How corrections are made
In September 2026 all eleven question banks were audited. Each finding was put to a reviewer whose job was to defend the question, and most of the findings that survived were checked again by a second, independent reviewer.
- Wrong or disputable answer: the question is removed. It is not edited until it passes. Removed questions leave the free quiz, the free pages and the PDFs.
- Wrong explanation: the explanation is corrected. The corrected line is written from a source the corrector opened and is checked by an independent verifier before it goes live. The question, its options and its answer stay the same.
- New questions go live only after a break attempt and a source check. They replace a question that tested the same fact as another, or bring a bank back to its official exam length. A reviewer tries to break each one and its source is checked independently; candidates that fail are dropped, not revised.
- Findings that are not defects are dismissed. Those questions are left as they were.
Later corrections are added to this page with their date. To report an error, use the Contact page.
Jump to: Summary · By trade · Exam facts and site pages · PDF files
Summary: September 2026 audit
| Trade | Removed | Replaced | Added | Explanations fixed | Bank size |
| 421A Heavy Duty Equipment Technician | 15 | 0 | 0 | 19 | 421 → 406 |
| 310T Truck & Transport Mechanic | 4 | 2 | 0 | 4 | 165 → 161 |
| 310S Automotive Service Technician | 0 | 1 | 0 | 1 | 139 → 139 |
| 306A Plumber | 5 | 1 | 0 | 3 | 135 → 130 |
| 309A Construction Electrician | 4 | 4 | 0 | 5 | 135 → 131 |
| 442A Industrial Electrician | 5 | 0 | 0 | 7 | 135 → 130 |
| 313A Refrigeration & Air Conditioning Mechanic | 1 | 1 | 0 | 2 | 116 → 115 |
| 420B Ironworker (Generalist) | 3 | 1 | 4 | 5 | 120 → 121 |
| 308A Sheet Metal Worker | 3 | 1 | 3 | 5 | 120 → 120 |
| 456A Welder | 1 | 0 | 6 | 6 | 120 → 125 |
| Gasfitter (Class A) | 2 | 0 | 0 | 8 | 112 → 110 |
| All eleven | 43 | 11 | 13 | 65 | 1,718 → 1,688 |
Bank size is before → after the audit. Explanations fixed: 58 come from the audit list (57 on 2026-09-13, one on 2026-09-14). Seven more were found while re-checking related questions: one 313A key concept on 2026-09-13 and six 421A explanations on 2026-09-14.
Replaced questions keep their place in the bank and get a new question on a different fact. Dates are the day a change went live on this site.
By trade
421A · 310T · 310S · 306A · 309A · 442A · 313A · 420B · 308A · 456A · Gasfitter
421A Heavy Duty Equipment Technician
Bank size: 421 before the audit, 406 after.
- 2026-11-23 4 questions changed; the same options are correct. Proving absence of voltage on an electric-drive loader’s high-voltage bus: the question and explanation attributed the steps to a named safety standard, with a 30 V threshold we could not confirm in a source. Both now give the procedure without the threshold or the attribution: prove the meter on a known live source, test between the conductors and from each conductor to chassis ground, then prove the meter again. Injector coil reading OL: the explanation called OL “overload/infinite” and gave a typical 5–50 ohm range. It now says OL means more than the meter can read on that range, that a coil still reading OL on the highest range is open, and to compare a reading with the specified coil resistance. Continuity testing: the explanation said testing a live circuit damages the meter and listed relay contacts as a plain continuity check. It now gives the reason (the meter supplies its own test current) and notes that pitted contacts can pass a continuity test yet drop voltage under load. Expansion valve system with high superheat and high subcooling: one wrong option was reworded so that the correct one is no longer the only option sharing words with the question.
- 2026-11-16 3 questions changed; the same options are correct. Air conditioning with the low side pulled into a vacuum and very high superheat: the question said the high side read normal to high, and the key concept said it stays there with a stuck-closed valve, but three equipment makers’ troubleshooting tables give a valve that has closed because its sensing bulb lost its charge low pressures on both sides. The question now says the high side reads below normal; the explanation says why, and that leaking reed valves would also leave the high side low but raise the low side instead of pulling it into a vacuum. Expansion valve system with high superheat and high subcooling: in the makers’ tables those two readings also fit a worn, inefficient compressor, so a second option could be defended. The question now also gives suction pressure below normal, which a restriction produces and an inefficient compressor does not, since it leaves suction pressure above normal with head pressure low; the explanation and key concept set out the four patterns. High, erratic head pressure after a compressor swap without a proper evacuation: the correct option called air and moisture non-condensable gases. It now names air only; the explanation says moisture left by the same mistake is a separate fault, which an equipment maker’s troubleshooting chart files under low suction pressure with an iced indoor coil, and that the repair, with a new drier and a deep vacuum, deals with both.
Earlier updates for 421A (12)
- 2026-11-07 2 questions changed; the same options are correct. Purpose of a final drive reduction: the explanation gave a ratio range of 10:1 to 30:1 and said the reduction sits inside each wheel hub or sprocket drive, neither of them sourced; both were removed. The question now tests the torque half: two wrong options say the speed falls while the torque stays the same or falls too, and the explanation says, after an engineering reference, that the speed is reduced as the torque is increased, that real gears lose some power to an efficiency, and that the ratio comes from the tooth counts. Excessive final drive backlash: the answer said it causes impact loading, noise and premature failure, and the explanation gave a typical range of 0.15–0.35 mm and said too little backlash causes overheating, none of them sourced, and a gear handbook says a bigger backlash in general causes fewer noise problems. The question now asks why backlash above the specification matters in a drive that reverses often, and the answer is that the teeth cross a wider gap at every change of load direction, as the gear handbook describes; the explanation adds why the ratio does not drop and why wear opens the gap rather than closing it.
- 2026-11-06 3 questions changed and 1 explanation and its key concept corrected; the same options are correct. Planetary gear set with the sun locked to the ring: the explanation said final-drive planetaries also give a direct-drive range, and that neutral is any set with no member held; it now says a planetary transmission gets its direct-drive range this way, and that neutral needs no member held and none locked together. The key concept says members are held or locked by hydraulically applied clutches and bands, and in some transmissions by one-way clutches, where it said clutches and brakes. The correct option was the shortest by one character and now reads “the entire set turns as one unit”. Final drive with a 72-tooth ring and an 18-tooth sun: the explanation said three or five planets give the same 5:1, but five planets of this size do not fit; it now says the planet count does not enter the ratio. It called 1.25:1 an inverted formula, and it is the ratio of a different arrangement, with the sun held and the ring driving the carrier. It counted five turns of the sun for one turn of the hub, where the ring is held in the hub; it now counts them against the carrier. The correct option was the shortest by one character and now ends “divided by the sun gear teeth”. ISO relay reading 85 ohms across its coil: the correct option was the only one that repeated a word from the question (untested, testing); it now reads “Coil is intact — the load contacts 30 to 87 are not yet checked”. Final drive backlash at the maximum of its specification: a typical range of 0.05–0.35 mm, which disagreed with another question, a claim that missed oil changes are the top cause of failure, and the chromium and lead attributions, none of them sourced, were removed. The explanation now takes the backlash definition and its two causes from a gear handbook, says a reading at the maximum does not on its own call for an immediate teardown, and gives iron as one of the elements that indicate wear and silicon as dirt getting in, as an oil analysis laboratory does.
- 2026-11-04 2 explanations and their key concepts corrected; the questions, options and answers are unchanged. Key-off battery drain test: the explanation said to disconnect the negative cable and put the ammeter between the cable and the post, which misses any other wire on that post, and on a machine with several batteries a meter at one battery reads only that battery’s share. It now says to put the meter where every path from the batteries runs through it, with any battery disconnect switch left on, and sets out how with one battery and with several. A 10-minute wait and a normal draw below 50 mA, neither of them sourced, were removed; the draw is now compared with the equipment maker’s specification, and a voltmeter in series is described as reading nearly full battery voltage rather than banned. ISO relay reading 85 ohms across its coil: a 50–120 ohm range for a good coil, with no source, was removed; 85 ohms is neither open nor near zero, and the reading is checked against the maker’s figure. The explanation no longer says pitted contacts fail the continuity check: that check can pass them, so the voltage drop across 30 and 87 is also measured with the work light on, and the coil is energized at its rated voltage following any polarity marked on the relay.
- 2026-11-02 1 question changed; the same option is correct. A 5V sensor supply shared by several sensors reads 4.2V instead of 5.0V: the answer said one sensor on the reference is shorted to ground, and it now says one sensor is partly shorted to ground. The explanation now says a direct short to ground pulls the reference almost to 0V, so a reading part way down points to a partial short, and that high resistance in the reference wire would lower the voltage only at the sensors beyond it, not on the ECM’s internal 5V bus that the module monitors and reports. The key concept no longer names a pinched connector wire as the common cause; it says that if the reference stays low with every sensor unplugged, the next step is to look for a reference wire shorted to ground between a sensor connector and the ECM, as a maker’s 5 V reference diagnostic procedure sets out.
- 2026-10-30 1 key concept edited; the question, options, answer and explanation are unchanged. Recovering R-134a from a scrapped haul truck: the key concept now says recycling, reclaim, disposal and reporting of the recovered refrigerant are settled by the provincial halocarbon regulation, where it began with recovery.
- 2026-10-29 4 explanations edited; the questions, options and answers are unchanged. Replacing an axial piston pump: a clause saying the cause is easily missed twice was removed. Battery load test: an opening line saying two figures get confused here now reads “Two points need care here”. Sub-task A-1.04: the explanation no longer says the sub-task concentrates on the electrical hazards deliberately, or that this is the list a candidate should be able to recite. Recovering R-134a from a scrapped haul truck: the explanation called naming US EPA Section 608 or 609 a frequent contamination from American question banks; it now says those are American rules with no force in Canada and that the TSSA does not govern this either, and it says the occupational standard cites jurisdictional regulations only for recycling and disposal, where it also listed recovery and reclaim.
- 2026-10-29 2 questions replaced. Moving a hydrostatic-drive machine whose engine will not run: the question asked what to do before towing it, and its explanation said every hydrostatic machine has a tow or bypass valve, stated how often one is left open, and added towing limits, a parking brake step and a tow bar, none of them with a source; the answer also gave its own reason. It now asks what to do before the machine is winched onto a float. The explanation follows pump makers’ manuals: the loop bypass, an option on some pumps, connects the two sides of the closed loop so oil can circulate while the motors turn; it is for a very short, very slow move only (one maker states that bypass valves are not tow valves), and it is closed afterwards, because the machine will not drive while it is open. Weak in reverse only: the answer, an internal bypass in one direction of the pump, was the only option that repeated a word from the question, and the explanation put the cause in a pump rotating group that works differently in each direction, with no source. The new question has one pump and one motor in a closed loop. Its answer is a leaking high-pressure relief or check valve, and its wrong options are three causes that act on the whole loop (a low reservoir level, a worn charge pump and a stuck-open charge relief); a pump service manual lists low fluid, a malfunctioning charge pump and a leaky charge relief valve under a drive that will not operate in either direction.
- 2026-10-19 3 questions changed: one wrong option was reworded in each, and the questions, answers and explanations are unchanged. In each one, only the answer repeated a word from the question, so it could be picked on wording alone. Spring brakes that have lost air pressure and cannot be caged: the torch option now mentions air pressure. Slow cranking with a 0.8 V drop on the battery positive cable, and a low reading at the battery positive post while the alternator charges: the cable-length options now name the positive cable.
- 2026-10-16 1 question replaced and 6 explanations or key concepts corrected. Torque converter: the old question had coupling begin at about 90% of impeller speed; the new question in its place asks what happens as turbine speed comes close to pump speed (the stator freewheels and the converter works as a fluid coupling), as Allison’s operator manuals describe it, with no fixed percentage. Spring brakes: the explanation called 90 psi a minimum and said the brakes release at 60 psi and fully release at 90 psi or more, with no source; it now gives Ontario’s air brake handbook (about 60 psi releases them) and SGI’s air brake manual (70 psi or more holds them released, they may drag below about 70 psi and they fully apply between 20 and 45 psi), so the 90 psi in the answer is enough to release them. Supplemental coolant additive: a single range of 1.5–3.0 units per gallon, tested at every service, was removed because the range depends on the additive and the coolant; the explanation now gives Cummins’ statements that under-concentration leads to liner pitting and over-concentration to additive drop-out, plugged radiator tubes and overheating. Starting circuit voltage drop: the limits are now the makers’ (Hino: under 0.2 V on the positive circuit while cranking; Delco Remy: more than 0.5 V for the positive and negative sides together at a 500 A carbon-pile load is too high). Charging circuit voltage drop: the test is now described as Delco Remy prints it, with a carbon pile loading the circuit to the alternator’s rated output and both sides added together, in place of an engine-speed test with limits that had no source. Wording that a topic appears regularly on safety exams and that a step is often skipped was removed.
- 2026-09-14 7 explanations corrected in the hybrid and electric equipment questions: one from the audit list and six found when the rest of that block was re-checked. No question, option or answer changed.
- 2026-09-13 15 questions removed. Three taught the torque-converter stall test backwards, or offered two defensible answers built on that rule; twelve more had two defensible answers or stated a diagnostic rule the wrong way round.
- 2026-09-13 12 explanations or key-concept lines corrected.
310T Truck & Transport Mechanic
Bank size: 165 before the audit, 161 after; 225 after the November 2026 expansion.
- 2026-11-25 64 questions added (161 → 225), mostly in official exam blocks the bank did not cover: Steering, Suspension & Tires (20), Trailers & Coupling (13) and HVAC (6) are new topic tabs; 12 air brake, 11 regulations and inspections (cab items) and 2 hybrid-electric safety questions (under Electrical) were added too. Every question was written from a named source (CCMTA National Safety Code Standard 11, the Motor Vehicle Safety Regulations, Ontario’s official air brake handbook, and Hendrickson, SAF-Holland, Meritor and Red Dot service manuals, each named in the question where the fact is the maker’s), then passed an attack review, a source review, a re-check and a whole-set review. 102 were drafted; 38 were dropped.
- 2026-11-16 1 explanation and its key concept corrected; the question, options and answer are unchanged. J1939 network on which several modules drop out at once: the explanation said a failed module only ever takes itself off the network. A CAN transceiver maker’s application note says some transceivers present a low impedance to the bus when they lose power and stop all data on it. The explanation and key concept still point to the backbone first, and now say that one unpowered module can also take the whole network down.
Earlier updates for 310T (8)
- 2026-11-06 1 question changed; the same option is correct. Battery discharged overnight with the isolator switch off: the correct option was the only one that repeated words from the question (isolator switch); it now reads “A load is drawing current past the battery disconnect”. The explanation adds why the other options do not fit: an alternator or a starter fed through the switch is cut off with it, and a healthy lead-acid battery loses only a few percent of its charge a month to self-discharge, far too little to flatten it overnight.
- 2026-11-04 1 explanation and its key concept corrected; the question, options and answer are unchanged. Battery discharged overnight with the isolator switch off: the 2026-11-02 correction put the ammeter between one battery terminal and everything connected to it, but on a truck with several batteries that meter reads only one battery’s share, and an accessory wired straight to another battery bypasses it. The explanation now says to put the meter where every path from the batteries runs through it: with several batteries, leave the leads that join the batteries in place and meter the negative post where the main cable to the frame lands, together with any negative post joined straight to it. The possible causes now read a switch whose contacts no longer make a complete break when it is turned off, or a circuit wired around the switch.
- 2026-11-02 1 explanation and its key concept corrected; the question, options and answer are unchanged. Battery discharged overnight with the isolator switch off: the test was a clamp-on ammeter on the cable between the switch and the battery. It is now an ammeter in series between one battery terminal and everything connected to it, as for a key-off drain test, so the meter sees the whole draw, including any circuit wired around the switch. The explanation adds that a clamp-on ammeter works for this only if it is a DC (Hall effect) clamp that resolves milliamps: a current transformer clamp does not read DC, and a clamp built for large currents may not register a draw below about half an ampere. “Common causes” now reads “Possible causes”.
- 2026-10-29 3 questions changed; the questions, options and answers are unchanged. Air brake lining at a periodic inspection: the explanation said a 1/16 inch (1.6 mm) figure circulates widely in study material; it now says only that the figure is nowhere near what a Canadian periodic inspection will pass. Air brake endorsement: a key concept line on what the topic is tested on was removed. Hours of service: the explanation and key concept no longer say that the 10-hour figure and the two off-duty rules are easily confused.
- 2026-10-16 1 explanation corrected (common-rail high-pressure pump): an injection pressure of typically 1,600–2,200 bar and a transfer-pump pressure of about 5–10 bar, neither of them sourced, were replaced with Bosch’s figures for its commercial-vehicle system, built for system pressures of up to 2,500 bar in versions scalable between 1,800 and 2,500 bar, and the key concept now describes fuel delivery to the rail as Bosch meters it (a metering unit or electric suction valves on the pump). Question, options and answer are unchanged.
- 2026-09-13 4 questions removed: one had two defensible answers on spring-brake apply pressure, one described a DEF inducement stage that does not exist, and two more were removed after two independent reviews.
- 2026-09-13 4 explanations corrected, including one that gave an out-of-date US speed limit for DEF-fault engine derate; it now points to the engine maker's service information.
- 2026-09-13 2 questions that tested the same fact as another question were replaced with new questions on different facts.
310S Automotive Service Technician
Bank size: 139 before the audit, 139 after; 183 since 2026-11-13.
- 2026-11-16 1 explanation and its key concept corrected; the question, options and answer are unchanged. Why an A/C system is evacuated before recharging: the explanation said to evacuate to about 29 inHg. A compound-gauge reading depends on elevation: at sea level 29 inHg of vacuum still leaves about 23,400 microns of absolute pressure, and above about 500 m it cannot be reached at all. The explanation now says to evacuate to the vacuum level and for the time the service information specifies, and that a reading that keeps rising while the vacuum is held indicates a leak.
- 2026-11-13 44 questions added; the bank grows from 139 to 183. 21 electrical (high-voltage safety on the 2012 Toyota Prius v, EV charging levels, lead-acid battery handling, lighting and signalling rules in the federal Motor Vehicle Safety Regulations, and Ontario and Manitoba lamp inspections), 10 engine (MAHLE failure analysis of pistons, valves and bearings, and reading the API oil symbol), 7 suspension, steering and tires, 4 brakes, 1 clutch and 1 air conditioning. Each question was written from a public source that its explanation names, then had its answer and wording reviewed and, separately, every statement checked against that source; drafts that failed either check were discarded, not patched (64 of 108).
Earlier updates for 310S (4)
- 2026-10-30 1 question changed; the same option is correct, and its wording changed. Front strut replacement: the question now says both front struts have been replaced on a vehicle with strut-type front suspension and asks which angles should then be checked, and adjusted where they are out of specification, where it said MUST. The correct option now names camber, caster and toe, where it named camber and caster, and all four options were rewritten. The explanation and key concept now rest on named maker documents for the vehicles they cover (General Motors Service Update A192221650, Mitsubishi recall SR-13-008 and Hyundai TSB 20-SS-001H), and on Monroe technical guides for how the strut attaches to the steering knuckle.
- 2026-10-29 1 explanation edited; the question, options and answer are unchanged. Front strut replacement: a closing sentence calling a skipped alignment a common comeback cause was removed; the explanation still says alignment should be verified.
- 2026-10-16 1 question replaced. Brake pull: the old question asked for the most likely cause of a vehicle pulling to the right when braking; it had a second defensible answer and taught the same point as another 310S question. The new question in its place is a hydraulic brake force calculation: a 20 mm master cylinder piston pushed with 1,000 N and a 60 mm caliper piston give 9,000 N at the caliper, ignoring losses, because the pressure is transmitted undiminished (Pascal’s law) and the force scales with piston area, which goes with the square of the diameter. The explanation follows the brakes chapter of Goodheart-Willcox’s Auto Fundamentals and a SkilledTradesBC apprenticeship text.
- 2026-09-13 No questions removed. 1 explanation corrected, and 1 question that tested the same fact as another question was replaced with a new question.
306A Plumber
Bank size: 135 before the audit, 130 after.
- 2026-10-30 5 questions changed; the same option is correct in each. Sizing the natural gas main for a 500,000 BTU/h commercial kitchen: the question now gives its own example capacity table and does not state CSA B149.1 figures. The table is labelled as practice figures, not taken from CSA B149.1, and the explanation tells the reader to use the CSA B149.1 Annex A table on the job. The earlier version printed its capacity figures as a reading of that table, which we could not confirm because the standard is paid. The question now names the total length/total load method, the explanation and key concept say Saskatchewan also accepts an actual length/actual load method, and the sentences saying what candidates who chose a wrong answer have usually done were removed. Backfilling a drain trench: the question now says the pipe manufacturer gives no backfill instructions and the pipe is not being encased in concrete, and it names the National Plumbing Code of Canada; the options, explanation and key concept now follow NPC Articles 2.3.5.1 and 2.3.4.6, and a sentence on a 75 mm concrete layer over vitrified clay, which is not in the 2015, 2020 or 2025 editions, was removed. Type K copper service in corrosive soil: the explanation and key concept now say the NPC summary table permits soft-temper Types K and L underground, and a line calling an idea about copper a belief that puts services in the ground unprotected was removed. DWV air test: a clause calling the point easy to reverse was removed. Supports for horizontal ABS drainage piping: a clause saying this is how it goes wrong on site was removed.
- 2026-10-29 6 questions changed; the questions and answers are unchanged. Six explanations had wording that called a point a common exam point, called a field shortcut or a mix-up common, or said how a calculation usually goes off; it was removed or the sentence rephrased, and the facts are unchanged: the flaring tool, backfilling a drain trench, gas piping materials, a buried steel gas line, wet vent length and sizing a hot water recirculation circulator. In the gas piping explanation the copper sentence now says the gas code does not ban copper for propane, where it called that ban an old shop rule. Flaring tool: only the answer repeated a word from the question (flare), so it could be picked on wording alone; it now reads “To form a conical bell on soft tubing ends”.
Earlier updates for 306A (6)
- 2026-10-28 1 explanation and its key concept corrected; the question, options and answer are unchanged. Minimum grade of a 3 in (75 mm) horizontal drain: the explanation said that with too much grade the liquid races ahead and leaves the solids behind, and the key concept said larger drains are allowed a flatter grade, not a steeper one. National Plumbing Code Note A-2.4.8.1.(1) says steeper slopes and higher velocities help keep pipes clean. Both now say that the 1 in 50 grade Sentence 2.4.8.1.(1) sets for drainage pipes NPS 3 or less is a minimum, not a maximum, and the key concept adds the Note’s advice that slopes below 1 in 100, permitted for pipes over NPS 4, be used only where necessary. A reason given for flatter grades on larger pipes, with no source, was removed.
- 2026-10-19 2 questions corrected; the answers are unchanged. Drain loads in fixture units: the key concept listed a 2-1/2 in branch row (12 fixture units) that National Plumbing Code Table 2.4.10.6.-B does not have, and the explanation and key concept ruled out one wrong option with US model-code figures (3 in = 20, 4 in = 160) for which we have no source. Every figure now comes from the NPC 2020 and 2025 tables: an NPS 3 branch, and an NPS 3 building drain at 1 in 50, each carry 27 fixture units, 36 is the building-drain figure at 1 in 25, and 20 is not a value either table gives an NPS 3 pipe. Expansion tank: the key concept cited the BC Plumbing Code 2018 for the thermal expansion rule and now cites the National Plumbing Code 2020 and 2025, Article 2.6.1.11., which reads the same in both. Only the answer repeated the question’s words for expansion and heating, so it could be picked on wording alone; it now reads “To absorb the volume increase as water warms”.
- 2026-10-16 1 explanation corrected; the question, options and answer are unchanged. Water heater drain pan: the explanation now cites National Plumbing Code Article 2.6.1.7., whose drain-pan sentences and relief-pipe clauses read the same in the 2020 and 2025 editions, and rebuts the wrong answers from it: a pan teed into the relief valve discharge pipe would empty through a pipe of the relief pipe’s own size rather than one two sizes larger, and would have no drain of its own under the relief discharge; a trapped pipe tied straight into the branch drain is not the indirect connection Article 2.4.2.1. requires for a drain or overflow from a water system. Wording that called an error common was removed.
- 2026-10-16 3 explanations corrected; one of the three questions was also reworded. Options and answers are unchanged. Bathroom exhaust fan: the explanation said a fan rated exactly 50 CFM sits right on the 25 L/s minimum of National Building Code Article 9.32.3.7; 50 CFM is about 23.6 L/s and falls short (about 53 CFM is needed). It also said British Columbia dropped its 23 L/s intermittent and 9 L/s continuous figures, but BC’s 2024 Building Code keeps them, and a US ASHRAE figure was removed. The question now names the 2020 and 2025 editions of the National Building Code, and the check on delivered airflow is tied to the fan’s rating at a set external static pressure (25 Pa for this fan, Article 9.32.3.10). Water heater supply: the explanation said the plumbing code sets no minimum size; National Plumbing Code Sentence 2.6.3.4.(4) sets NPS 3/4 for the supply to a water heater that serves more than one fixture, and the tank connection size is now quoted from water heater makers’ manuals. Fill valve: a fill valve that will not shut off was described as phantom flushing; it gives a running toilet, and a toilet that refills on its own is losing water, past the flapper or flush valve or through a refill tube pushed too far into the overflow pipe (Fluidmaster). Wording about what the exam often asks and which errors are common was removed from all three.
- 2026-09-13 5 questions removed: one asked about a wall-hung water closet and answered with the floor-mount procedure; four more were removed after two independent reviews.
- 2026-09-13 3 explanations corrected, and 1 duplicate question replaced with a new question.
309A Construction Electrician
Bank size: 135 before the audit, 131 after; 181 since 2026-11-19.
- 2026-11-23 4 questions changed. CAT III tester on a 600 V motor control centre: the correct option said a CAT IV tester may be needed, and the key concept rated receptacles and listed impulse-voltage figures we could not source. The question now puts the MCC on a feeder from the plant’s main switchboard. The correct option (same position) now says a CAT III tester is appropriate there, because the measurement category follows the location in the installation; a new wrong option states the common belief that every MCC needs CAT IV. Contactor coil reading 0 Ω: the question now says the coil was disconnected, and the explanation drops an unsourced typical resistance range and the claim that zero ohms means the insulation between turns has broken down. Clamp meter: the explanation and key concept called clamping “safe” and gave an unsourced minimum current. They now say the meter senses the magnetic field around one conductor, that it is quick but not safe in itself near energized parts, and that small currents may be below what it can resolve. Non-metallic-sheathed cable in a basement: the explanation counted a drop to a panel among the runs caught by the 1.5 m rule and offered a wood running board as protection for a drop. It now names a furnace or water heater and protection by location, and a sentence that contradicted the explanation’s own first line was rewritten.
- 2026-11-19 50 questions added; the bank grows from 131 to 181. 20 on generating, distribution and service systems (service and feeder load calculations, services, grounding electrodes and bonding, single point grounding, a delta-to-wye conversion, interconnecting generators and solar inverters, transformer derating, testing and K-factor, breakers and fuses), 11 on signalling and communication systems (fire alarm silencing, alarm signal patterns, in-suite audible devices, voice communication and paging, carbon monoxide alarm location, smoke alarm wiring on Class 2 circuits, an energy management system on an EV charger circuit), 10 on wiring systems (NMD90 installation details, AFCI and GFCI on new and extended circuits, replacement breakers, cable protection, wiring at a gasoline dispenser, lighting retrofits and exit signs), 7 on motors and controls (jog, plugging and anti-plugging circuits, wye or delta identification, and ABB soft starters) and 2 on rigging. Code questions rest on regulators’ published explanations of the code, which each explanation names with its date: Electrical Safety Authority bulletins on the 2024 Ontario Electrical Safety Code, Alberta STANDATA bulletins on the 2024 Canadian Electrical Code, Technical Safety BC, and the National Building Code of Canada 2020. Each question was written from a public source that its explanation names, then had its answer and wording reviewed and, separately, every statement checked against that source; drafts that failed either check were discarded, not patched, and the whole set was then reviewed together for questions that give each other away. 114 were drafted and 64 were not added: 50 failed a check, and 14 that passed were held back to keep this round at 50.
Earlier updates for 309A (12)
- 2026-11-04 1 explanation corrected; the question, options and answer are unchanged. Like-for-like replacement of a receptacle beside a bathroom basin in Ontario: the explanation said arc fault protection does not respond to current leaving the circuit through a person; it now says arc fault protection is fire protection rather than shock protection for a person. Where it said the protection may come from a device upstream, it now says a Class A ground fault circuit interrupter upstream. A line calling a ground fault receptacle the ordinary way it is done was removed, and the test-button line no longer states a requirement.
- 2026-11-02 1 question changed; the same option is correct. Ground fault on a 15 A branch circuit: the correct option said a Class A device trips on 4 to 6 mA in milliseconds, and it now reads that a Class A GFCI trips on a 4 to 6 mA imbalance between conductors. Only that option repeated the question’s word “ground”, so it could be picked on wording alone. The key concept now says threshold and trip time are separate specifications: the maximum permitted trip time falls as the imbalance grows, from about 5.6 s at 6 mA to about 20 ms at 300 mA or more (the inverse-time curve of CSA C22.2 No. 144.1, harmonized with UL 943). The explanation now calls 4 to 6 mA a few thousandths of an ampere, where it said roughly a thousandth of what the breaker needs, and says an arc fault device is fire protection rather than shock protection for a person, where it said a clean ground fault through a person passes it unremarked.
- 2026-10-30 5 questions changed; the same option is correct in each. NMD90 installation: the correct option now reads “In wet locations, in underground raceways, or exposed to mechanical damage”, where it said in concrete or masonry, and it now rests on Electrical Safety Authority Bulletin 12-19-17. The other three options were rewritten as places that bulletin accepts. The explanation no longer says wet means underground and no longer says what a candidate is likely to be marked on, and it now gives the bulletin’s protection wording for studs, joists and the faces of members. Direct-buried branch circuit to a detached garage: the explanation and key concept now use the bulletin’s words, dry or damp locations only, where they called NMD90 a dry-location cable. Ground fault on a 15 A branch circuit: the key concept no longer says a rule catches most garages and carports; it now says receptacles installed outdoors and within 2.5 m of finished grade need Class A protection too (Rule 26-704, ESA Bulletin 26-29-6). 120/208 V feeder colours: the explanation now says black, red and blue swaps phases A and B, where it called that a habit carried over from single-phase work, and a clause saying some shops extended orange, brown and yellow to 347/600 V circuits was removed. Sealing fittings in hazardous locations: “case is easy to miss” in the key concept now reads “further case”.
- 2026-10-29 2 key concepts edited; the questions, options, answers and explanations are unchanged. Delta and wye voltages: a closing line telling the reader to know both configurations for the exam was removed. Ground fault on a 15 A branch circuit: the line saying room-based lists mislead on Canadian questions now says room-based lists are the US National Electrical Code approach, and that code has no force in Canada.
- 2026-10-28 10 questions changed: 2 replaced, 3 reworded with their explanations corrected, and 5 more explanations corrected. In the reworded questions the keyed choice is the same. Overcurrent device for a conductor with an allowable ampacity of 97 A: the answer, 100 A as the next standard rating above, rested on an allowance to round up to the next larger standard rating, for which no accepted source was found. The new question in its place asks up to what device rating the Table 13 alternative in Rule 14-104 applies: 800 A, as Burr’s road map to the 26th edition of the CE Code gives it. Three more Section 14 questions (protection where a feeder is reduced in size, conductors for a 20 A circuit, and the largest device for a conductor corrected to 60 A): their explanations taught the same allowance, and it was removed; Rule 14-104 is now given as Burr sums it up, the device generally not above the ampacity of the conductors it protects, with Table 13 as the alternative up to 800 A. Also removed, with no source: fixed ceilings of 15, 20 and 30 A for 14, 12 and 10 AWG copper, the conductor sizes tied to 15 A and 20 A breakers, a list of ampacity corrections, and wording that called an error common. The 80% continuous-load limit is now given with its conditions under Rule 8-104 (a device marked for 80% continuous operation, or not marked). Shock approach boundaries at 15 kV and at 600 V: the question rested on approach-boundary distances from the CSA Z462 tables, for which no accepted source was found. The new question in its place asks what the arc flash PPE selection tables of the 2024 edition give in place of the PPE category numbers: a minimum arc rating of 4, 8, 25, 40 or 75 cal/cm² (CSA Group’s overview of the 2024 edition). PPE for energized work on a 600 V panel: the answer was the longest option and the only one that listed both kinds of protection, so it could be picked on its form. All four options now pair a type of glove (voltage-rated rubber gloves or leather welding gloves) with an outfit (arc-rated clothing and face protection, or plain cotton coveralls and safety glasses), and the answer is voltage-rated rubber gloves with arc-rated clothing and face protection. The explanation now follows CSA Group’s overviews of the 2024 and 2015 editions of CSA Z462 (two hazards, shock and arc flash; arc flash PPE chosen by an incident energy analysis or by the table method; rubber insulating gloves worn with protectors, the 2024 term), and glove class voltages and a call for hearing protection, with no accepted source, were removed. Steps after lockout: the question asked for the required sequence of steps, but no accepted source gives an order for the steps after lockout, and the answer began with attempting a start, which none of our sources states. The question now asks what is required after the equipment is isolated and locked out, before the maintenance starts, and the answer reads: verify the lockout and the stored-energy discharge, test each point of work, apply grounds if required (WorkSafeBC OHS Regulation s. 10.6, Ontario Regulation 213/91 s. 190, and CSA Z462 as CSA Group’s overviews describe it). An apprentice working under a journeyman’s lockout: the answer was shorter than every other option, and now reads that each worker must install their own personal lock before doing any work exposed to the hazard. The explanation said CSA Z460 and CSA Z462 require each exposed worker to control their own isolation point with a personal lock, with no source; it now gives British Columbia’s OHS Regulation as an example (Part 10, ss. 10.7 to 10.9), including its exception: where the worker who installed a lock cannot remove it, the supervisor or manager in charge is responsible, after every reasonable effort to contact that worker and after making sure the equipment can be operated safely. Electrically safe work condition: the explanation now cites Ontario Regulation 213/91 s. 190, the 2024 edition’s requirement to verify the absence of voltage at each point of work (Clause 4.2.5), grounding in the job plan (2015 edition) and WorkSafeBC s. 10.7, and statements with no source were removed, among them an order for applying grounds and a list of stored-energy types. Motor branch-circuit conductors at 125% of full-load current: the rule’s only source was a trade magazine column; it is now cited from the installation bulletin BTI-015 of Quebec’s Corporation des maîtres électriciens (2019, on the 2018 code) and Alberta’s STANDATA 24-ECB-028 (2025, on the 2024 code).
- 2026-10-20 1 question changed: only its key concept; the question, options, answer and explanation are unchanged. Voltage drop under Rule 8-102: the key concept gave the single-phase formula with a circular-mil constant (K = 12.9 for copper, the run length in feet and the conductor area in circular mils) and a worked example built on it. These were removed, as the same constants were from the 309A common mistakes page on this date. The key concept now gives VD = 2 × L × R × I, with L the one-way run, R the conductor resistance per unit length and I the current, and says the factor of 2 accounts for the return conductor, so the length is not doubled again. The 3% and 5% limits are unchanged.
- 2026-10-19 3 questions changed; the answers are unchanged. Range demand in a dwelling service calculation: the key concept ended by saying Canada has no rule that multiplies a continuous load by 125% and adds the non-continuous load, and that this additive method belongs to the US National Electrical Code. We have no source for either statement, so that sentence was removed from this question. Only the answer used the question’s word “size”, so one wrong option now says the Code carries a range of any size at full nameplate. Gas piping bonded to a separate ground rod (Ontario): only the answer used the question’s word “electrical”, so the wrong option about a low-resistance rod now says the rod is acceptable to the electrical inspector; it is still wrong. Service factor: the explanation now names its source in full, the SkilledTradesBC open textbook Block E: Transition to Journeyperson on BCcampus (Competency E2, Learning Task 3). Before, it said only “the SkilledTradesBC text on BCcampus”.
- 2026-10-16 2 questions reworded with their explanations corrected; answers are unchanged. Overload trip class on a long run-up: the answer, a relay with a longer trip class at the same current setting, no longer names Class 20, and the explanation no longer says a longer trip class leaves the running protection where it was: Rockwell Automation’s trip class comparison chart shows a longer class also trips later on a running overload. The overload settings of 115% and 125% of full-load current were removed from this question too; the setting is now tied to the service factor marked on the motor (Rule 28-306, from Burr’s road map to the 2024 code). One wrong option, a timing relay that bypasses the overload contact while the motor accelerates, now jumpers the contact out altogether, and the explanation says Rule 28-310 permits overload protection to be shunted only during the starting period. Flexible metal conduit: the answer is unchanged (a bonding conductor run within the conduit), and the question now names Rule 10-610 of the 2018 CE Code. The rule is now cited to Alberta’s STANDATA 18-ECB-010, written to the 2018 code, and the wording about the armour to the SkilledTradesBC plumbing apprenticeship text on BCcampus, which reproduces the subrule without naming a code edition; the explanation says to check the subrule in the edition in force where you work. The statement that the short-run, small-circuit allowance belongs to American codebooks, and the wording with it about how often that error is made, were removed.
- 2026-10-16 3 questions reworded with their explanations corrected, and 1 more explanation corrected; answers are unchanged. Continuous loads under Rule 8-104 (two questions): the options now give only the ampere values, without reasons attached. One of them described the free-air limit as 70% of the circuit rating; both now give it as Burr’s road map to the 2024 code does, 70% of the ampacity of single conductors selected under Section 4 (the free-air tables), beside the limits for a device marked for 80% or not marked: its marking, or 80% of the conductor ampacity. In that question a comparison with the US National Electrical Code and a sentence about Section 26, neither of them sourced, were removed, and a continuous load is now defined: a load counts as continuous unless in normal operation it will not persist for more than 1 h in any 2 h period (loads up to 225 A) or 3 h in any 6 h period (above 225 A). The other question now says its feeder is run as conductors in a raceway, and its list of classic errors was removed. Motor branch-circuit conductors: the question now says the motor is on continuous duty and names Rule 28-106, the options give only the values, and the 125% minimum is quoted from Rule 28-106 1) of the 2024 edition; overload percentages (115% and 125%) and Table 29 percentages (250% and 175%), which had no source, were removed from its key concept, along with a statement that the 125% factor covers motor starting. Service factor: overload settings of 125% and 115% of full-load current, confirmed only for the 2018 edition of the Canadian Electrical Code, were removed from this question; service factor is now given as the Code defines it, as quoted by Burr (a multiplier on rated horsepower indicating the permissible continuous loading at rated voltage and frequency), with the SkilledTradesBC example of a 10 hp motor with a service factor of 1.15 delivering 11.5 hp, and a statement with no source that a service factor of 1.0 means no overload capability was removed.
- 2026-10-16 1 key concept corrected (bonding gas piping): bonding the piping to its own ground rod is now described only as not complying, with the Electrical Safety Authority’s reason; the line calling it a common field error was removed. Question, options and answer are unchanged.
- 2026-09-13 4 questions removed: one mixed CSA Z462 PPE categories with an incident-energy analysis, one gave an unsupported conductor size for luminaire wiring, one more was removed after two independent reviews, and one after the two reviewers disagreed and a third review found the question's premise wrong and a second option defensible.
- 2026-09-13 5 explanations corrected, and 4 duplicate questions replaced with new questions.
442A Industrial Electrician
Bank size: 135 before the audit, 130 after.
- 2026-11-23 1 key concept corrected and one wrong option lengthened; the answer is unchanged. Measuring current with a multimeter: the key concept said to always check the voltage range before measuring current, which is not the safety step. It now gives the set-up (power off, open the circuit, meter in series, red lead in the amp or milliamp jack for the expected current, then power back on to read) and warns that leads left in a current jack short any voltage source they touch.
- 2026-10-29 1 explanation edited; the question, options and answer are unchanged. Delta-wye transformer connection: a “Red Seal point” label before the sentence on 600 V/347 V systems was removed.
Earlier updates for 442A (7)
- 2026-10-28 8 questions changed: 3 replaced, 1 reworded with its explanation corrected, and 4 more explanations or key concepts corrected. Three CSA Z462 questions rested on figures for which no accepted source was found: a limited approach boundary compared between a fixed circuit part and a movable conductor, a six-step order for establishing an electrically safe work condition, and a rule that the arc rating must be at least the calculated incident energy (that question also called rounding down common). The new questions in their place ask, from CSA Group’s overview of the 2024 edition, when energized work may go ahead instead of an electrically safe work condition (only where establishing that condition is not practicable), where the absence of voltage must be verified (at each point of work, Clause 4.2.5), and what the 2024 edition calls the gloves worn over rubber insulating gloves (protectors, of leather or another material). Arc flash: the question asked which CSA standard governs arc flash safety and now asks which covers protection from it in the workplace; the answer, CSA Z462, is the same. The description of an arc flash now follows Ontario’s Workers Health & Safety Centre, and a temperature of up to 20,000°C and an arc flash suit rated in cal/cm², with no source, were removed. PPE for energized work at 600 V: the explanation and key concept now follow CSA Group’s overviews of the 2024 and 2015 editions; glove class voltages (Class 00 at 500 V, Class 0 at 1,000 V) and the statement that there is no blanket minimum arc rating were removed, and leather protectors are now protectors, the 2024 term. Motor branch-circuit conductors at 125% of full-load current (three questions): the rule is now cited from Quebec’s CMEQ installation bulletin BTI-015 and Alberta’s STANDATA 24-ECB-028 in place of a trade magazine column, and a remark from that column, that these rules depart from Rule 14-104 so that motor inrush current does not trip the device, was removed.
- 2026-10-20 1 question changed: three options were reworded; the question, the keyed choice and the explanation are unchanged. Direct-on-line (DOL) motor starter: only the answer repeated the question’s words “direct” and “motor”, and it was the longest option, so it could be picked on wording alone. The answer now reads “Full supply voltage applied to the motor at start-up”, and the wrong options about series resistors and a gradual voltage increase now also name the motor.
- 2026-10-16 1 question rewritten with its explanation corrected. Voltage unbalance: the question gave a 2% unbalance and asked what NEMA MG-1 calls for, with derating the motor or correcting the supply as the answer; a 1% limit with derating beyond it, a statement that most manufacturers’ warranties are then void and a rule that insulation life halves for every 10 °C were removed. The question now gives a 3% unbalance on a loaded motor whose overload relay has begun to trip and asks for the right response: find and correct the cause of the supply unbalance. The explanation follows US Motors (Nidec), based on NEMA MG 1: the current unbalance runs roughly 6 to 10 times the voltage unbalance, and in the hottest phase the temperature rise goes up by about twice the square of the percentage unbalance (about 18% at 3%). Raising the overload setting and relying on the service factor are ruled out from the same guidance and from the Code’s definition of service factor, and the makers’ limits are given for the products they cover: Danfoss NTZ compressors, 2% voltage unbalance; Copeland’s 1.5–5 ton ZP scrolls, a current imbalance over 20% to be investigated.
- 2026-10-16 2 questions reworded with their explanations corrected. Thermal overload relay: the answer is unchanged (it protects the windings from sustained overcurrent). The overload settings of 125% and 115% of full-load current, confirmed only for the 2018 edition, were removed from this question as well; the explanation now says Rule 28-306 sets the overload device with the motor’s marked service factor taken into account and that the limits come from the code edition in force, and it describes the thermal element from the BCcampus Basic Motor Control text and Rockwell Automation (a Class 10 relay trips in less than 10 seconds at locked-rotor current). One wrong option now reads reversed phase rotation instead of voltage imbalance: a thermal element responds only to the heat of the motor current, and Rockwell lists phase rotation among the voltage-protection functions of its advanced electronic relays. 3.6 mA on a 4–20 mA loop: the keyed answer was reworded from verifying the loop supply and trimming the zero to reading the transmitter’s diagnostics and checking its supply and sensor; the explanation now says a zero trim or recalibration comes only after the failure signal has cleared, and gives the NAMUR NE 43 levels as transmitter makers implement them (Endress+Hauser, Pyromation): down to 3.8 mA below range, 3.6 mA or less for a failure signal.
- 2026-10-16 1 question replaced, 3 questions reworded with their explanations corrected, and 7 other explanations or key concepts corrected. Service factor: the old question keyed “no action needed” for a motor drawing 46 A against a 42 A nameplate with a service factor of 1.15, by multiplying the full-load current by the service factor; service factor is a multiplier on rated power (NEMA MG1, as EASA quotes it), and the new question in its place asks which statement about the motor is correct: its winding runs hotter and its insulation life is shortened. Motor protection: overload settings of 125% and 115% of full-load current, which were confirmed only for the 2018 edition of the Canadian Electrical Code, were removed from four questions; the 125% minimum for the branch-circuit conductors of a continuous-duty motor is now quoted from Rule 28-106 1) of the 2024 edition and stated the same way in the three questions that use it; and branch-circuit overcurrent protection is described from Rule 28-200 and Table 29. Motor nameplate: the options were rewritten so that the answer is no longer much shorter than the others. Polarization index: the question now states Class F insulation, and the minimums are given by insulation class (1.5 for Class A, 2.0 for Class B and higher; IEEE 43 as quoted by test-instrument makers and ANSI/EASA AR100). PLC scan time: the question asked about program scan time, which is one part of the scan, and a typical range of 1–100 ms with no source was removed. Approved equipment (Section 2): a list of certification marks, a statement about UL marks without a small “c” and an Ontario regulation number had no source; the explanation now uses the Electrical Safety Authority’s bulletin wording. Harmonic filters: the explanation that listed drives among the loads that overheat neutral conductors (noted as under review on 2026-10-15) now says that balanced three-phase drives produce no triplen harmonics (Rockwell Automation). Direct-on-line starting current is now ABB’s figure, usually 6 to 8 times rated current, not 5–8 times. Wording that a topic is often tested on the exam or that an error is the usual or most frequent one was removed from three explanations.
- 2026-09-13 5 questions removed: one had two defensible answers, and four more were removed after two independent reviews.
- 2026-09-13 7 explanations corrected.
313A Refrigeration & Air Conditioning Mechanic
Bank size: 116 before the audit, 115 after.
- 2026-11-23 1 key concept corrected and wrong options reworded in 2 questions; the answers are unchanged. Compressor that will not start: the key concept gave one ±10% tolerance for every capacitor and called the run capacitor the most common failure. It now says to compare the reading with the rating marked on the capacitor and the tolerance its maker gives. Walk-in freezer with low suction and high superheat, and rooftop unit not holding setpoint: wrong options were shortened or reworded so the correct option no longer stands out by its length or its form.
- 2026-11-16 3 explanations or key concepts corrected; the questions, options and answers are unchanged. Walk-in freezer with low suction pressure and high superheat: the key concept listed a dead evaporator fan and a frost-blocked coil among the causes of that pattern. In equipment makers’ troubleshooting tables lost evaporator airflow pulls suction pressure down but leaves superheat low or about normal, not high; the key concept now gives it a line of its own. Walk-in cooler at setpoint with every reading normal: the explanation and key concept listed an evaporator fan out and an iced or dirty evaporator as load sources. Lost airflow pulls suction pressure below normal, so it cannot sit behind normal readings; both were taken off the load list and the reason is given. Rooftop unit not holding setpoint with normal pressures on both circuits: the explanation listed a dirty condenser coil and a dirty evaporator coil among the causes, and the key concept said to check both coils. A dirty condenser drives head pressure up and a dirty evaporator pulls suction pressure down, so neither is what normal pressures point to; the explanation and key concept now say so.
Earlier updates for 313A (11)
- 2026-10-30 1 question replaced; the same option is correct. Variable frequency drive on a condenser fan: the two-part question, which asked what the drive does and what a common installation mistake is, now asks which arrangement puts the winding insulation of a 460 V motor most at risk from reflected-wave voltage spikes. The options, explanation and key concept were rewritten from US Department of Energy Motor Systems Tip Sheet 14, which cites NEMA MG 1-2011, and the explanation says a general-purpose motor on a fan is not wrong in itself. The lines on Class F insulation, shaft grounding and input line reactors were removed.
- 2026-10-29 2 explanations edited; the questions, options and answers are unchanged. Liquid receiver: the explanation now sets the receiver apart from two other vessels, where it said the receiver is often mixed up with them. R-410A as a near-azeotropic blend: an opening line saying two things get confused here now reads “Two separate things are at work here”.
- 2026-10-28 1 explanation and its key concept corrected; the question, options and answer are unchanged. Capillary tube when the evaporator load rises: the explanation opened by saying the tube passes whatever the pressure difference across it will push through a fixed bore, and the key concept said flow follows the pressure difference across a fixed bore; neither had a source. Both now say only what the Danfoss article they cite states: the restriction is fixed, so the device cannot open further when the load rises.
- 2026-10-21 3 questions changed. Capillary tube when the evaporator load rises: the keyed choice is the same, and the answer now says the tube cannot adjust its restriction because its bore and length are fixed; it no longer repeats the question’s word “respond” and is no longer the shortest option. The explanation said a capillary tube does not meter, although the question calls it a metering device; it now says the tube does not modulate. Statements that flow depends on the tube’s length and that capacity falls short were removed, and so was the list of consequences (critical charge, no receiver, accumulator, sensitivity to charge error). The explanation now quotes Danfoss (ASHRAE Journal, February 2020): a fixed orifice device will not open more when the load increases, which raises the superheat, and when the load decreases the risk of liquid reaching the compressor rises; a TXV modulates to hold superheat constant. The key concept now says “no moving parts” of capillary tubes, where it said it of all fixed orifices. Compressor restart timer: the question now describes a single-phase condensing unit with a reciprocating compressor whose timer keeps the compressor off for at least five minutes. The answer is the same choice, now worded as Rheem’s installation instructions put it: a start at unequalized pressures that trips the overload or blows a fuse. The explanation follows the makers: Rheem (single-phase PSC units off for a minimum of 5 minutes so the pressures equalize, which the time delay control in the low-voltage circuit enforces; start components with non-bleed expansion valve coils on its reciprocating-compressor models) and Danfoss (a low-starting-torque device with capillary tube control and pressure equalizing, a high-starting-torque relay and start capacitor for expansion valve control or capillary control without equalizing). Scroll compressors are read maker by maker: Copeland says its ZP scrolls start unloaded with no minimum off time, apart from a short lock-out of single-phase scrolls after brief power interruptions, and Rheem keeps the 5-minute off time on its 14AJM scroll units. Statements that a fixed orifice equalizes in a couple of minutes, that TXV systems carry a hard start kit and that the timer caps starts per hour were removed. R-410A replacement: the question was rewritten. It rested on a claim about common use, and its answer named two refrigerants (R-32 or R-454B) and was the only option to repeat the question’s word “lower-GWP”. It now asks which refrigerant is designed to take R-410A’s place in new residential air conditioning equipment; the answer is R-454B, an A2L refrigerant made from R-32 and the hydrofluoroolefin R-1234yf (Chemours, Opteon XL41: GWP 466 against R-410A’s 2088, new equipment only). The explanation also gives R-32 (GWP 675; Daikin and the Ozone-depleting Substances and Halocarbon Alternatives Regulations, SOR/2016-137), and the wrong options are ruled out from the sources: carbon dioxide (Chemours: currently no comparable non-flammable, low-GWP alternative has pressures close to R-410A’s), R-125 (GWP 3 500, above R-410A’s) and R-22 (the Regulations prohibit manufacturing a product containing or designed to contain HCFC-22).
- 2026-10-19 2 questions changed; the questions and answers are unchanged. Superheat at the evaporator outlet and at the compressor suction service valve: only the answer used the question’s word “suction”. The wrong option about heat of compression now says it is added to the suction gas, and it is still wrong because that heat is added after the suction port. Charging method: the key concept now agrees with its explanation. Rheem adjusts the factory charge for liquid-line size and length, where the key concept said length only. It also now says suction pressure alone is not a charging method, where it said suction pressure; Rheem’s superheat chart is read by vapour line pressure.
- 2026-10-16 1 question replaced, 3 questions reworded with their explanations corrected, and 1 more explanation corrected. TXV hunting: the old question asked for the most likely cause and correction, and its answer listed a lost bulb charge among the causes, although the bank’s key concept on hunting says a bulb that has lost its charge does not hunt (the valve closes and the coil starves). The new question in its place asks what is built into some valves to damp hunting on a universal bulb charge: a ballast in the bulb, which Danfoss calls an anti-hunt charge. Starved evaporator: the answer is unchanged, and the options no longer carry their reasons. A superheat target of 8–12°F and a 15°F threshold, given with no source, were removed; the yardstick is now the superheat the equipment maker specifies, with Danfoss’s TR 6 figure as an example, and the wrong answers are rebutted from Rheem’s system problem table: an overcharge gives low superheat, and high subcooling appears alongside high superheat for a liquid-line restriction, a lost bulb charge, a low outdoor ambient or an inefficient compressor without causing it. High discharge temperature with normal pressures: this is the 313A question the entry below lists as still under review. The answer is unchanged (high superheat in the returning suction gas), now cited to Carlyle and Bitzer, with Copeland’s 120 °C discharge-line limit for its 2D, 3D and 8D semi-hermetics; the explanation no longer says a scroll run backwards damages itself within minutes, and the reverse-rotation and discharge-service-valve options were replaced with an overcharge and low evaporator airflow, which Rheem’s table shows moving the pressures. Scroll compressor advantage: the options no longer name four compressor types; the question describes the scroll and asks what advantage it gives over a reciprocating compressor. The answer, fewer moving parts and lower sound and vibration, is now Copeland’s (70% fewer moving parts); higher efficiency was dropped from it, statements with no source about liquid tolerance, failure modes and how widely scrolls are used were removed, and the wrong options are claims Copeland’s documents rule out (floodback with no oil dilution, pumping in either direction, pump-down on the built-in discharge check valve). Charging method: the explanation now takes each method from makers’ instructions: subcooling for TXV systems (Lennox, Trane, Daikin), liquid line pressure from the unit’s charging chart for Rheem’s expansion-valve systems, superheat against the maker’s chart for fixed orifices, and weighing in the nameplate charge where the maker calls for it. It no longer says a TXV holds superheat whatever the charge (a low enough charge still raises superheat, Danfoss), and the result it gave for swapping the two methods, with wording about how often that happens, was removed.
- 2026-10-16 2 questions rewritten and 1 more explanation corrected. Scroll compressor that no longer pumps: the question now gives the pattern makers publish for a damaged scroll on a correctly charged system that has run normally for several seasons (low discharge pressure, high suction pressure and low amp draw; Daikin’s service manual and Rheem’s system problem table) in place of a rough sound and normal subcooling; the answer now reads damaged or broken parts inside the compressor instead of worn scroll wraps, and the other options are other faults from Rheem’s table. A statement that liquid flood-back causes the wear was replaced with Copeland’s account: scroll involutes wear in rather than wear out, and excessive off-cycle migration can break scrolls if the slugging pressure is high enough. Start-up noise that clears within seconds: the answer is still refrigerant that migrated into the compressor during the off cycle, and the question and options were rewritten. The statement that scrolls are less tolerant of liquid than reciprocating compressors was replaced with Copeland’s account (the scrolls separate to let some liquid pass, but excessive floodback or repeated flooded starts dilute the oil and wear the bearings), and the prevention list now follows Copeland: a crankcase heater tied to the compressor’s charge limit by model and phase, and no pump-down cycle for migration control on its 1.5 to 5 ton air-conditioning scrolls; the old list recommended pump-down and a check valve in the suction line. Phase monitor relay: statements with no source were removed (single-phasing as the leading cause of burnout on three-phase motors, how commonly phase protection is specified, a reciprocating compressor being far less sensitive to rotation direction, fans and pumps losing their output), the current unbalance is now given as US Motors states it (about 6 to 10 times the voltage unbalance), and the explanation is built from makers’ documents (Lennox, Macromatic, US Motors, Copeland, Bitzer). Reverse rotation: two of these questions said a scroll run backwards is damaged within minutes; they now give Copeland’s statements that a short period of reverse running (under one hour) has no negative impact on durability, that the internal overload trips after several minutes, and that repeated restarts in reverse permanently damage the bearings. One more 313A question that repeats the old statement is still under review.
- 2026-10-16 1 question replaced and 7 explanations or key concepts corrected. R-22 to R-407C retrofit: the old question put low suction pressure after the conversion down to a TXV that needs recalibration or replacement; Arkema’s published retrofit data lists no TXV change-out for R-407C, and the new question in its place asks which statement agrees with that data; the answer is that the TXV stays, and the explanation adds that POE oil is required and that the charge is about 90–95% of the R-22 charge. Five explanations or key concepts gave superheat of 8–12°F, subcooling of 10–15°F or a condensing temperature 20–30°F above ambient as typical, with no source; they now point to the figure the equipment manufacturer specifies, two of them with Danfoss and Trane figures as examples, and the key concept on TXV hunting now adds that a bulb that has lost its charge does not hunt: the valve closes and the coil starves. An unsourced sentence about R-466A was removed, and the refrigerant handling card is now described as Ontario’s (an approved one-day course offered through HRAI and its delivery partners, renewed through HRAI) rather than as a card used across most of the country.
- 2026-09-13 1 question removed: it had two defensible answers.
- 2026-09-13 1 explanation corrected, and one key concept that gave the wrong reference point for R-407C superheat now reads dew point for superheat and bubble point for subcooling.
- 2026-09-13 1 duplicate question replaced with a new question on reading superheat from the dew column of a zeotropic blend's pressure-temperature chart.
420B Ironworker (Generalist)
Bank size: 120 before the audit, 121 after.
- 2026-10-29 5 questions changed; the questions and answers are unchanged. CSA W59: the explanation now tells the reader not to confuse it with CSA W47.1, where it said the two are often confused, and a summary addressed to the Red Seal ironworker exam now begins “In short”. TOS on a structural steel drawing: a line saying wrong answers often confuse TOS with the beam depth or the centreline elevation now states that TOS is neither; the answer was the longest option by 10 characters and now reads “Top Of Steel — the elevation of the beam top flange”. Four-leg bridle sling under British Columbia’s OHS Regulation, a misplaced anchor rod, and a covered deck opening under Ontario Regulation 213/91: three sentences about what people reach for or what site practice skips were rephrased, and the rules they explain are unchanged.
- 2026-10-16 1 question replaced, and 1 question reworded with its explanation corrected. Crane STOP signal: the old question asked which hand signal means STOP, but published charts differ (CCOHS shows STOP as the arm extended, palm down, held rigidly, and the same arm with the hand moved rapidly right and left as EMERGENCY STOP). The new question in its place asks what an operator must do when a worker who is not the designated signaller gives a STOP signal: stop, under Alberta’s OHS Code s. 191(7) and BC’s OHS Regulation s. 14.47(2). Standard 90° hook on a 25M bar: the answer is unchanged (a 12-diameter extension and an inside bend radius of about 3 bar diameters); the question no longer names a concrete strength or one standard, the explanation now cites two published Canadian tables, the Ontario Cast-in-Place Concrete Development Council’s reference guide to CSA A23.1-09 and Ontario MTO’s standard drawing SS112-1 (CHBDC-2019), and says to read hook geometry from the edition the drawings name, and statements about 180° hooks and development length, which had no source, were removed from its key concept.
Earlier updates for 420B (2)
- 2026-09-13 3 questions removed: one gave a single minimum safety factor for all rigging hardware, which does not hold for chain slings, and two more were removed after two independent reviews.
- 2026-09-13 5 explanations corrected, 1 duplicate question replaced, and 4 new questions added.
308A Sheet Metal Worker
Bank size: 120 before the audit, 120 after.
- 2026-10-30 1 explanation edited; the question, options and answer are unchanged. Welding a bracket to a used solvent drum: a line calling airing the drum a near miss and a practice that kills people now says airing the drum meets neither subsection, because it is not the thorough cleaning that subsection (1) requires and not the test by a qualified person that subsection (2) requires.
- 2026-10-29 3 questions changed; the questions and answers are unchanged. Travel restraint and fall arrest: the explanation said the hardware difference runs opposite to a common belief; it now says the hardware differs between the two. Resistance spot welding: a line calling each wrong answer a real confusion now reads “Reading the wrong answers”. Joining two duct sections end to end: the explanation said the exam expects the two families of duct connection kept apart, and that the names pocket lock and snap lock are often run together; both were removed, and with the second went the statement that a pocket lock is a transverse joint, here and in the key concept, because we have no source for it. Each wrong option named where it runs on the duct, which does not fit a joint between two sections, while the answer named none, so all four options are now just the connection names: Pittsburgh lock, button punch snap lock, grooved seam, and S and drive cleats.
Earlier updates for 308A (4)
- 2026-10-16 1 question replaced, and 1 question reworded with its explanation corrected. Grooved seam: the old question keyed the grooved seam as the spiral seam on round duct, but SMACNA’s 1995 edition also lists the grooved seam (pipelock), Type L-3, among the longitudinal seams for rectangular duct, so a second option was defensible. The new question in its place asks what applies to the spiral lockseams of factory-made spiral pipe when the seal class calls for longitudinal seams to be sealed: they are exempt from sealant, while the joints are still sealed, as SMACNA presents its current 4th edition; SMACNA’s 2021 technical bulletin gives the reason (sealant in a spiral seam can result in poor seam closure). Saddle branch connections: the answer is unchanged (a branch up to two thirds of the main diameter, with nothing projecting into the main); the question now names the clause it rests on, S3.4 of SMACNA’s HVAC Duct Construction Standards, 2nd edition (1995), and the explanation says to check the clause against the edition the project specification names. Two statements with no source were removed: that a projecting stub adds a loss the designer never allowed for, and that a branch close to the size of the main removes so much metal that no fastening restores it. Wording that called the sealing rule the one that catches people was removed.
- 2026-10-16 3 explanations corrected; questions, options and answers are unchanged. Welding screens: the explanation said a reflective screen can throw ultraviolet radiation onto workers standing behind it; reflected radiation goes back around the welding area, toward the welder, helpers and anyone at the open sides (CCOHS). Pittsburgh lock: SMACNA’s designation, Type L-1, is now given for the current 4th edition as well as the 1995 2nd edition, and two statements with no source, that sealant goes in the pocket when a tighter seal is needed and that it is the most widely used seam, were removed. Seal classes: the sealing table is Table 1-2 in the 1995 edition and Table 1-1 in the 2005 and current 4th editions, and details taken from the 1995 edition are now labelled with that edition. Wording that called one requirement the one people forget was removed.
- 2026-09-13 3 questions removed: one relied on a confined-space regulation that excludes the work settings the question described, and two had two defensible answers.
- 2026-09-13 5 explanations corrected, 1 duplicate question replaced, and 3 new questions added.
456A Welder
Bank size: 120 before the audit, 125 after.
- 2026-10-30 1 question changed; the question, options and answer are unchanged. GMAW solid wire polarity: the closing sentence of the explanation said a habit of assuming DCEP would eventually cost a welder a porous, poorly fused weld; it now says to check the polarity against the classification of each flux-cored wire rather than setting DCEP for every spool. The key concept now names T-4 and T-6 as examples of self-shielded wires that run on DCEP, where it said a few are classified that way.
- 2026-10-29 4 explanations edited; the questions, options and answers are unchanged. GMAW metal transfer modes: a “Red Seal key point” label now reads “Key point”. Pulsed GTAW background current: a clause calling this the most common way the point gets remembered backwards was removed. Flux-cored contact-tip-to-work distance: a line saying the wrong answers carry real misconceptions now reads “The other three answers are wrong”. Two-leg sling at 30 degrees (IHSA): the 500 lb option is now described as what splitting the load in half gives, where it was the answer a weak candidate reaches.
Earlier updates for 456A (6)
- 2026-10-28 1 explanation and its key concept corrected; the question, options and answer are unchanged. E7018: the explanation said the low-hydrogen coating contains potassium, for which we have no accepted source. The digit 8 is now explained as Hobart’s AWS classification chart gives it, the type of coating and current: an iron powder low-hydrogen coating, run on AC or DCEP. E6010, which a wrong option resembles, is now described in Hobart’s terms, a cellulose sodium electrode run on DCEP with a digging arc that penetrates deeply.
- 2026-10-19 2 explanations corrected; the questions, options and answers are unchanged. Carbon equivalent: the explanation said steel makers such as Algoma print the formula on their plate data sheets. The only sheet cited for it is Algoma’s AR225, so the explanation now says Algoma, for example, prints it on its AR225 plate data sheet, as the 456A exam tips page does. Welding symbols: the explanation said an electrode classification with its storage requirements belongs in the tail. No source puts storage requirements there, so it now says the classification can go in the tail as an optional note and that storage requirements are not part of the symbol.
- 2026-10-16 1 question reworded with its explanation corrected; the options and answer are unchanged. Welding symbols: the question asked what AWS welding symbols indicate and now asks what they mainly show, and the explanation now says the tail can carry optional notes such as the process or the electrode (Miller, Moran) but that those are supplementary to the type, size and location of the weld. A statement that CSA W59 adopts the AWS A2.4 symbols with conventions of its own, for which no source was found, was removed from this question, the reference is now given as AWS A2.4:2020, and the finishing letters as C, G, M, R and others. Two details near its end (the field-weld flag and the weld-all-around circle; where size, length and pitch are written) are now introduced as details to read carefully, and the label the explanation gave them was removed.
- 2026-10-16 1 question reworded and 5 explanations corrected. Low-hydrogen electrode storage: the answer gave one oven range, 120–150°C (250–300°F), but holding temperatures differ by product (Hobart gives 250–300°F for 7018 XLM and 220–350°F for 418); the question now says the package has been opened, and the answer is an oven held at the electrode maker’s temperature. E7018: a fixed 120–150°C storage temperature and a 4-hour limit out of the oven were replaced with the maker’s figures, a claim that E7018 is the go-to electrode for structural steel was removed, and the box marking is now quoted from a Hobart data sheet (AWS A5.1 E7018 H4R, AWS A5.1M E4918, CWB E4918-1-H4). Carbon equivalent: the key concept said preheat is required above a CE of 0.45; CE is one input, with thickness, hydrogen level, restraint and process, to the preheat the WPS or WPDS specifies. Welder position tests: the AWS D1.1 ranges are now taken from the CWB’s comparison of CSA W47.1 with D1.1 (2015 edition). Tungsten colours: the statement that the 2009 edition of AWS A5.12 moved ceriated tungsten from orange to grey, and the current types given for the thoriated and lanthanated electrodes, had no source; the colours now follow tungsten makers’ charts (grey for 2% ceriated, formerly orange). Intermittent welds: pitch is measured centre to centre, now cited to Miller’s guide to weld symbols. Wording that called an error common or classic, or said a change catches people out on the exam, was removed from three explanations.
- 2026-09-13 1 question removed: the two independent reviewers disagreed, and a third review found a second option defensible (a neutral flame for aluminum).
- 2026-09-13 6 explanations corrected, and 6 new questions added, which brings the bank to the length of the official exam so the full mock exam runs at real exam length.
Gasfitter (Class A)
Bank size: 112 before the audit, 110 after.
- 2026-11-23 1 explanation and key concept corrected and one wrong option shortened; the answer is unchanged. Flame rod (flame rectification) check: the explanation gave a 1–2 second shut-off time and the key concept said to clean a rod with fine steel wool, neither of which we could source. The timing is gone, and the key concept now says to clean the rod with the material the appliance maker specifies.
- 2026-10-30 2 questions changed; the questions, options and answers are unchanged. Buried metallic gas piping: this entry supersedes the 2026-10-29 entry below, which says the explanation still says cathodic protection is not an automatic requirement. That sentence was replaced, because British Columbia adds a requirement regardless of pressure (Clause 6.15.15, added to CSA B149.1-20 by its Gas Safety Regulation, consolidation current to October 27, 2026). The explanation and key concept now say whether cathodic protection is required is set by the code edition and provincial amendments in force, and give the British Columbia clause and its exceptions as the example. The list of accepted coating methods, which we had no source for, was also removed: the explanation now says the pipe goes in with a coating applied at the factory or with a wrap, and it attributes the wording wrapped and/or factory-coated piping to the informative Annex O of CSA B149.1:25. Copper tubing in a propane system: a sentence calling the idea that propane or its odourant rules copper out shop lore was removed, the key concept now says Clause 6.2.5 allows either phase of propane with no condition about odourant, and the Saskatchewan example now cites the Saskatchewan Interpretations for CSA B149.1:25 (TSASK, effective April 1, 2026).
Earlier updates for Gasfitter (5)
- 2026-10-29 2 explanations edited; the questions, options and answers are unchanged. Buried metallic gas piping: a clause calling it a common misreading to treat cathodic protection as automatic on every buried steel line was removed; the explanation still says it is not an automatic requirement. Tubing in a hollow stud wall: the 6 ft (2 m) figure is no longer described as one a candidate may recall; the explanation still says it is the support spacing, not a protection trigger.
- 2026-10-16 1 question reworded with its explanation corrected. Category I venting: the answer now reads Type B double-wall vent or a lined masonry chimney, where it read a listed masonry chimney: the National Building Code (Article 9.21.3.1., 2020 and 2025) requires every masonry or concrete chimney to have a lining, and Saskatchewan’s interpretations of B149.1:25 call for an approved metal liner when a masonry chimney is connected to a gas appliance. The three wrong options all began with “Category I” and the answer did not, so it could be picked on its form; they are now other venting choices (plastic vent certified to ULC S636, polypropylene vent, and a flue shared with a wood fireplace or wood stove), ruled out from IPEX’s and DuraVent’s listings and NBC Article 9.21.2.1. Category I is now defined as CSA B149.1 defines it, a non-positive vent static pressure and a flue loss of 17% or more, in place of flue gas above its dew point.
- 2026-10-16 2 questions reworded and 2 explanations corrected. Vent categories: only the answer used the word “Categories”, so it could be picked on wording alone. All four options now read “Categories I–IV, by …”; the answer now reads vent pressure and flue loss, where it read vent pressure and flue temperature, and the explanation gives CSA B149.1’s basis, non-positive or positive vent static pressure and a flue loss of at least 17% or less than 17%, in place of flue temperature against dew point. Pipe sizing: the question now names the capacity tables and sizing method in Annex A of CSA B149.1, and the explanation says that Saskatchewan’s Actual Length/Actual Load method enters the tables differently and is not the method asked about. A statement that 14 in. WC may appear as a regulator lockup reading at zero flow had no source and was removed, and wording that called one answer the classic near miss was removed.
- 2026-09-13 2 questions removed after two independent reviews.
- 2026-09-13 8 explanations corrected.