowel extends from the footing to lap splice with the column bars. The minimum lap splice length is typically:
- A) Equal to the bar diameter × 10
- B) Determined by the engineer's calculations
- C) Always 300 mm for all bar sizes
- D) Equal to the concrete cover thickness × 10
Correct answer: B
Dowel lap splice length is calculated by the engineer based on development length calculations considering bar size, grade, concrete strength, cover, and splice class. Ironworkers must follow the drawings — never assume a standard splice length.
Key concept: Lap splice length: engineer-specified on drawings. Based on development length × splice factor. Always follow the drawings — do not guess.
Q93hard
Rebar that has mill scale (light rust) on its surface before placement — what action should the ironworker take?
- A) The bars must be sandblasted clean before placement
- B) Place the bars as is — light rust is acceptable
- C) Apply a rust inhibitor coating before placing in forms
- D) Replace all rusty bars with new material
Correct answer: B
Light surface rust is acceptable and actually improves bond between rebar and concrete. Only heavy, flaking (loose) rust that significantly reduces the bar cross-section must be removed. CSA A23.1 permits light rust.
Key concept: Light surface rust: acceptable and may improve bond. Heavy/flaking rust: remove before placing — it reduces bar cross-section and bond strength.
Q94medium
What is the purpose of "stirrups" or "ties" in a reinforced concrete beam or column?
- A) To resist longitudinal tension forces along the beam axis
- B) To resist shear and confine the concrete core
- C) To provide anchorage for the formwork
- D) To position the longitudinal bars at the correct concrete cover depth
Correct answer: B
Stirrups (beams) and ties (columns) resist shear and torsion forces, confine the concrete core to increase ductility, and brace the longitudinal bars against buckling under compression load.
Key concept: Stirrups/ties: resist shear force, confine concrete core, and prevent longitudinal bar buckling. Critical for seismic ductility — closer spacing in plastic hinge zones.
Q95hard
An ironworker is placing rebar in a concrete footing. The drawing specifies 20M bars at 200mm c/c each way, with 75mm cover to the outside face. The footing is 400mm thick. After placing the bottom mat, the ironworker notices the total rebar height plus both covers would leave no room for a top mat. What is the CORRECT response?
- A) Reduce the bottom cover to 50mm to create space for the top mat
- B) Notify the superintendent and engineer of the conflict
- C) Place both mats touching — concrete cover can be eliminated for interior footings
- D) Eliminate the top mat — one layer of rebar is sufficient for footings
Correct answer: B
Rebar placement conflicts with dimensions must be reported to the superintendent and engineer — the footing design may have a drawing vs. actual dimension error. A 400mm footing with 75mm bottom cover + 20M bar (19.5mm) + chair height + 20M top bar + 75mm top cover = physical impossibility. This indicates either a footing dimension error, a cover requirement error, or a bar size error in the drawings. NEVER reduce cover or eliminate reinforcement without engineering direction.
Key concept: Rebar cover is structural code requirement (CSA A23.3) — cannot be reduced without engineer approval. Drawing conflicts = stop and notify engineer.
Q96medium
An ironworker is tying rebar for a suspended floor slab. The drawing calls for top bars (negative moment reinforcement) in the vicinity of column supports. The ironworker places these bars at the bottom of the slab instead. What is the structural consequence?
- A) No consequence — rebar works in tension or compression regardless of position
- B) The slab loses top tension reinforcement at supports, risking failure
- C) Minor consequence — the bars provide 75% of the required capacity in either position
- D) No consequence — concrete carries tension at column supports
Correct answer: B
Top reinforcement at column supports resists the hogging bending moment (negative moment) where the top fiber is in tension. Placing these bars at the bottom reverses the reinforcement — the top fiber has no tension reinforcement at the critical moment location. Concrete cannot carry tension, so the slab is effectively unreinforced at the most critical stress location, leading to cracking and potential failure at the supports under service and live load.
Key concept: Top bars = negative moment (hogging) reinforcement at supports. Bottom bars = positive moment (sagging) at midspan. Placement is critical — wrong position = unrpeinforced at the peak moment location.
Safety & Fall Protection — 15 questions
Q97easy
At what height must ironworkers be protected from falls per Canadian OHS regulations?
- A) 1.2 m (4 ft)
- B) 2.4 m (8 ft)
- C) 3 m (10 ft)
- D) 4.5 m (15 ft)
Correct answer: C
Most Canadian provincial OHS regulations require fall protection for ironworkers when working at heights of 3 m (10 ft) or more. Some jurisdictions require protection at lower heights.
Key concept: Fall protection required at 3 m (10 ft) or greater for most Canadian jurisdictions. Ironworkers must be 100% tied off during steel erection above this height.
Q98easy
What does a "Personal Fall Arrest System" (PFAS) consist of?
- A) Safety boots, hard hat, and safety glasses
- B) Full body harness, connecting lanyard, and anchor point
- C) Body belt, rope grab, and vertical lifeline
- D) Safety net and horizontal lifeline only
Correct answer: B
A PFAS has three essential components: (1) full-body harness, (2) connecting means (lanyard, self-retracting lifeline, rope grab + lifeline), and (3) an anchor point with sufficient strength.
Key concept: PFAS = full-body harness + connecting means (lanyard/SRL) + anchor. Body belts are NOT acceptable as PFAS — only full-body harnesses.
Q99medium
What is the minimum anchor strength requirement for a personal fall arrest system anchor point?
- A) 5 kN (approximately 500 kg)
- B) 16 kN (approximately 1,600 kg) or be capable of withstanding twice the maximum arrest force
- C) 22.2 kN (5,000 lb) per OSHA standard
- D) Anchors must be engineered for each specific application
Correct answer: C
CSA Z259.16 and most OHS regulations require PFAS anchors to withstand 22.2 kN (5,000 lbf) per attached worker. This equals the OSHA standard and ensures the anchor can survive worst-case fall arrest forces.
Key concept: PFAS anchor minimum strength: 22.2 kN (5,000 lb) per attached worker per CSA Z259.16/OSHA. Each worker needs their own anchor or anchor rated for combined load.
Q100medium
A "Controlled Decking Zone" (CDZ) allows ironworkers to work without fall protection under specific conditions. Which statement is correct about a CDZ?
- A) Workers inside a CDZ never require fall protection of any kind
- B) It permits decking work without PFAS under strict zone rules
- C) CDZs apply to all steel erection operations above 3 m
- D) A CDZ is always required when more than 5 ironworkers are on the deck at once
Correct answer: B
A CDZ is a designated zone with specific dimension, positioning, and monitoring requirements (maximum 90 feet/27 m wide, with a CDZ monitor assigned) where ironworkers placing decking are exempt from PFAS requirements due to the nature of the work. Specific regulatory requirements must be met.
Key concept: CDZ: exemption from PFAS for decking placement — requires designated zone, CDZ monitor, and compliance with specific dimensions and positioning rules per jurisdiction.
Q101easy
Before using a full-body harness, the ironworker should:
- A) Inspect the harness only after a fall event to check for damage
- B) Inspect it before each use for damage and proper fit
- C) Check the harness every Monday morning and log the inspection
- D) Harnesses do not require inspection — replace every 2 years
Correct answer: B
PFAS components must be inspected before every use for cuts, fraying, corroded hardware, and proper fit. After a fall event, the harness must be removed from service and inspected by a competent person before any reuse.
Key concept: Harness inspection: BEFORE every use. Check for cuts, fraying, chemical damage, corroded hardware, and bent components. After any fall: remove from service immediately.
Q102hard
Calculate the minimum fall clearance needed for a 1.8 m lanyard with a 1.07 m maximum deceleration distance. The harness D-ring is 1.5 m above the feet. The required safety factor adds 1.2 m.
- A) 3.87 m
- B) 4.57 m
- C) 5.57 m
- D) 6.77 m
Correct answer: C
Fall clearance = lanyard length (1.8 m) + deceleration distance (1.07 m) + D-ring height (1.5 m) + safety factor (1.2 m) = 5.57 m minimum clearance below anchor.
Key concept: Fall clearance = lanyard + deceleration distance + D-ring height + safety factor. Must have this much clear space below anchor before using the lanyard.
Q103medium
What is the maximum free-fall distance permitted in a personal fall arrest system under CSA Z259?
- A) 0.6 m (2 ft)
- B) 1.2 m (4 ft)
- C) 1.8 m (6 ft)
- D) 3 m (10 ft)
Correct answer: B
CSA Z259.11 and most OHS regulations limit free fall in a PFAS to 1.2 m (4 ft) for shock-absorbing lanyards. Positioning the anchor above the D-ring minimizes free fall distance.
Key concept: Maximum free fall in PFAS: 1.2 m (4 ft) per CSA Z259.11. Connect anchor as high as possible above the D-ring to minimize free fall. SRLs allow near-zero free fall.
Q104easy
What is a "Self-Retracting Lifeline" (SRL) and its main advantage over a conventional lanyard?
- A) An SRL stores wire rope; it has no advantage over a lanyard
- B) It locks automatically, limiting free fall to under 0.6 m
- C) An SRL is permanently attached to the building structure
- D) An SRL allows workers to work at heights below the anchor point only
Correct answer: B
An SRL pays out and retracts like a tape measure. In a fall, the rapid pull engages an internal braking mechanism that locks automatically, stopping the fall within milliseconds — limiting free fall to less than 0.6 m and reducing peak arrest force compared to a conventional lanyard.
Key concept: SRL: locks within 0.6 m of free fall (vs 1.2 m for lanyard). Reduces peak arrest force. Allows greater freedom of movement than a fixed-length lanyard.
Q105medium
Safety nets for fall protection in steel erection must extend beyond the edge of the work surface by at least:
- A) 1.5 m (5 ft) from the work surface edge
- B) 2.4 m (8 ft) for drops up to 6 m
- C) 3 m (10 ft) from the work surface edge
- D) The net must extend to the nearest column line
Correct answer: B
Per OSHA 1926.502 and equivalent Canadian standards, safety nets must extend at least 2.4 m (8 ft) beyond the edge for drops of 6 m or less, 3 m for drops 6–12 m, and 3.6 m beyond for drops over 12 m.
Key concept: Safety net extension: 2.4 m beyond edge (drops ≤6 m), 3 m (drops 6–12 m), 3.6 m (drops >12 m). Nets must be tested, inspected, and tagged.
Q106medium
What does "100% tie-off" mean for ironworkers during structural steel erection?
- A) The ironworker must be tied off for 100% of the workday
- B) At least one PFAS connection at all times, even when moving
- C) The ironworker must use a full 100-foot lifeline at all times
- D) 100% of the rigging must be secured before erection begins
Correct answer: B
100% tie-off means continuous connection — the ironworker must have at least one PFAS connection at all times, including while moving or transitioning their tie-off point. A double-lanyard or SRL with a second connection allows transitioning without a gap.
Key concept: 100% tie-off: never unclipped. Use dual lanyards or SRL to maintain connection while transitioning between anchor points.
Q107easy
What is the correct procedure after a worker has taken a fall while wearing a personal fall arrest harness?
- A) If the worker is unhurt, the harness can be put back in service immediately
- B) The harness and lanyard must be removed from service and inspected by a competent person before reuse
- C) Only the lanyard needs to be replaced after a fall; the harness can be reused
- D) Perform a 10-minute visual inspection and return to service if no visible damage
Correct answer: B
All PFAS components subjected to fall arrest forces must be removed from service. Internal damage not visible externally may have occurred. Only a competent person can return equipment to service after inspection.
Key concept: After a fall: remove ALL PFAS components from service immediately. Inspect by competent person before any reuse. When in doubt, discard.
Q108hard
A horizontal lifeline is rigged between two anchor points 10 m apart at a sag of 0.3 m at midspan. A 100 kg worker falls from midspan. What can be said about the anchor force?
- A) Each anchor feels exactly 490 N (half the worker weight)
- B) The anchor force is much greater than the worker weight due to the geometry of the shallow sag
- C) The horizontal lifeline eliminates force on anchors because the load hangs vertically
- D) Anchor force equals worker weight plus lanyard weight only
Correct answer: B
Horizontal lifelines with small sag create very high anchor forces due to geometry. With 0.3 m sag over 5 m (half span), the horizontal tension ≈ (W × L)/(4 × sag) = (980 × 5)/(4 × 0.3) ≈ 4,080 N per side — more than 4× the worker weight. This is why HLL anchors require engineered design.
Key concept: Horizontal lifeline: anchor force >> worker weight due to shallow sag geometry. HLL MUST be engineered. Never improvise a horizontal lifeline — forces can exceed 10× body weight.
Q109hard
An ironworker is working on a steel structure 8m above grade and must temporarily remove a guardrail to swing a beam into position. There are no overhead tie-off points available. What fall protection option is MOST appropriate?
- A) Proceed without fall protection — the task will take less than 5 minutes
- B) Work without protection is permitted if spotters are below
- C) A safety net below or a positioning device with restraint
- D) Stop work and wait until a tie-off point is installed by others
Correct answer: C
Fall protection must be maintained continuously — never remove a guardrail without equivalent alternate protection already in place; doing so violates provincial OH&S regulations. Options when tie-off points are unavailable above: 1) Safety net below the work level (pre-installed). 2) Positioning device with secondary restraint, or a personnel platform with guardrails. 3) Repositioning to access an available anchor. 4) Install a temporary structural anchor before removing the guardrail. "Less than 5 minutes" is never a valid exception.
Key concept: Fall protection: never remove guardrails without equal or better alternate protection. Safety nets, personal fall arrest, or guardrails must be in place at all times above 3m (varies by province).
Q110medium
An ironworker using a self-retracting lifeline (SRL) is working on a steel beam 5m above the next lower level. The SRL has a maximum arresting force of 6 kN and the worker weighs 100 kg. What is the approximate total fall distance if a fall occurs?
- A) 0.6m — SRL locks within 1 foot of fall
- B) About 1.8-2.4m including lock and deceleration
- C) 5m — SRL only prevents ground impact
- D) 0.3m — SRL eliminates free fall completely
Correct answer: B
SRL total fall distance is not zero. An SRL allows 0.3-0.6m of free fall before locking, plus 0.6-0.9m of deceleration distance during arrest, plus 1.5-1.8m of suspended body height below the anchor. Total clearance required: approximately 1.8-2.4m below the anchor point. At 5m above the lower level, there is sufficient clearance. Always verify clearance before using an SRL.
Key concept: SRL clearance = free fall (0.6m) + deceleration (0.9m) + body height (1.8m) ≈ 3.3m below anchor. Verify clearance before use, especially near lower levels.
Q111hard
A gang of ironworkers is erecting steel 12m above grade. The controlled decking zone (CDZ) provisions allow workers within 3m of the leading edge to work without guardrails under specific conditions. Which of the following does NOT qualify as a condition for using the CDZ provision?
- A) Workers are wearing and using personal fall arrest systems (PFAS)
- B) The CDZ has a designated competent person monitoring compliance
- C) Decking bundles are placed to serve as barriers at the leading edge
- D) No other falls hazards within the CDZ exist
Correct answer: C
Decking bundles do NOT qualify as CDZ barriers. CDZ conditions (per provincial OH&S regulations and OSHA 1926 Subpart R): 1) Only decking work is performed. 2) Employees stay back 3m from edge unless using PFAS. 3) Decking is not used as a barrier (bundles shift and are removed). 4) A competent person monitors the zone. Decking bundles appear substantial but are not approved CDZ barriers — they move and are intentionally removed.
Key concept: CDZ valid conditions: PFAS in use OR 3m setback from edge. Competent person monitoring. NOT valid: decking bundles as barriers, non-decking work, or other hazards present.
Tools & Equipment — 9 questions
Q112easy
What is an "ironworker machine" (also called a hydraulic ironworker)?
- A) A mobile crane specifically designed for steel erection
- B) A hydraulic machine that shears, punches, and bends steel
- C) A portable wire rope swaging machine for rigging
- D) A hydraulic torque wrench for high-strength bolt installation
Correct answer: B
An ironworker machine is a multi-function hydraulic bench-top or freestanding machine used in fabrication shops and on site for shearing plate, punching bolt holes, notching angle iron, and bending bar stock.
Key concept: Ironworker machine: hydraulic multi-function tool for shearing, punching, notching, and bending steel. Common in fabrication shops and ironworker tool trailers.
Q113easy
What is the difference between a "drift pin" and a "spud wrench"?
- A) They are the same tool — different regional names
- B) A spud wrench adds a wrench end; a drift pin only aligns
- C) A drift pin can tighten bolts; a spud wrench cannot
- D) A spud wrench is used only for rigging; a drift pin is used only for concrete work
Correct answer: B
A drift pin is only a tapered alignment tool for bolt holes. A spud wrench combines a wrench (typically open-end or box) on one end with a tapered shank for alignment on the other, allowing both alignment and bolt tightening in one tool.
Key concept: Drift pin: alignment only. Spud wrench: wrench end + tapered shank = alignment + bolt snugging in one tool.
Q114medium
A hydraulic bolt tensioner is used instead of a torque wrench for high-strength bolt installation. What is the key advantage?
- A) It is lighter and cheaper than a torque wrench
- B) It applies direct tension, eliminating torque variability
- C) It can install bolts in confined spaces where a torque wrench cannot fit
- D) It works on all bolt grades including stainless steel and aluminum
Correct answer: B
Hydraulic tensioners apply direct tensile load to the bolt by pulling the threaded end rather than applying torque, eliminating the torque-to-tension variability that comes from lubrication, thread condition, and technique. This achieves more consistent and accurate pretension.
Key concept: Hydraulic tensioner: applies direct tension (not torque). Eliminates torque-tension variability. Used for critical or high-volume installations.
Q115medium
A "come-along" (manual chain hoist) is rated for 1.5 tonnes. When can this rating be exceeded?
- A) When the load is lowered slowly rather than lifted
- B) When the come-along is used by two workers together
- C) When the load is lifted vertically — the rating applies only to horizontal use
- D) The rating must NEVER be exceeded under any circumstances
Correct answer: D
Equipment WLL ratings must never be exceeded. The rated capacity applies regardless of load speed, number of workers, or direction of use. Overloading can cause sudden failure without warning.
Key concept: WLL MUST NOT be exceeded under any circumstances. Overloading come-alongs and chain hoists is a leading cause of rigging failures. Use the right tool for the load.
Q116easy
What is a "beam clamp" used for in ironworking?
- A) To permanently connect two beams at a splice
- B) To attach rigging to a beam flange without welding
- C) To hold a beam in plumb during erection until it is bolted
- D) To clamp the welding electrode holder to the beam during welding
Correct answer: B
Beam clamps attach to a beam flange by clamping action, providing a temporary rigging point for hooks, slings, and blocks — for hoisting, pulling, or hanging equipment without welding, drilling, or otherwise permanently modifying the beam.
Key concept: Beam clamp: attaches to beam flange without welding/drilling. Provides temporary rigging point. Must be rated for the load and installed per manufacturer instructions.
Q117medium
A "burning bar" (thermic lance) is used in ironwork for:
- A) Heating structural steel for straightening or hot bending
- B) Cutting hard materials like steel, concrete, and rock
- C) Preheating weld areas to prevent hydrogen cracking
- D) Marking cut lines on structural steel by burning shallow grooves
Correct answer: B
A burning bar (thermic lance) uses a steel tube packed with metal wires and fed with oxygen. It burns at over 5,000°C, cutting through extremely hard materials that conventional cutting cannot handle — hardened steel, concrete, and even rock — used for emergency cutting and demolition.
Key concept: Burning bar (thermic lance): cuts through steel, concrete, and rock at >5,000°C. For extreme applications where conventional cutting fails. Produces intense heat and sparks — significant fire and burn hazard.
Q118medium
An optical level or builder's level is used during structural steel erection to:
- A) Check the alignment of bolt holes in connections
- B) Establish level reference elevations across the structure
- C) Measure the plumb of columns using the level bubble
- D) Read the crane load chart to determine crane capacity
Correct answer: B
A builder's level (optical or laser) establishes and verifies a horizontal datum plane across the site. It is used to set column base plate elevations, check beam levelness, and verify floor deck elevations.
Key concept: Builder's level: establishes horizontal reference. Used to set base plate elevations and verify that beams are level. Must be set on a stable base and calibrated.
Q119hard
A pneumatic impact wrench is being used to snug-tight high-strength structural bolts. What precaution is required?
- A) No precautions needed — impact wrenches are the standard tool for all high-strength bolt installation
- B) The impact wrench must be calibrated and limited to prevent over-tensioning beyond snug-tight
- C) Impact wrenches cannot be used for high-strength bolts under any circumstances
- D) A torque multiplier must be used with all impact wrenches on structural connections
Correct answer: B
Impact wrenches can over-torque and over-tension high-strength bolts if not controlled. For snug-tight installation, the tool must be set or adjusted so it stops after achieving snug. Final tensioning requires a calibrated method (turn-of-nut, TC bolt, DTI, or calibrated torque).
Key concept: Impact wrenches: acceptable for snugging only — must be controlled/limited to prevent over-tensioning. Final pretension requires a verified tensioning method per AISC/CISC.
Q120medium
Before using any rigging hardware (shackles, hooks, chains) on a job site, the ironworker should:
- A) Test each piece by applying twice the WLL to check for deformation
- B) Visually inspect for damage and verify adequate WLL
- C) Apply a fresh coat of oil to all moving parts
- D) The equipment only requires inspection during the annual company audit
Correct answer: B
Pre-use inspection of rigging hardware is mandatory. Visually inspect for cracks, deformation (hooks opening, shackle bowing), corrosion reducing cross-section, missing or illegible load ratings, and pin security — and verify the WLL is adequate for the lift.
Key concept: Pre-use rigging inspection: check for cracks, deformation, corrosion, and verify WLL marking is legible and adequate. Remove any questionable hardware from service.
← Back to the timed 420B quiz ·
Free 50-question 420B mock exam PDF
Independent, unofficial study resource — not affiliated with or endorsed by the CCDA,
the Red Seal Program, or any provincial/territorial apprenticeship authority.
“Red Seal” is used solely to describe the examination this material provides
practice for. All questions are original works. No guarantee of results.